Jess Albino CF – Breakout Session June 17, 2008 1 Facility Advisory Committee LINAC Coherent Light Source Project Conventional.

Slides:



Advertisements
Similar presentations
Project Planning: Assembling a Mortenson “Integrated Work Plan”
Advertisements

1 BROOKHAVEN SCIENCE ASSOCIATES Procurement Dave Paveglio, Contract Administrator NSLS-II PAC Meeting May 25, 2007.
David Saenz FAC CF April 20, 06 Meeting of the LCLS Facilities Advisory Committee LCLS Conventional Facilities D. Saenz.
Richard M. Boyce FAC Review – Accelerator Installation October 29-31, Installation – Accelerator Systems Installation Planning.
David Saenz CM/GC April 8, 2005 CM/GC Overview CM/GC Plan & Status Systems Description Cost Estimate Construction Schedule.
1 John Arthur 1 FEH Status CXI Review June 3, 2009 FEH Layout, Status John Arthur – LCLS Expt’l Facilities Div June 3, 2009.
Jess Albino Session 5 Conventional November 11, Facility Advisory Committee LINAC Coherent Light Source Project.
Michael Scharfenstein FAC June 17, ES&H Status of Construction and Technical System Installations Michael Scharfenstein.
Richard M. Bionta XTOD October 12, 2004 UCRL-PRES-XXXXX X Ray Transport, Optics, and Diagnostics, Overview Facility Advisory Committee.
John N. Galayda LCLS FAC 20 April Linac Coherent Light Source Overview and Charge Facility Advisory Committee John.
David Saenz Facility Advisory October 30, 2007 CONVENTIONAL FACILITES MANAGEMENT.
1 David Saenz 1 Hutch Construction in FEH June 08, 2009 Hutch Construction in Far Experimental Hall David Saenz – Project Manager.
Richard Hislop FAC April 20-21, 2006 CONSTRUCTION SAFETY Richard Hislop LCLS Construction Safety Coordinator.
Jess Albino CF Breakout April 16, CONVENTIONAL FACILITIES Project Team CF Changes Electrical Engineer - done Mechanical.
Mark Reichanadter LCLS FAC October 29-31, 2007 Report to the LCLS Facilities Advisory Committee Project Management Project.
David Saenz Far Experimental Hall - June 17, Far Experimental Hall - Hutches Scope Budget Schedule.
Mark Reichanadter LCLS FAC April 20-21, 2006 Meeting of the LCLS Facilities Advisory Committee LCLS Project Management M.
Jess Albino / David Saenz / Facility Advisory Committee October 30, 2007 FACILITY.
Jess Albino FAC CF April 16, 2007 Meeting of the LCLS Facilities Advisory Committee LCLS Conventional Facilities Jess.
1 Jess Albino 1 Conventional Facilities Status FAC Review – Breakout Session CONVENTIONAL FACILITIES STATUS Jess Albino – Associate.
David Saenz FAC CF Oct 12-13, 2004 Conventional Facilities Overview SLAC Site Plan Systems Description Construction Schedule.
Jess Albino Facility Advisory October 29, 2007 FACILITY ADVISORY COMMITTEE PLENARY CONVENTIONAL FACILITIES UPDATE October.
David Saenz CF Oct 30, CF MEP Commissioning.
M. Reichanadter LCLS Project June 2008 FAC Meeting Report to the LCLS Facilities Advisory Committee Project Management.
Richard M. Boyce FAC October 29-31, Installation Planning Integration process – IMT update Installation Planning &
Jess Albino Facility Advisory October 30, 2007 FACILITY ADVISORY COMMITTEE BREAKOUT SESSION 5 TURNER CONTRACT OVERVIEW.
John N. Galayda LCLS FAC October Linac Coherent Light Source Overview and Charge Facility Advisory Committee.
Jess Albino Session 5 Conventional November 11, Facility Advisory Committee LINAC Coherent Light Source Project.
Jo Beth Folger FAC - CF Breakout – Sector April 8, Sector 20 Project Overview Sector 20 Site Plan Description Schedule.
Bob Law FAC Oct 24, Sector 20 Project Overview Sector 20 Site Plan Description Organizational Chart Schedule Cost.
David Saenz FAC November 11, 2008 SLAC National Accelerator Laboratory 1 Far Experimental Hutches David Saenz Project Manager.
Mike Scharfenstein FAC Review - November 11, 2008 SLAC National Accelerator Laboratory 1 Environment Safety & Health Status.
Mike Scharfenstein CF Breakout - 12 November 2008 SLAC National Accelerator Laboratory 1 ES&H Status of Construction and Technical.
M. Scharfenstein - ES&H Coordinator 8 June 2009
1 BROOKHAVEN SCIENCE ASSOCIATES LOB - Ring Building Construction Coordination Michael P. Bromfield Construction Engineer NSLS-II Conventional Facilities.
1 BROOKHAVEN SCIENCE ASSOCIATES Construction Management Status Steve Sawch Assistant Director for Construction Management NSLS-II Conventional Facilities.
1 BROOKHAVEN SCIENCE ASSOCIATES Ring Building Construction Status Steve Sawch Assistant Director for Construction Management NSLS-II Conventional Facilities.
NCSX Management Overview Hutch Neilson, NCSX Project Manager NCSX Conceptual Design Review Princeton, NJ May 23, 2002.
1 BROOKHAVEN SCIENCE ASSOCIATES Ring Building Construction Status Michael P. Bromfield Construction Engineer NSLS II Conventional Facilities Advisory Committee.
M. Reichanadter LCLS Project November 2008 FAC Meeting Slac National Accelerator Laboratory Report to the LCLS.
1 BROOKHAVEN SCIENCE ASSOCIATES Presentation to PAC R. Casey NSLS-II ESH Program Status May 25, 2007.
1 Zoe Van Hoover 1 User Safety: Commissioning and Early Experiments NEH ARR User Safety: LCLS NEH Commissioning and Early Experiments.
David Saenz Readiness for Oct 12, 2006 # Meeting of the LCLS Facilities Advisory Committee LCLS Conventional Facilities.
John N. Galayda LCLS Accelerator Readiness December 2, LCLS Overview December 2, 2008 Project Construction Status.
Mark Reichanadter LCLS October 9-11, 2007 LCLS BCR Overview and EIR LOIs Project Progress / Status Revised Project Baseline.
David Saenz EIR Review Oct 9-11, Conventional Facilities (CF) WBS 1.9 ETC and Methodology David Saenz CF Systems Manager.
CF Organization & Schedule
Meeting of the LCLS Facilities Advisory Committee
Far Experimental Hall Hutches Civil Construction
CONVENTIONAL FACILITIES STATUS
M. Scharfenstein - ES&H Coordinator 14 May 2009
Electron Beam Systems ETC and Methodology
Department Of Energy Review LINAC Coherent Light Source Project
Conventional Facilities (WBS 1
Details supporting the increase
Far Experimental Hall - Hutches
Project Status Review May 13-15, 2008.
Conventional Facilities WBS 1.9
Integrated Safety and Environmental Management
Michael Scharfenstein Project ES&H Coordinator
Conventional Facilities Status
CONVENTIONAL FACILITIES
Installation Status & Operational Readiness Process
Richard Hislop Construction Safety Coordinator
Department Of Energy Review Linac Coherent Light Source Project
Conventional Facilities
Phase 1 Statement of Work Preconstruction “Plan The Work”
CF Scope, Management & Organization
CMGC Overview SLAC Site Plan Systems Description Construction Schedule
PROJECT SAFETY Richard Hislop.
Presentation transcript:

Jess Albino CF – Breakout Session June 17, Facility Advisory Committee LINAC Coherent Light Source Project Conventional Facilities Overview and Status Scope, Schedule, and Budget J. Albino

Jess Albino CF – Breakout Session June 17, Exec. CF Committee R. Claus, J. Jobe B. Miller M. Reichanadter Turner Bill Jangraw Project Executive CF Construction Organization

Jess Albino CF – Breakout Session June 17, Beneficial Occupancy Dates Front End Enclosure JUL08 Central Utility Plant JUL08 Undulator Hall JUL08 Near Experimental Hall JUL08 Beam Dump JUL08 Beam TransferJ UL08 Xray/Diagnostics SEP08 Far Experimental Hall SEP08

Jess Albino CF – Breakout Session June 17, CONVENTIONAL FACILITIES ~90% Scope completed to date: Beneficial Occupancy Beam Transport Hall West (BTHwest) Co-occupancy Beam Transport Hall (BTH) to Near Experimental Hall (NEH) Beam Transport Hall West upgrades Natural Gas Line New service line from Pacific Gas & Electric Substation S522 Sector 20 (LCLS Injector Facility) Magnet Measurement Facility Beam Transport Hall Switchboard Sector AC Power Upgrade

Jess Albino CF – Breakout Session June 17, Turner Construction Contract

Jess Albino CF – Breakout Session June 17, BTH Headhouse looking west

Jess Albino CF – Breakout Session June 17, BTH Headhouse looking west

Jess Albino CF – Breakout Session June 17, BTH looking east

Jess Albino CF – Breakout Session June 17, BTH looking east into Undulator Hall UNDULATOR MAGNET STANDS

Jess Albino CF – Breakout Session June 17, Electron Beam Dump

Jess Albino CF – Breakout Session June 17, Near Experimental Hall Subbasement looking west

Jess Albino CF – Breakout Session June 17, Finishing the Final Floor Slab in X-ray Tunnel

Jess Albino CF – Breakout Session June 17, Far Experimental Hall south rib Installing re-bar in the Far Experimental Hall Far Experimental Hall Structural Shell

Jess Albino CF – Breakout Session June 17, Far Experimental Hall west wall

Jess Albino CF – Breakout Session June 17, Construction Adit Backfilling

Jess Albino CF – Breakout Session June 17, Backfill operation over Beam Dump and FEE

Jess Albino CF – Breakout Session June 17, BTH looking east

Jess Albino CF – Breakout Session June 17, Surface Restoration in Research Yard

Jess Albino CF – Breakout Session June 17, Next 6 Months CONSTRUCTION Complete Site Grading Complete Mechanical / Electrical / Plumbing installations Complete Surface Restoration (curb and gutters, site drainage, etc.) Complete Punch Lists Turner / Conventional Facilities Commissioning Close-out Trade Contracts Close-out Turner Contract (before December 2008)

Jess Albino CF – Breakout Session June 17, Next 6 Months (cont.) ADMINISTRATION / DESIGN Turner Claim CF Staff Assignments Design of Far Hall Hutches Conceptual Design / prelim. cost estimate – Spring/Summer 08 Final Design / cost estimate – Fall/Winter 08 Construction – Complete by Nov 09 Design of Space Renovation for Offices Design start in 2 nd Quarter of Fiscal Year Construction complete 3 rd Quarter of Fiscal Year 2010

Jess Albino CF – Breakout Session June 17, Schedule Delays Waterline breaks Lab Operations Undulator Hall slab Saturated Soils at storm drain NEH waterproofing (delayed other trades) Late delivery of elevator for NEH Productivity issues with electrical trade contractor; misc. steel Resolution of trade contract scope of work (AIC Painting: Seismic bracing) Weather Contingency Winter 2006: below average (good) Winter 2007: about average (minor impact) 100-year storm in January 2008 Schedule Mitigation Re-sequencing of activities Additional work force for electrical installations System modifications to allow work to proceed (water valves)

Jess Albino CF – Breakout Session June 17, Conventional Facilities Level 3 Milestones: (6 month lookahead) Conventional FacilitiesDate Near Experimental Hall Co-Occupancy21-Apr-2008 CUP S522 Substation Beneficial Occupancy30-Apr-2008 Undulator Facility Beneficial Occupancy20-May-2008 Near Experimental Hall Beneficial Occupancy20-May-2008 Front End Enclosure Beneficial Occupancy20-May-2008 Beam Dump Beneficial Occupancy20-May-2008 Central Utility Plant Beneficial Occupancy20-May-2008 Beam Transport Hall Beneficial Occupancy20-May-2008 Far Experimental Hall Co-Occupancy22-Jul-2008 X-Ray Transport Co-Occupancy22-Jul-2008 Far Experimental Hall Beneficial Occupancy22-Aug-2008 X-Ray Transport Beneficial Occupancy22-Aug-2008

Jess Albino CF – Breakout Session June 17, Conventional Facilities Performance TECOPC % CompleteSPICPI% CompleteSPICPI Conventional Facilities79.9% %

Jess Albino CF – Breakout Session June 17, Cost to Go at WBS Level 3 (as of APR08) 1.09 Conventional Facilities $M, Burdened, Escalated TEC Estimate to Complete Contingency %Contingency Total Estimated Cost (TEC) % System Management & Integration % Title 1 & Title 2 Conventional Facilities Construction-T3 Conventional Facilities % – includes FEH hutches and space renovation construction estimates

Jess Albino CF – Breakout Session June 17, Integrated Safety Management Define Work Trade Contractor Task Plan Analyze Hazards Job Safety Analysis – reviewed and approved by Safety Pre-Task Meeting – conducted by foreman/crew members Develop Controls Personal Protective Equipment Special Tools / Training Safety Oversight Perform the Work Zero Accidents Stop and Evaluate Changes in the Work or Controls Work within Pre-task plan Obtain Feedback and Improve Safe Performance Observations Monthly Safety Meetings Safety Recognition Programs Elicit feedback from the crews through direct communication

Jess Albino CF – Breakout Session June 17, Total Project Hours 1.73 M Hours worked LCLS Collaboration 1.27 M Hours worked 2 DART Incidents None in past 24 months LCLS Sub-Contractors 108 K Hours worked No Injuries TCCo 348 K Hours Worked 8 DART Incidents DART Rate Note: Injury rates based on 200 K hours (100 man years) of effort. PROJECT SAFETY EXPERIENCE 29 March 2008

Jess Albino CF – Breakout Session June 17, CONVENTIONAL FACILITIES Project (Turner) Safety Performance History LCLS Prepares for Field Work to begin Safety Record as part of selection process Site Safety and Health Plan Driving home the message Result: Procedural Violations Actions Stand Down of Construction Activities Review of Approval Process for field work Review of Project safety statistics – Analyze Hazards / Define Controls inadequate Check/correction of existing documentation Turner Construction “in full swing” Data points indicate rising trends (near misses) Paperwork trivialized by CM/GC and trade contractors Result: Injury to Concrete Pump Operator Actions: Stand Down of Construction Activities CM/GC and trade Personnel changes / fines levied Letter to Turner Corporate Joint Safety Stewardship Committee established

Jess Albino CF – Breakout Session June 17, CONVENTIONAL FACILITIES Safety Performance (continued) Turner Construction “over the hump” Injury rate increases (DART rate above national average) Turner personnel and trade personnel changes / fines levied Tunnel contractor begins to de-mobilize Result: Serious injuries (shoulder and hand) Actions: Work Activity stopped. Trade personnel changes made Safety statistics reviewed – Perform the Work inadequate Letter to Turner Corporate Plan for joint observation and monitoring of the work planning and execution prepared. Review of JSA / Pre-task meeting notes Attendance at each Pre-task meeting (Turner augmented by CF UTRs) Monitoring Specific trade contractors or activities for safe work practices We own Safety. It is our obligation to complete the project injury free!

Jess Albino CF – Breakout Session June 17, Issues (and Mitigation) Site Security and Safety Safety Statistics Re-emphasis on Safe Work November 20, 2007 Stand-down Safety Stewardship Additional Staff defined and constantly evaluated Construction Delays Site Conditions – Saturated soils Waterproofing Cut-and-cover structures Above average precipitation

Jess Albino CF – Breakout Session June 17, Issues (and Mitigation) cont. Technical Systems Construction Tolerances Undulator Hall tunnel invert slab Clearance zones for follow-on work Integration management and site walks Disputes and Claims Known Claims Request for Arbitration = $4.5M Request for Equitable Adjustment = $ 1.5M Total / Percent of May08 EAC = $6 / $88 = 6.8%

Jess Albino CF – Breakout Session June 17, Summary Good Progress - Beneficial Occupancy of BTH to NEH is imminent. Staff replenished after key personnel left the project. Emphasis on cost control - continue to critically review change requests Interface with DOE, SLAC, Tech. Systems, CM/GC to get buy in on procedures Increased visibility of Line Management show promising return with respect to safety. Co-occupancy successful and relatively seamless.

Jess Albino CF – Breakout Session June 17, End of presentation