How to use a Dumpy Level Example 1

Slides:



Advertisements
Similar presentations
Construction Surveys
Advertisements

Ways of ensuring something is level Leveling Tube A transparent tube that is filled with water. The water at the two ends will always be level. Spirit.
CALCULATOR MANIPULATION. Due to the differences in calculators you will have to be able to use your own effectively.
Levelling Checks.
Precise Digital Leveling Section 7 Wrap-up and Bench Mark Resets.
Review Homework.
Surveying I. Lecture 2..
Profile Leveling.
S.H.H.S Building Construction
Energy & Environment. What are these lines called and what are they used for? If this map has a scale of 1:25,000 what does this mean? They are called.
Indiana LICA Contractor Certification Training Workshop 2008 Basic Surveying Concepts.
Review Homework.
Principles of Surveying
CHAPTER 3 LEVELING.
Differential Leveling
Differential Leveling
Lesson Applying Profiling Leveling Techniques. Interest Approach Discuss with the students why producers sometimes put drainage ditches in their fields.
Rounding Jeopardy $10 $20 $30 $40 $50 $20 $30 $40 $50 $30 $20 $40 $50 $20 $30 $40 $50 $20 $30 $40 $50 Round to the Nearest 100 Round to the Nearest 1,000.
What is “Leveling” Levelling is the process by which differences in height between two or more points can be determined. Its purpose may be to provide.
THE SHAPE OF THE GROUND RELIEF is a term used to describe the shape of the ground. Relief has two elements:1. HEIGHT 2. SHAPE HEIGHTS can be represented.
Chapter (5) Leveling Introduction:
Dumpy Level Surveying Energy & Environment.
Levelling Applications:
GUJARAT TECHNOLOGICAL UNIVERSITY BIRLA VISWAKARMA MAHAVIDHYALAYA (ENGINEERING COLLEGE) VALLABH VIDYANAGAR SUBJECT: ELEMENTS OF CIVIL ENGINEERING (CODE )
Find the equation of the line that has... A B C D E F
Using the Dumpy & Recording Levels
Chap 7 – Differential Leveling
Do we have enough food?. This problem is only difficult to answer because it has a lot of parts. Finding the answer just requires subtracting and comparing.
Lesson Applying Differential Leveling Techniques.
1 Applications Stream cross sections Highways Canals Sewers Water mains Sidewalks Retaining walls Fences Application of Differential Leveling Introduction.
3.2: Slope How steep?. Slope is the measure of steepness. Some hillsides are not steep. They are easy to climb. They have a small slope.
How to Navigate a Set of Field Notes….. First the Jargon… Benchmark Backsight Foresight Height of Instrument Elevation Turning Point Station.
How to: Some Basic Principles for Leveling
Solve for the missing side length.. A forest ranger spots a fire from the top of a look-out tower. The tower is 160 feet tall and the angle of depression.
Surveying 1 / Dr. Najeh Tamim
Construction Surveys. List of Figures Stages and Measurements of CS Design stages: topographic Surveying, and site maps Construction stage: Setting-out.
Find the difference in height between the benchmark and the top of the slope Top of Slope ? Divide hill into 3 spots to make easier Otherwise too far to.
Chapter (5) Leveling Introduction:
Stadia Reduction.
DIFFERENTIAL – PROFILE LEVELING
Rounding Jeopardy.
Profile Leveling.
Visit for more Learning Resources
LEVELLING AND CONTOURING BY:- ANAND R. JIBHAKATE CIVIL ENGINEER 1 1.
C.K PITHAWALLA COLLEGE OF ENGINEERING AND TECHNOLOGY
Levelling – Height Measurement
Unit: Surveying Lesson: Differential Leveling
Review Homework.
Engineering Surveying
Leveling Intro to Leveling.
Right Triangle Trigonometry
Solving Two-Step Equations
Upscaling Basic Sanitation for the Urban Poor (UBSUP)
Find: Average Slope AD [%]
As the water loses elevation from the high end of the pipe to the low end, it gains velocity. To find the exact value of any parameter, we apply the Bernoulli.
Leveling By : Parveen Kumar.
Leveling.
Leveling.
Leveling.
Leveling.
Leveling.
Leveling.
Differential Leveling
Leveling.
LEVELING.
What's Missing? The game that challenges you to see if you can spot which punctuation mark has GONE!
Note 8: Applications A surveying team are trying to find the height of a hill. They take a ‘sight’ on the top of the hill and find that the angle of.
Stream Crossing Bootcamp
Lecture 7.
Review Homework.
Presentation transcript:

How to use a Dumpy Level Example 1 Find the difference in height between the benchmark and the top of the slope Top of Slope ? Divide hill into 3 spots to make easier Otherwise too far to see or leveling staff not long enough

How to use a Dumpy Level Example 1 9mAOD Back sight

How to use a Dumpy Level Example 1 Rotate Dumpy round Back sight 9mAOD 2m Foresight 2mAOD Move Level to new position

How to use a Dumpy Level Example 1 Move Dumpy to new position 6mAOD Back sight 9mAOD Back sight 2mAOD Foresight

How to use a Dumpy Level Example 1 Rotate Dumpy round to new position 6mAOD Back sight 9mAOD Back sight 2mAOD Foresight Move Level to new position

How to use a Dumpy Level Example 1 1mAOD Foresight 6mAOD Back sight 9mAOD Back sight 2mAOD Foresight

How to use a Dumpy Level Example 1 1mAOD Foresight 6mAOD Back sight Level of dumpy = 926m Level of dumpy = 922m 9mAOD Back sight 2mAOD Foresight 6m 6m + 920m 1m 2m 9m 913m + 9m   Ground Level Backsight (from Dumpy Level) Height of instrument (Ground Level + Backsight from Dumpy Level) Foresight (from Dumpy Level) Height of new point (Height of instrument-foresight) Bench mark 913 9 922 2 920 6 926 1 925

How to use a Dumpy Level Example 1 ?   Ground Level Backsight (from Dumpy Level) Height of instrument (Ground Level + Backsight from Dumpy Level) Foresight (from Dumpy Level) Height of new point (Height of instrument-foresight) Bench mark 913 9 922 2 920 6 926 1 925 So the difference in height is 925m-913m=12m

Example 2 I want to construct a water pipe on the hill by Vigyan Ashram To find the pressure that will result from the pipe I need to know the height difference between point A and point D A= 875mAOD B C D

Example 2 A= 875mAOD B C D Ground Level Backsight (from Dumpy Level)   Ground Level Backsight (from Dumpy Level) Height of instrument (Ground Level + Backsight from Dumpy Level) Foresight (from Dumpy Level) Height of new point (Height of instrument-foresight) Benchmark A=875 B= C= D= B C D A= 875mAOD

Example 2 4m 9m A= 875mAOD 11m 1m B B= 870mAOD 2m 12m C C= 860mAOD D Level of dumpy=879mAOD 4m 9m A= 875mAOD Level of dumpy=871mAOD 11m 1m B B= 870mAOD Level of dumpy=862mAOD 2m 12m C C= 860mAOD D D= 850mAOD

Example 2 Ground Level Backsight (from Dumpy Level)   Ground Level Backsight (from Dumpy Level) Height of instrument (Ground Level + Backsight from Dumpy Level) Foresight (from Dumpy Level) Height of new point (Height of instrument-foresight) Benchmark A=875 4 879 9 B= 879-9=870 B= 870 1 871 11 C= 871-11=860 C= 860 2 862 12 D= 862-12= 850

Example 2 Once you have gone down the hill,   Ground Level Backsight (from Dumpy Level) Height of instrument (Ground Level + Backsight from Dumpy Level) Foresight (from Dumpy Level) Height of new point (Height of instrument-foresight) Benchmark A=875 4 879 9 B= 879-9=870 B= 870 1 871 11 C= 871-11=860 C= 860 2 862 12 D= 862-12= 850 Once you have gone down the hill, check you answer by coming back up the hill   Ground Level Backsight (from Dumpy Level) Height of instrument (Ground Level + Backsight from Dumpy Level) Foresight (from Dumpy Level) Height of new point (Height of instrument-foresight) D=850 C= B= A=

Example 2 4m 9m A= 875mAOD 1m B 11m B= 870mAOD 2m C 12m C= 860mAOD D Level of dumpy=879mAOD 4m 9m Level of dumpy=871mAOD A= 875mAOD 1m 11m B Level of dumpy=862mAOD B= 870mAOD 2m 12m C C= 860mAOD D D= 850mAOD

Example 2 Once you have gone down the hill,   Ground Level Backsight (from Dumpy Level) Height of instrument (Ground Level + Backsight from Dumpy Level) Foresight (from Dumpy Level) Height of new point (Height of instrument-foresight) Benchmark A=875 4 879 9 B= 879-9=870 B= 870 1 871 11 C= 871-11=860 C= 860 2 862 12 D= 862-12= 850 Once you have gone down the hill, check you answer by coming back up the hill   Ground Level Backsight (from Dumpy Level) Height of instrument (Ground Level + Backsight from Dumpy Level) Foresight (from Dumpy Level) Height of new point (Height of instrument-foresight) D=850 12 862 2 C=862-2=860 C=860 11 871 1 B=871-1=870 B=870 9 879 4 A=879-4=875

Example 2 So what was the change in height? Change in height= 25m A= 875mAOD B C D A= 850mAOD

Summary Questions What is a Dumpy Level Used for? What 2 things can you use to check if things are level? How does a spirit level work? One you have done a backsight reading what would you do next with a dumpy level?