Project Scheduling: Networks, Duration estimation, and Critical Path
Project Scheduling Terms Successors Predecessors Network diagram Serial activities Concurrent activities E D C B A F
Project Scheduling Terms Merge activities Burst activities Node Path Critical Path E D C B A F Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall
Network Diagrams Help schedule resources Show interdependence Show start & finish dates Facilitate communication Determine project completion Identify critical activities Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall
AOA vs. AON The same mini-project is shown with activities on arrow… D B F …and activities on node. C E D B F
Node and activity labels in AoA diagrams (NOT following the textbook) Deadline Activity identifier Duration 1 2 EET LET Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall
Node Labels in AoN diagrams (NOT completely following the textbook) Free float Early Start Total Float Early Finish Activity Descriptor Late Start Activity Duration Late Finish
Duration Estimation Methods Past experience Expert opinion Mathematical derivation – Beta distribution Most likely (m) Most pessimistic (b) Most optimistic (a)
Beta distribution Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall
Sketch the network described in the table. Determine the expected duration and variance of each activity. Task Predecessor a m b A -- 7 8 15 B 13 16 19 C 14 18 22 D B, C 12 E 1 4 F 6 10 G F, E 11 TE s2 9 1.8 16 1.0 18 14 0.4 5 4.0 10 14.3 1.4 Task a b c Mean Variance Z 7 8 15 9.00 1.78 Y 13 16 19 16.00 1.00 X 14 18 22 18.00 1.78 W 12 14 16 14.00 0.44 V 1 4 13 5.00 4.00 T 6 8 14 8.67 1.78 S 11 14 19 14.33 1.78 Task Early Start Early Finish Late Start Late Finish Slack Z 0 9 0 9 0 Y 9 25 11 27 2 X 9 27 9 27 0 W 27 41 27 41 0 V 41 46 44.67 49.67 3.67 T 41 49.67 41 49.67 0 S 49.67 64 49.67 64 0 Project Length 64 Project Variance 7.555556 Project Std.dev 2.748737
Solution with AoN diagram 2 2 b 9 25 2 11 27 16 e 41 46 5 51 a 9 d 27 41 14 g 51 65 14 c 9 27 18 f 41 51 10 Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall
Constructing the Critical Path Forward pass – an additive move through the network from start to finish Backward pass – a subtractive move through the network from finish to start Critical path – the longest path from end to end which determines the shortest project length Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall
Rules for Forward/Backward Pass Forward Pass Rules (ES & EF) ES + Duration = EF EF of predecessor = ES of successor Largest preceding EF at a merge point becomes EF for successor Backward Pass Rules (LS & LF) LF – Duration = LS LS of successor = LF of predecessor Smallest succeeding LS at a burst point becomes LF for predecessor
Sketch the network described in the table. Task Predecessor Time A -- 4 B 9 C 11 D 5 E 3 F 7 G D, F H E, G 2 K 1 Sketch the network described in the table. Determine the ES, LS, EF, LF, and total float of each activity Task ES EF LS LF Slack A 0 4 0 4 0 B 4 13 8 17 4 C 4 15 4 15 0 D 13 18 17 22 4 E 13 16 22 25 9 F 15 22 15 22 0 G 22 25 22 25 0 H 25 27 25 27 0 K 27 28 27 28 0
Laddering Activities Project ABC can be completed more efficiently if subtasks are used ABC=18 days A(3) B(6) C(9) A1(1) A2(1) A3(1) B1(2) B2(2) B3(2) C1(3) C2(3) C3(3) Laddered ABC=12 days
Useful with a complex project or one that has a shared budget Hammock Activities Used as summaries for subsets of activities 0 A 5 0 5 5 B 15 5 10 15 15 C 18 15 3 18 0 Hammock 18 0 18 18 Useful with a complex project or one that has a shared budget
Reducing the Critical Path Eliminate tasks on the CP Convert serial paths to parallel when possible Overlap sequential tasks Shorten the duration on critical path tasks Shorten early tasks longest tasks easiest tasks tasks that cost the least to speed up Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall
Optional HW Create the AoA & AoN networks of your project using the symbols of this class. Prize: 15% Task list with cost estimation: +5% Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall
Thanks for your attention