Continuous Optimisation JISC Improved Sustainability Across Estates Through The Use of ICT Continuous Optimisation – an Imperial College estates initiative.

Slides:



Advertisements
Similar presentations
Using Ground Source Heat Pump The Avenue Centre.
Advertisements

Load Management System with Intermittent Power on the Grid Ruth Kemsley CEng MIMechE MIEE Econnect Ventures Ltd.
Energy Conservation Energy Management.
Energy Management Practices: Rolling Mills 1. Contents Introduction Energy Intensive Processes & Reduction in Energy Expenditure through Innovative Practices.
Energy Efficiency Strategy. THE ENERGY WHITE PAPER Energy White Paper sets out four key goals for energy policy to: Cut the UK’s carbon dioxide emission.
Intelligent Air Handling Units AADTECH INDIA PRIVATE LIMITED
Prior activities of FEWE Under the bilateral and multilateral co-operation, several projects to support the rational energy use in different sectors.
OPPORTUNITIES FOR BUSINESSES TO DIRECTLY IMPROVE THE BOTTOM LINE THROUGH ENERGY EFFICIENCY 3 rd May 2010 Kees Brinkman Managing Director.
L2 Compliance: Project Darwin
King Fahd University of Petroleum and Minerals Mechanical Engineering Department Presented by Mohammad A. Al-Muaigel /10/2004 National Energy.
The Value of DOD Installation Energy Management Control Systems (EMCS) and Command Centers for Improved Operations and Increased Energy Efficiency Moderator:
Facility Energy Efficiency Switch it Off - Turn it Down - Reuse it Jon Barker CEng MEI Chartered Energy Engineer Enerjon
Variable Frequency Drives VFD Basics
Electrical Consumption Pattern of an Academic Building Dr Mehreen Gul EAUC November 2014.
Implementing the SET-plan proposed Energy Efficiency Directive The proposed Directive establishes a common framework for promoting energy efficiency in.
Lab Energy Management Big Ten Mechanical & Energy Conference October
Energy Efficient Operations: Giving facility operators the tools to optimize building performance The B3 Energy Efficient Operations Manual Garrett Mosiman.
Chemistry Teaching Laboratory Fume Cupboard Refurbishment – University of Leeds Bob DouglassEnergy Officer.
Carbon Saving Initiatives Update 2009 / 2010 FACILITIES MANAGEMENT ENVIRONMENTAL & ENERGY IMPROVEMENTS.
Imperial College Carbon Management Plan The Carbon Management Plan Imperial College Facilities Management June 2010.
Energy Management with the use of an Intelligent Building Management System.
Carbon Management Steering Board 7 th October 2011 Filter Survey - Update CARBON MANAGEMENT BOARD – October 2011.
Simon Bunn – Derceto Inc
SUSTAINABLE ENERGY REGULATION AND POLICY-MAKING FOR AFRICA Module 14 Energy Efficiency Module 14: DEMAND-SIDE MANAGEMENT.
1 Kevin Cope Imperial College London Head of Building Operations Carbon Management Plans - achievements, maintenance and the future.
Renewable Technologies Available in Ireland Paul Kane.
Water policy reform – moving ahead Presentation for the Water Policy in the MDB Workshop 22 October 2010 Will Fargher, General Manager Water Markets and.
© 2005 by West Pharmaceutical Services, Lionville, PA. All rights reserved. This material is protected by copyright. No part of it may be reproduced, stored.
SUSTAINABLE ENERGY REGULATION AND POLICY-MAKING FOR AFRICA Module 13 Energy Efficiency Module 13: SUPPLY-SIDE MANAGEMENT.
DISTRIBUTION STATEMENT A: Approved for public release; distribution unlimited. NSWCDD-PR Will Clark Robert Snodgrass, PE Naval Surface Warfare.
1 Air Source Heat Pumps Potential Changes in the RTF’s Specifications & Savings Estimates and Their Impact on C&R Discount Program Credits.
University of Cambridge Dept of Chemistry – Lensfield Road Energy Audit & Opportunities Malcolm Tait of KJ Tait Engineers Introduction The Utility Challenge.
© ABB Engineering Services Energy Responding to the Challenge of Climate Change.
Presented by the Industrial Energy Efficiency Project.
© OECD/IEA – 2011 Key Insights from IEA Indicator Analysis ENERGY INDICATORS Efficient Power Generation 2011 Roundtable 4: Efficient use of energy in the.
Smart Buildings Srirangarajan Kadaba National Manager – Energy Edge Buildings Business Schneider Electric 21June 2010.
Industry Handbook Energy Efficiency in Industry Handbook Teacher Training The sole responsibility for the content of this presentation lies with the authors.
Data centre air management Case studies Sophia Flucker.
Cutting the Corporate Energy Bill 20 th November, 2013 Marginal gains and why they matter David Collier, Energy and Sustainability Manager.
Lindab Solus - Simply the natural choice.... lindab | comfort Chilled beam revolution! + Save up to 45 % cooling energy!* + Installation and investment.
GREEN GOWN AWARD 2008 DALHOUSIE BUILDING DEREK MITCHELL ENERGY MANAGER JUNE 2009.
Management and Organisation of Electricity Use Electrical System Optimisation Belgrade November 2003.
BREEAM HIGHER EDUCATION AND LABORATORIES Peter James Higher Education Environmental Performance Improvement (HEEPI)
Tier 2 Power Supply Planning Workshop Advanced AMI Benefits Overview.
Photovoltaic Systems: Market Drivers, economics and opportunities Lyndon Frearson General Manager CAT Projects.
PNW RoofTop Unit Working Group - RTUG – RTU Savings Research Project Phase 3 December 15, 2009.
Wurster Hall MBCx Project October 30th, Project Overview Project Goals Project Objectives Identify Low Cost/No Cost Measures Identify Retrofit.
RTF RTUG Update Aug 12, 2010 “The Turn of the Screw” Premium Ventilation Extended Monitoring Reid Hart, PE Associate Director Technical Research Group.
Copyright © 2015 Optimum Energy LLC. All Rights Reserved. Proprietary & Confidential Incorporating Energy Conservation Strategies into University Research.
Easy FlowTM and Smart FlowTM
Metering and Monitoring  The Business Case.  Implementing the project.  Benefits – accurate data and data analysis.  On-going challenges.
Turning Energy Data into Operations Intelligence Presented to: FMA September 17, 2013.
University of Oxford Environmental Sustainability Team Environmental Sustainability at the University of Oxford Twitter and £
Contract: EIE/07/069/SI Duration: October 2007 – March 2010Version: July 7, 2009 Ventilation for buildings Energy performance of buildings Guidelines.
Contract: EIE/07/069/SI Duration: October 2007 – March 2010Version: July 7, 2009 Ventilation for non-residential buildings - Performance requirements.
Renewable Energy Technologies and the Building Schools for the Future Programme Property Group - M&E Team Michael J Rigby M & E Team Manager Mechanical.
Heat Network Demonstration SBRI: policy context & objectives for the competition Natalie Miles Heat Strategy and Policy (Heat Networks)
ENERGY SAVING AND EFFICIENCY OF AIR CONDITION & LIGHT SYSTEMS AT PUBLIC BUILDINGS Meitav-tec (Contel group)
Carbon Management Journey
Integrate Lighting, Daylighting and HVAC Control in the Laboratory Room Duane Ranski Siemens Industry Inc.
Transition towards Low Carbon Energy Monday 12th June 2017
THE RECP ASSESSMENT Brent Goliath NATIONAL CLEANER PRODUCTION CENTRE
Time Shifting / Storage – Above Ground
Thembi Kodisang-Sibanda
Economic Operation of Power Systems
Sustainability and Life Cycle Costing of Air Filtration
Sustainability Its our choice
Total Production Increases as Consumption Remains Steady
Calibrated Energy Models: One New Change
How to tackle air pollution
Presentation transcript:

Continuous Optimisation JISC Improved Sustainability Across Estates Through The Use of ICT Continuous Optimisation – an Imperial College estates initiative reducing the carbon consumption of plant & services, and how ICT infrastructure underpins it’s delivery

Continuous Optimisation - Content Content Continuous Optimisation (ConCom) – what is it? –Background –Initiatives »Flowers building ‘night set-back’ »Air change rationalisation »Filter optimisation How does ICT support Continuous Optimisation? –TREND system –Carbon Desktop –Real Time Logging

Continuous Optimisation Continuous Optimisation (ConCom) – what is it?

Continuous Optimisation - Background Background Imperial College’s ‘Carbon Management Plan’ requires us to achieve a 20% reduction in carbon consumption by ,026 tCO 2 reduced by 16,805tCO 2 to 67,221tCO 2 Continuous Optimisation of plant & services, targeted to deliver 4,903tCO 2 This can only be achieved if we have: »Extensive control systems »Robust operational information »The cooperation of the academic community As a Science, Engineering and Medicine focussed University, our research and teaching relies heavily on controlled environments.

Continuous Optimisation - background We are challenging how environments were originally commissioned by considering: –The original design, at sign-off –How the environments are now being used –The occupation strategy –What service strategies are really needed to provide, safe and productive environments, without compromising our research & teaching. Through Continuous Optimisation (continuous commissioning ‘ConCom’), we are implementing: –Air change volume adjustments –AHU operational set-backs (temperature & time) –Introducing more efficient plant –Adjusting pump delivery to meet flow demands –Improving filter efficiencies –Introducing occupancy controls e.g. CO 2 sensors, ‘user switches’

Continuous Optimisation – Flowers building ‘night set-back’ Flowers Building ‘Night set-back’ Initiative

Continuous Optimisation – Flowers building ‘night set-back’ Flowers Building ‘Night set-back’ Methodology We identified Flowers building main air handling services were operating 24 hours a day, 7 days a week Environmental conditions and operational dependencies were discussed with users The four supply & extract air handling units were re-commissioned to ensure they could continue to operate to the original design This helped establish that new motorised dampers and controls would be required to manipulate the air pressures and volumes, while ensuring that dedicated equipment areas continued to receive 24hr ventilation / cooling.

Continuous Optimisation – Flowers building ‘night set-back’ Methodology (cont’d) The energy profile for the building was then measured across a normal week The new controls and motorised dampers were installed The air supply pressure was then reduced from 400pa to 300pa The air volume delivered overnight was reduced to an average of 6 air changes / hour, from 13, between 22.00hrs to 07.00hrs. The energy profile for the building was measured throughout this process and checked in subsequent weeks. Further commissioning followed; reducing air pressures, and extending the time to between 18.00hrs to 07.00hrs, more savings resulted.

Continuous Optimisation – Flowers building ‘night set-back’ Savings The base load has reduced from 280kW to 210 kW a 70kW saving Day time air pressure was reduced, heating & cooling savings resulted This realised overall savings of SavingskWh£CO2 Tonnes Night Set Back273,00023, Reduce daytime pressure218,40018, Heating & Cooling70,1756, Add weekends28,0802, Total589,65544,416315

Continuous Optimisation – Flowers building ‘night set-back’ Electricity profile the week before the damper replacement and night setback initiation Dampers replaced (Mon 5 th & Tues 6 th October) Night set back initiated Wednesday 7 th October kW Base load has reduced from 280kW to 210kW

Continuous Optimisation – Air change rationalisation Air Change Rationalisation

Continuous Optimisation – Air change rationalisation Air Change Rationalisation As part of our ConCom programme we challenge the air change strategy for each building, comparing the design, current operation and recommended standards. CIBSE guidelines recommend 6 air changes / hr for laboratories. We find that our environments are commissioned within significant excesses of this standard, often between 10 and 14 air changes / hr. Working closely with users, we measure the current air changes, and then gradually adjust the fan-sets, optimising their delivery but without compromising the business need or safety.

Continuous Optimisation – Air change rationalisation This approach can deliver significant savings through: –reduced fan motor speeds –reduced heating demands –reduced cooling demands An example of this approach in the Sir Alexander Fleming building, where we focussed on 3 of the main AHU’s has already delivered annual savings: 980,588 kWhrs,£31, tonnesCO 2

Continuous Optimisation – Air change rationalisation 14 Floor area served m2Volume served m3/s FloorAHU 1AHU 2AHU 3AHU 1AHU 2AHU ,700 2,577 Air delivered (design) m3/s Air delivered (measured 2010) m3/s Air Delivered (setback) m3/s ACH (design) ACH (measured 2010) ACH (setback)

Continuous Optimisation – Air change rationalisation 15

Continuous Optimisation – Air change rationalisation Carbon Desktop - Electricity demand profile for Transformer 40 - MCP3 at SAF. MCP 3 feeds AHUs 1,2,3, 4, 7,8,17,18,16,9 & 23. A further £15K in heating and cooling savings using bin weather data. 16

Continuous Optimisation – Filter Optimisation Filter Optimisation

Continuous Optimisation – Filter Optimisation Filter Optimisation Most air handling units (AHU’s) have integral filter strategies, applied primarily to supply, and for some applications, the extract. Filter media provides significant resistance within the air flow path, resistance increases as filters become blocked. Higher resistance of the filter, results in increased energy consumed by fan motor to provide the required air flow. Initial trials (Carbon Trust Funded) in the SAF building have shown, that by using filter media (e.g. HiFlo bag filters) with a larger surface area, significant savings can be achieved on fan motor power.

Continuous Optimisation – Filter Optimisation 19 Bag Filters % installed at the IC (approx) Energy Rating Comparative Cost per filter (£) Details S Flo - WU series30%E£19.73 Basic economic bag ~ 300mm deep S Flo – WP series50%E£18.23 Basic economic bag ~ 500+mm deep Opakfil Green20%A£60.68 Energy efficient “rigid” bag Used at SAF Hi Flo – M series0%A£48.05 Energy efficient – high surface area bag Not used anywhere at IC yet.

Continuous Optimisation – Filter Optimisation 20 NoMeasure Implement Immediately? Energy Savings (kWh/yr) CO2 Savings (tonnes/y r) Energy Cost Savings (£/yr) Total Life Cycle Cost Savings - LCC (£/yr) SAF 1Replace HEPAs (H13 to H10) YES50,43027£3,278 SAF 2 Replace standard G4 panels with 30/30 panels (implemented) YES64,34735£4,183£2,574 SAF 3 Replace Opakfil Bags with Hi Flo and remove Panels NO - TRIAL REQ’D138,3255£9,129£8, ,10267£16,590£13,889 NoMeasure Energy Savings (kWh/yr) CO2 Savings (tonnes/y r) Energy Savings (£/yr) Total Cost Savings LCC (£/yr) All filters measures above 2,271,7651,156£146,710£87,008

Continuous Optimisation – Filter Optimisation 21 No Measure Implement Immediately? Savings CurrentProposed Energy (kWh/yr) CO2 (tonnes/yr) Cost (£/yr) Total Life Cycle Cost - LCC (£/yr) 1HEPAs H13HEPAs H10 MORE INFO REQ’D TBC 2Standard G4 panels30/30 panelsYES252,217137£16,39410,936 3Pad filters 30/30 pleated panel filters YES126,10869£8,1975, mm Bags600 mm Hi Flo BagsTRIAL REQ’D464,447247£ ,691 7 S Flo (WU) & Opakfil (rigid) Bags Hi Flo Bags (no panels) YES87,93848£5,7161,443 8Change panel filters at lower pressure dropYES252, ,39410,936 9Change bag filters at lower pressure dropYES162, ,5856, Improved filters &changing regime for AHUs < 15 kW YES672, ,37324, (SAF) HEPAs H13HEPAs H10YES50,43027£3, (SAF) Standard G4 panels30/30 panelsYES64,34735£4,183£2, (SAF) Opakfil BagsHi Flo bags (no Panels)TRIAL REQ’D138,3255£9,129£8,037 2,271,7651,156£146,710£87,008

Continuous Optimisation – Filter Optimisation 22 Hi flow bag S Flow bag Opakfil Rigid bag 30/30 Pleated Panel

Continuous Optimisation – How does ICT support Continuous Optimisation? How does ICT support Continuous Optimisation?

Continuous Optimisation – TREND System TREND System (BMS) Imperial College has the largest TREND Building Management System in the UK (original installation commenced1996). Traditionally it has been used to monitor the operational status of plant & services and in particular, plant failure (replaced Sauter). This system was stand alone with a ‘hard wired’ network, which as it grew, became less reliable and access speed slowed significantly. To overcome these issues and future demand we now run the BMS over the Cat 3 network, which assures capacity, improves access and has increased reliability. This approach has allowed us to widen access via a web link, and start utilising it’s potential for improving sustainability through better control and awareness.

Continuous Optimisation – Flowers building ‘night set-back’ Electricity profile the week before the damper replacement and night setback initiation Dampers replaced (Mon 5 th & Tues 6 th October) Night set back initiated Wednesday 7 th October kW Base load has reduced from 280kW to 210kW

Continuous Optimisation – Carbon Desktop Carbon Desktop

Continuous Optimisation – Carbon Desktop

Pre Set-BackPost Set-Back

Continuous Optimisation – Carbon Desktop Weekly range = 0.4 tCO2 Pre Set-Back

Continuous Optimisation – Carbon Desktop Post Set-Back Weekly Range = 0.8 tCO 2

Continuous Optimisation – Real Time Logging Real Time Logging

Continuous Optimisation – Real Time Logging Real Time Logging Imperial College has spent over £1M in extending our metering capacity in the past 2.5 years. Despite this investment, this growth generally doesn’t extend itself to individual items of plant, which can make assessment of actual load, and any beneficial improvements difficult to monitor. We are introducing ‘Real Time Logging’ utilising meters with radio interfaces linking to an accessible website. This allows us to run real time trials e.g. AHU fan motors with filter changes and verify savings.

Continuous Optimisation – How does ICT support Continuous Optimisation? The use of these approaches, provide fundamental support to our ConCom programme and help to: –Raise awareness within the academic community –Demonstrate improved sustainable performance –Validate data and savings

Continuous Optimisation How are we achieving improved sustainability Building Management Academic Community ICT Services TOGETHER