1 Hall B RICH Review September 05+06, 2013 Readiness Review Process Rolf Ent.

Slides:



Advertisements
Similar presentations
Transition from the Long Shutdown to Hot Checkout: Pre-Hot Checkout Steve Suhring Operability Manager 6/6/13.
Advertisements

1 BROOKHAVEN SCIENCE ASSOCIATES Environment, Safety and Health Steve Hoey, ESH Manager NSLS-II Project Advisory Committee Meeting March 29, 2012.
Winter 2009 Scheduled Accelerator Down Environment Health & Safety Working in the Experimental Halls Bert Manzlak.
 Every stage from phase DESIGN in Software Development Process will have “design document” especially in analysis and design phases.  “Design document”
LCLS Transition to Science DOE Status Review of the LUSI MIE Project LCLS NEH ARR John Arthur LCLS Experimental Facilities Division August 11, 2009 Welcome.
FAC 4/20/06 D. Schultz 1 The SAD and ARR for Commissioning The Status of the SAD Being written as a part of the SLAC Linac SAD The Status of the ARR Design.
Safety Oversight for SLAC Accelerator Department Operations
Stephen Milton Undulator System 20 April, 2006 LCLS Undulator System Update S. Milton, ANL FAC, April 20 th, 2006.
Systems Engineering Management
An updated Baseline Design for MICE From proposal to technical reference Paul Drumm, Dec 2003.
The New EMC Directive 2004/108/EC and the DTI transposition Brian Jones and Peter Howick.
Effective Methods for Software and Systems Integration
LCLS NEH Operational and User Safety Programs
 A project is “a unique endeavor to produce a set of deliverables within clearly specified time, cost and quality constraints”
THE PROTOTYPING MODEL The prototyping model begins with requirements gathering. Developer and customer meet and define the overall objectives for the software.
Fermilab Implementation of DOE Critical Decision Process FRA Project Management System Presentation by L Edward Temple Jr Head, Office of Project Management.
Page 1 MODEL TEST in the small GENERALIZE PROGRAM PROCESS allocated maintenance changes management documents initial requirement project infrastructure.
1 BROOKHAVEN SCIENCE ASSOCIATES Authorization Basis Plan Steven Hoey, ESH Manager NSLS-II Project Advisory Committee Meeting December 10 – 11, 2009.
Software Quality Assurance Activities
NCSX Management Overview Hutch Neilson, NCSX Project Manager NCSX Conceptual Design Review Princeton, NJ May 23, 2002.
1 Kenneth Osborne, 9/14/07 Inter Group communications at the Advanced Light Source. Overview of the different methods of communication between different.
IAEA International Atomic Energy Agency. IAEA Outline LEARNING OBJECTIVES REVIEW TEAM AND COUNTERPARTS Team Composition Qualification PREPARATORY PHASE.
July LEReC Review July 2014 Low Energy RHIC electron Cooling Edward T. Lessard ESHQ.
OFFICE OF SCIENCE 2.3 Infrastructure and Installation Sims, Edwards 1.Does the conceptual design and planned implementation satisfy the performance specifications.
Using ISMS Principles and Functions in Developing an ARRA Readiness Review Process Presented by Linda K. Rogers Assessments & Readiness Programs Manager.
Comments from Physics Division Rolf Ent Associate Director for Experimental Nuclear Physics SOLID collaboration meeting, February 03, 2012 Thomas Jefferson.
7/26/2006 Wyatt Merritt 1 DECam CD1 Documentation DOE Critical Decision Process Documentation Requirements.
1 Zoe Van Hoover 1 User Safety: Commissioning and Early Experiments NEH ARR User Safety: LCLS NEH Commissioning and Early Experiments.
Energy, Environment and National Security Directorate (EENS) Best Management Practices in the Experimental Safety Review Program Robert Doty Experimental.
End Station A Test Beam (ESTB) Carsten Hast and Mauro Pivi August 23 th 2012 Proposals, Procedures, Schedule.
1 1. Some recent views ( ) 2 Linac tunnel
Configuration Management and Change Control Change is inevitable! So it has to be planned for and managed.
IRES: an update on the revision process Vladimir Markhonko United Nations Statistics Division The 4 th meeting of the Oslo Group on energy statistics Ottawa,
Jefferson Lab 12 GeV Upgrade Accelerator Readiness Review Phase 3 Roger Erickson SLAC National Accelerator Laboratory ARR Team Chairman August 26-28, 2014.
NCSX Systems Engineering Management Plan Peer Review Bob Simmons May 15, 2003.
FACET User Support Carsten Hast Accelerator Research Division Test Facilities Department
Transversity Readiness and Timeline Xiaodong Jiang, March 17th, This document specifies the overall readiness for Hall A experiments E06-010/E
Winter 2011SEG Chapter 11 Chapter 1 (Part 1) Review from previous courses Subject 1: The Software Development Process.
Transverse Momentum Dependence of Semi-Inclusive Pion and Kaon Production E : Spokespersons Peter Bosted, Rolf Ent, Hamlet Mkrtchyan 25.5 days.
PRad Recent Achievements 1)PRad Implementation (“Position”) document developed and submitted to Jlab. 2)Jlab’s Director Office scheduling review passed.
IAEA International Atomic Energy Agency. IAEA Outline LEARNING OBJECTIVES REVIEW TEAM AMD COUNTERPARTS Team Composition Qualification PREPARATORY PHASE.
Thursday August 20, 2009 John Anderson Page 1 Accelerator Interlock System Issues Flow Down of Requirements from the Safety Order to Engineered Safety.
Experiment Readiness Review P. Rossi – Hall C Coll. Meeting Jan 21, 2016.
Linda Bagby - SBN Program Electrical Coordinator ICARUS Electronics Meeting 27 January 2016 SBN Program Operational Readiness Clearance.
Linda Bagby - SBN Program Electrical Coordinator T600 Installation 8 February 2016 SBN Program Operational Readiness Clearance.
ESS Cryomodule Status Meeting – Elements of Safety | | Christine Darve Elements of Safety Applicable to the ESS 2013 January, 9 th Christine.
Audits & DOE Walkthroughs ISO and OHSAS surveillance audits August 18 th – 20 th –CD, ESH&Q, and FESS organizations to be audited Software.
PIP-II Environment, Safety, Health & Quality Assurance Strategy John Anderson Jr. DOE Independent Project Review of PIP-II 16 June 2015.
Overview of FESHCom Subcommittees Don Cossairt, Radiation Protection Manager, ESH&Q Section October 1, 2013.
IS&T Project Reviews September 9, Project Review Overview Facilitative approach that actively engages a number of key project staff and senior IS&T.
Financial System Upgrade Agency Change Champion Deployment Session March 16 th, 2006.
Communication Tools Used For Commissioning the 12 GeV CEBAF Accelerator Brian Freeman WAO (Mainz, Germany) October 2014.
Safety Configuration Management Process at JLab
JLab Phase 4 Final Results
Head, Office of Project Management Oversight (OPMO)
Experiment Readiness Review
PERSONAL SAFETY INTERLOCKS External EHS Expert Panel Workshop
Jefferson Lab Overview
2K CB FDR Overview:  Agenda, Charge, Review Process
Preparations for a Lehman Review
1 Zoe Van Hoover 1 User Safety: Commissioning and Early Experiments NEH ARR User Safety: LCLS NEH Commissioning and Early Experiments.
IS&T Project Reviews September 9, 2004.
LERF Readiness Review: Charge
Ian Evans SSRL Safety Office
DOE Review of the LCLS Project October 2006
Licensing update ESHAC #7, October 2017
Lessons from the 1st Safety Readiness Review
ESHAC #8 Safety Readiness Review Thomas Hansson, ESH
Safety Program for LCLS Experiments
SNS-PPU upgrades the existing accelerator structure
Presentation transcript:

1 Hall B RICH Review September 05+06, 2013 Readiness Review Process Rolf Ent

2 Readiness Review Process Jefferson Lab experiments typically use a combination of base equipment and new, often JLab-user led and constructed, equipment. How do we integrate such new equipment effectively and safely? Outline: Experimental Readiness Review Process in the 4 & 6 GeV era Management self-assessment for "Installation of New Equipment Involving Multiple Groups”. New Experimental Readiness Review Process in the 12 GeV era Implications for RICH

3 Experiment Systems Readiness reviews are standalone reviews required prior to delivery of any beam to the respective Hall. The Experiment Systems Readiness Process has been used effectively for all JLab experiments since the start of experiments in Experiments went through different levels of readiness reviews depending on being categorized as “Experiments using major new apparatus”. Goal: assure that the equipment can be safely and effectively operated, and to document operational procedures appropriate for its commissioning. All 12-GeV equipment will undergo an Experiment Systems (Hall A, B, C, and D) Readiness review as a modular piece of the overall Accelerator Readiness Review (ARR) process. Basic commissioning of components initiated under JLab Temporary Operational Safety Procedures (Chapter 3320, “Temporary Work Permits”) Checkout of full equipment with beam requires  Conduct of Operations (COO)  Radiation Safety Assessment Document (RSAD)  Experimental Safety Assessment Document (ESAD)  Safety Checklists Experiment Systems Readiness Process - General

4 Experiment Systems Readiness Process - Example G0 Experiment in Hall C as example of “Experiments using major new apparatus”. Series of Equipment Readiness, Safety, and Documentation reviews during design & construction phases before operations. target service vessel beam line SC magnet detectors

5 G0 Safety and Technical Reviews (2002 only) G0 Experiment in Hall C as example of “Experiments using major new apparatus”. G0 reviews in 2002, the year of final installation and commissioning (many more before th DateSystemScopeReviewers Feb TargetEngineering & Safety ReviewJ. Kilmer (FNAL), J. Mark (SLAC), J. Domingo (JLab), D. Kashy (JLab), W. Vulcan (JLab), M. Seely (JLab) May 01Magnet + TargetTOSP for Vacuum EvacuationESH&Q + Subject Matter Experts (SME) MayTargetPunchlist Items ReviewJ. Domingo (JLab,), D. Kashy (JLab), W. Vulcan (JLab) MayTargetTOSP Neon TestESH&Q + SME MayTargetTOSP Hydrogen CooldownESH&Q + SME Jun MagnetEngineering & Safety ReviewB. Schneider (JLab), A. Visser (FNAL), J. Gomez (JLab), A. Guerra (JLab) JulyMagnetTOSP Magnet CooldownESH&Q + SME Aug. 09G0RSADESH&Q (Radiation Control Group) Aug. 14G0Full EH&S Review (I) (Last Readiness Review) G. Dodson (ORNL), J.P. Chen (JLab), B. Manzlak (JLab), E. Smith (JLab), M. Spata (JLab), W. Vulcan (JLab) Aug. 21G0TOSP G0 Beam TestsESH&Q + SME Sep. 09G0 + MagnetTOSP Powering of the G0 SMS and G0 Beam Tests ESH&Q + SME Sep. 16G0COO and ESADESH&Q + SME Sep. 19G0Full EH&S Review (II) (Last Readiness Review) G. Dodson (ORNL), J.P. Chen (JLab), B. Manzlak (JLab), E. Smith (JLab), N. Okay (JLab), W. Vulcan (JLab)

6 Experiment Systems Readiness Process - findings Performed a Management Self-Assessment process at the end of the 6-GeV era to look at “Installation of New Equipment Involving Multiple Groups”. Asked group to fold in experience of Hall C/Qweak and Hall A/g2p experiments, Hall B/HDICe, and earlier reports/lessons learned on for instance Hall C/HKS, Hall A/PREX, etc. Both staff and users were polled. Two findings Experiment Readiness Review Process has not been followed thoroughly for the last couple of projects -Not well defined what constitutes an experiment with major new apparatus -Readiness Review process and reviews should be clearly articulated -Design changes were allowed until very (too) late -Identification of beam and lab infrastructure requirements need to be done early Experiment Readiness Review Process not commonly known -Discrepancies in knowledge amongst Hall C vs. other Halls -Discrepancies in knowledge amongst Physics Division vs. other Divisions -Discrepancies in knowledge amongst Staff vs. Users Two noteworthy practices Roles and Responsibilities seemed to be well known. The existing model seems to work well, with very good communication, coordination, and cooperation.

7 Jefferson Lab has revisited the experimental readiness review process in preparation of the 12-GeV startup. That means:  Partly correcting the Experiment Readiness Review web pages  Folding in feedback from the management self- assessment for "Installation of New Equipment Involving Multiple Groups”. The document, expected to be officially released with the completion of the web pages, will give the guidance for running experiments in the 12 GeV era.

8 DECOMMISSIONING Submitting Proposals TAC & PAC Process Director’s Decision PROPOSAL PHASE PRELIM. PLANNING PHASE Exp. Description and Requirements Exp. Readiness Review Calendar  DESIGN PHASE  PESAD, specific equipment reviews Complete Conceptual Designs & “1 st ” Readiness Review  CONSTRUCTION PHASE Fabrication of the equipment Test of the individual elements of the equipment (OSP/TOSP) SCHEDULING OF EXPERIMENT by JLab SCHEDULING OF EXPERIMENT by JLab EQUIPMENT INSTALLATION  RUN THE EXPERIMENT “Final” readiness review Final ESAD & RSAD COO Safety Checklist(s) Experimental Procedures Construction near-completed, designs frozen “2 nd ” Readiness Review before submitting scheduling request Readiness Review Process – Flow Chart

9 Readiness Review Process – Web Pages Or as text only version:

10 By the spokespersons

11 By the Division Safety Officer

12 ESH&Q Integration for RICH in Physics Fully integrate ESH&Q into planning and design –Perform hazard analysis for new scope No hazard found requiring PESAD/1 st readiness review of RICH –Coordination of work with outside institutions –Design and safety reviews of major subsystems Prepare for “2 nd ” readiness review stage before scheduling request Integration of assembly and commissioning tasks –Design changes where appropriate, e.g., No flammable gases, environmental-friendly where possible Reduce voltage where possible Freeze design after “2 nd readiness review” to prevent surprises for installation and running.

13 Concentrates on ESH Final readiness documents for experiments include: -Conduct of Operations (generic for all Halls, A-D) -Experiment Safety Assessment Documents (<40 page document of generic form) -Radiation Safety Assessment Documents (no changes) -Safety Checklists -Experimental Procedures (these are for the users, they can be on wikis or as “one-pagers” in the Hall documentation) Includes planning for decommissioning, if applicable We plan to independently construct an “Operations Manual” for experts that simply links all TOSPs used for commissioning the new equipment – the RICH would be folded in here. RICH can be declared “base equipment” only by the Division Safety Officer

14 Readiness Review Process - Summary The Experiment Systems Readiness Process has been used effectively for all JLab experiments since the start of experiments in 1995 The existing model seems to work well, with very good communication, coordination, and cooperation amongst multiple divisions, and roles and responsibilities well defined (work coordinator, physics liaison, accelerator liaison, engineering coordinator) Nonetheless, the process was not well known and not always followed Revisited experiment systems readiness process to - Clarify review process from the start – communicated to users - Update web pages for consistency – in progress - Update safety documentation and Hall safety walkthrough to become as generic as possible for all Halls (A-D) COOgeneric document ESADgeneric format (draft) RSADgeneric format Safety checklists Experimental procedures for users (wiki or “how-to’s”) Operations Manual for experts Safety Walkthroughsgeneric format (draft) - Include decommissioning in reviews RICH comes in at “2 nd readiness review”: review before scheduling request