SiD assembly Marco Oriunno (SLAC), May. 14, 2014 ALCW 2014, Fermilab Infrastructures & Timeline for Hybrid Access.

Slides:



Advertisements
Similar presentations
Kitakami IR Access Discussions T. Markiewicz/SLAC 13 May 2014 SiD Meeting / AWLC Fermilab.
Advertisements

SiD Surface assembly Marco Oriunno (SLAC) MDI-CFS Meeting Sep. 4-6, 2014, Ichinoseki (Japan)
Cryogenics at CERN (LHC)&Helium Inventory Brief review with emphasis given on cryogen management Americas Workshop on Linear Colliders 2014 Fermilab,
The CERN-JINR Collaboration J. Engelen March 27, 2006.
Assembly Hall in Hybrid-A’ and ILD 2014/9/6 Yasuhiro Sugimoto 1.
NLC - The Next Linear Collider Project IR Layout Tom Markiewicz SLAC LCWS Cornell 15 July 2003.
DH in Hybrid-A and ILD 2014/9/5 Yasuhiro Sugimoto 1.
Experimental hall in Japanese mountain site Y. Sugimoto ILD MDI/Integration 1.
Global Design Effort Detector concept Plenary introductory talk IRENG07 Kurt Krempetz September 17, 2007.
Construction and Installation of the CLIC Experimental Area
Status of ILC Barry Barish Caltech / GDE 17-Aug-07.
1 GLD Surface Assembly Y. Sugimoto KEK
SID Engineering Marco Oriunno (SLAC), Jan CLIC Workshop, CERN Toward the TDR.
CES Status J.Osborne 6 November 2009 Status Report from Civil Engineering and Services Working Group J.Osborne GS/SEM for CES Working Group.
1 Alternative assembly option of ILD Y.Sugimoto 2010/10/18 ILD Integration
Experimental hall in Japanese mountain site Y. Sugimoto 1.
ARUP Studies Update ILC Interaction Region Design Requirements John Osborne CERN, Yung Loo & Matt Sykes (ARUP) CFS-ADI Joint Meeting - University of Tokyo.
Global Design Effort - CFS SiD Collaboration Meeting - SLAC 1 VERTICAL ACCESS ILC IR LAYOUT for SiD and ILD CONVENTIONAL FACILITIES AND SITING.
WP2 Superbeam Work Breakdown Structure Version 2 Chris Densham (after Marco Zito version 1 )
ILC experimental area - How to ‘develop’ CFS details for TDP (cavern size, number of shafts, HVAC, EL spec etc) ? - KEK site specific issues CFS V.Kuchler.
LINEAR COLLIDER COLLABORATION Designing the world’s next great particle accelerator Detector Hall Configuration Overview New baseline (Hybrid A’) proposed.
Beam Commissioning Marco Oriunno (SLAC), May 14, 2014 ALCW 2014, Fermilab Engineering Issues.
September 18, 2007H. J. Krebs1 SiD Collaboration One Piece End Door Design Concept plus Forward Equipment Interfaces H. James Krebs SLAC September 18,
Santa Cruz Meeting August 12 th 2008 Layout options & Schedule Issues David Lissauer 8/12/2008 1David Lissuaer, Santa Cruz Meeting.
10/2010 IWLC2010 Global Design Effort 1 Brief Overview of Interaction Region Conventional Facilities in RDR Times Presenter Tom Lackowski.
The CMS detector as compared to ATLAS CMS Detector Description –Inner detector and comparison with ATLAS –EM detector and comparison with ATLAS –Calorimetric.
1 SiD Push-pull Plans Marco Oriunno, SLAC International Workshop on Linear Colliders 2010 Geneva, October 2010 M.Oriunno, IWLC10 – Geneva, Oct.2010.
Transport of the CLIC Modules and Elements CLIC Workshop October 2007 Two Beam Hardware and Integration Working Group Keith Kershaw (CERN)
ILD requirement for assembly space and time 2015/11/3 Yasuhiro 1.
Strategy of detector solenoid construction Yasuhiro Sugimoto KEK 1.
Experimental Areas Studies Lessons learnt at CMS M Gastal & CMS Technical Coordination (A Ball, W Zeuner)
ILC D RAFT P ROJECT S CHEDULE K LYCLUSTER 500GeV K Foraz & M Gastal ILC Mechanical & Electrical Review and CFS Baseline Technical Review Many thanks to.
Access Yard Assembly Marco Oriunno (SLAC), November 13, 2013 LCWS13, TOKYO.
Experience from large helium inventory management at CERN ILC Cryogenics and Helium inventory meeting CERN, Wed. 18 th of June 2014 D. Delikaris Technology.
GLD experimental hall and detector assembly Y.Sugimoto KEK 27 Sep
Assembly scenario of ILD Si trackers 2015/4/21 Yasuhiro 1.
ILD and SiD in Japanese site (from discussions in SiD/ILD E/D Interface Working Meeting) Yasuhiro Sugimoto, Marco Oriunno 2011/12/15 SiD
SiD MDI Issues Tom Markiewicz/SLAC Beijing ACFA/GDE Meeting 05 February 2007.
Experimental hall in Japanese mountain site 2011/11/30 Yasuhiro CFS Webex meeting 1.
8/29/07K. C. Wu - Brookhaven National Lab1 Major Components in ILC IR Hall Interchangeable Detectors.
AWLC14 - FERMILAB May 12-16, 2014 Conventional Facilities & Siting Working Group Summary V Kuchler, A Enomoto, J Osborne.
SECONDARY BEAM HANDLING AND INFRASTRUCTURE DESIGN STATUS BRUNO FERAL (CERN/EN) DIAMANTO SMARGIANAKI (CERN/EN) Project Leader: I.Efthymiopoulos (Cern/EN)
MEA Machine and Experiment Assembly Norbert Meyners, MEA 12. July 2007ILC IRENG07 WG-A1 LDC Engineering Design (Status) Introduction General Design Detector.
12 July 2007IRENG07 WG-A M. Breidenbach1 SiD Concept SiD is relatively modest in scale compared to the LHC detectors, and comparable to SLD: Tracker Radius.
An idea of ILD general assembly plan 2015/10/8 Yasuhiro Integration Meeting 1.
Ideas on TPC Assembly Volker Prahl, Thomas Schörner-Sadenius Paris, 8/9 October /9 October 2015TSS: TPC Assembly1.
Kitakami Side AHCAL Assembly or anywhere in any detector.
M.Oriunno, SLAC 1 SiD installation with horizontal access shafts Marco Oriunno, SLAC SiD/ILD Engineering Meeting SLAC, December 2011.
1 Update of detector hall in mountain regions Y.Sugimoto in Granada.
Experimental Hall in Mountain Regions
SiD Collaboration Meeting SLAC, December 2011
2016/9/30 Yasuhiro Infra/CFS mini-ws
Detector Hall Design and Cost Information CONVENTIONAL FACILITIES
Introduction and Meeting Objectives
Yasuhiro Sugimoto 2012/2/1 ILD integration meeting
Marco Oriunno (SLAC), March 12, 2014 MDI WG
Experimental hall design in Japanese site
Update of experimental hall in Japanese mountain site
SiD LoI Costs M. Breidenbach 29 July 2010 M. Breidenbach.
Detector hall in mountain regions
Sub-Detector Assembly Area Summary of discussion at ALCW2015
CLIC Civil Engineering Update
Tom Lackowski Revised 10/12/2011
Integration and IR Hall
Detector hall in mountain regions
ILC Detector Technology
RDR Baseline Layouts for Interaction Region
L H C A T L A S International Collaboration on the LHC Project
Kitakami IR Access Discussions
as a prototype for Super c-tau factory
Presentation transcript:

SiD assembly Marco Oriunno (SLAC), May. 14, 2014 ALCW 2014, Fermilab Infrastructures & Timeline for Hybrid Access

Physics requirements : Strong central field of 5 Tesla + Full Silicon Tracker + High Granularity Calorimetry -> Compact and Light Detector Push Pull requirements Self-shielded -> Monolithic Iron Barrel with, ~2.6 meter Iron thick Short L* (3.5 m) -> FFS Captured in the door SID key Features SID Outer Diameter 3 meter < than ILD SID full length is half than CMS

3 The Magnet drives the assembly procedure The Solenoid and the sectors of the Iron Magnet are the heaviest and largest parts. They have an envelope diameter of 7 meters and 3 meters respectively. Both are under 200 Tons. They dominate the construction logistic and the infrastructures requirements.

4 Lean assembly – Some Examples CMS Detector Shipbuilding Airbus

1.Construction and Testing of large sub-assemblies in remote sites (Institutes/Factories). 2.Checking after transport and pre-commissioning on Surface. 3.Complete the construction underground. The iron of the magnet has a modular design with parts below 200 Tons, constructed at the factory and shipped to the site. The unit will be completed in situ with detectors (RPCs) and tested before they are moved in the Detector Hall Because of the compact design of SID, the full weight of the Solenoid is well under 200 Tons. The two coils will be made at the factory, where they will installed in the Cryostat and shipped to the site before a low current check test, which will be eventually repeated before to move it in the Detector Hall. All the detectors within the Solenoid diameter, Tracker, EMCAL and HCAL, will need appropriate infrastructures, therefore will be built and tested in remote Labs/Campus before being shipped to the site for the final installation. Construction and Assembly Strategy:

6 Assembly with the Hybrid Design Option #1: Vertical shafts Option #2: Horizontal Tunnel Option #3: Both access VT HT

7 Option #1: Vertical shafts The barrel and the doors are fully assembled on Surface and lowered through the main shaft, with the solenoid inside the barrel Calorimeters and Tracker through the Horizontal Tunnel with OD8m Infrastructure required by SID alone : 20 x 20 m 2 Platform one 200 T capacity crane on surface one 4,000 T Gantry on the main shaft (to be shared with ILD) one 50 T crane underground Heavy Load Truck with a capacity of 50 T on < 10% slope Cryogenics and Power Supplies required on surface if the Solenoid is commissioned to the full current. Two systems very likely required, one each detector. Not trivial if the Helium compressors are located underground (CMS has compressor and Helium storage on surface)

Option #1: Vertical shafts

Option #1: Vertical Shaft, HCAL Installation Through the HT or a second shaft is required

10 Option #1: Vertical shaft, comments 1.Large infrastructures on Surface 2.Handling of components with large mass and dimensions 3.A single shaft shared by both detectors, requiring a not trivial logistic with high infrastructures density. 4.HT still required for Inner Detector (HAC, ECAL, Tracker) 5.Require Cryogenics on Surface for commissioning. Inconsistent with the idea of compressors underground. Strategic advantage to full commission the Solenoid on surface and decouple the constructions of the Experimental Cavern and the Detector Assembly. But some of the benefits are lost because of a the point #3 and #4

11 Option #2: Horizontal Tunnel with OD8m Segments of the barrel and the doors with detectors are assembled on Surface and transferred through the horizontal tunnel. Solenoid assembled at the factory, burned in on surface and transferred through the horizontal tunnel. Full current commissioning only happen underground. Calorimeters and Tracker through the Horizontal Tunnel with OD8m Infrastructure required : one 200 T capacity crane on surface for SID One 50 Tons (my guess) capacity crane on surface for ILD one 2,000 T Gantry on the main shaft (only for ILD) one 200 T crane underground for SID and ILD Heavy Load Truck with a capacity of 200 T on < 10% slope * No Cryogenics required on Surface for SID

12 Dampimg Ring Surface 11 m 9 m 200 t + 20 t IR hall Specifications Helium Compressors Loading Area

13 Access tunnel Large Part Heavy Part

66 Tons 11 trips from Surface /Door 1 heavy lift / day Door Assembly on the platform

15 Access Tunnel, Coil

Solenoid Installation 215 tons Crane

17 Option #2: comments 1.Medium-large infrastructures 2.Handling of components with large mass and dimensions but gantry limited to 2,000 Tons 3.Heavy handling schedule decoupled for the detectors 4.Larger crane undergrounds 5.Doe not Require Cryogenics on Surface (at least for SID)

18 Handling of Large Weight CMS Lowering Start-to-End = 12 months for 11 large components < 2,000 Tons i.e. ~ 1 lowering/month 3 rings 5 rings Endcap - Endcap + Barrel

19 SID Options SID Option 1a = 3 components (2 x 2,500 T and 1 x 4,000 T) SID Option 1b = 5 components (2 x 2,500 T and 3 x 1,300 T) SID Option 2 = 40 components < 200 T

20 Schedules, Gantt Chart Jan.2027 (t0+2yr) Aug.2026 (to+1.5yr) 5.5 Years t0 = 2025 Sep.2026 (to+1.7yr)

21 Schedule, summary 5.5 years t0 + 2 years t years t years Cavern Construction t0 < 200 Tons parts, Horizontal Tunnel 2,000 Tons parts, Single Shafts 4,000 Tons parts, Single Shafts 6 months lag

22 LHC = Vertical Shafts

23 LHC Schedule drivers 1.LHC was built inside the preexisting LEP tunnel. 2.The main schedule drivers were the removal of the LEP parts and the installation of the new magnets. 3.The CMS schedule challenges were because the cavern was built almost entirely, certainly true for the two new large shafts, versus an almost ready-to-go detector hall for ATLAS. 4.The ILC complex will be entirely built by scratch.

24 LHC IR layouts CMS, IP5 ATLAS, IP1 ALICE, IP2 LHCb, IP8 4 shafts 3 shafts

25 ILC Schedule 4 years

26 Shafts versus Tunnel 1.Vertical shafts are an obvious solution for underground accelerator complex in flatlands (CERN) 2.Are less obvious in mountainous sites if the choice of short and flat tunnels is available VS HT Hyb.

27 Gran Sasso Lab = Horizontal Tunnel

28 Assembly Yard - CMS 140 m 223 m 150 m 34,000 m2 25 m Control Room Offices Gas 1 Gas 2 He

29 SPS beam extraction - North area (CERN) 46 m 230 m

30 Kitakami Access Yard = one 50T crane + one 200T gantry 60,000 m2 Tunnel

31 Detector Units on cart + Pushback track

32 Transferring parts underground

33 Conclusion Large detector elements < 200Tons will be built remotely in Labs/Factories and shipped to the site. SID has developed assembly procedures compatible with Vertical Shafts, Horizontal Tunnels or a combinations. In the first case the schedule is only marginally shorter (few months) but with a non trivial heavy handling logistic on surface with a single shared main shaft. SID prefers the underground assembly through the horizontal tunnel of sufficient diameter OD8m and moderate slope. If horizontal tunnels become not possible, a second large shaft, one each detector, would be needed, which would also decrease the schedule risk.

34 EXTRA SLIDES

35 ILC Site

36 Assembly Yard - CMS

37 SPS beam extraction - North area (CERN)

Geology Study (CLIC geometry) Baseline Baseline + 10m +10 m ARUP

Detector Hall Delivery before Detector Assembly 1.Two Cranes < 215 tons, 2.Platforms 3.Minimum set of infrastructures (Power, Compr. Air, etc.) 4.Pacmen can wait until detectors are ready