P.-R. KettleMEG Review July 20031 MEG Beam Line Studies.

Slides:



Advertisements
Similar presentations
1 MICE Beamline: Plans for initial commissioning. Kevin Tilley, 16 th November. - 75days until commissioning Target, detectors, particle production Upstream.
Advertisements

Peter-Raymond Kettle MEG Review February Cockcroft-Walton Status Carlo Bemporad Angela Papa Giovanni Signorelli Peter-Raymond Kettle Carlo Bemporad.
COBRA Magnet Test Milestone AssemblyDesignManufactoring DesignAss.TestWinding & Cryo. Deliv. PSI Test Platform Calibration Mapping device.
P.-R. KettleMEG-Review February MEG Beam Line Studies  E5 Z-Branch NOW !!! NOW !!!
P.-R Kettle MEG Review February Beam Line & Target Status Topics to be Addressed: Results of Beam Line Commissioning Phase Results of Beam.
1 G4MICE studies of PID transverse acceptance MICE video conference Rikard Sandström.
Super-B Factory Workshop January 19-22, 2004 Super-B IR design M. Sullivan 1 Interaction Region Design for a Super-B Factory M. Sullivan for the Super-B.
1 PSI 27/6/2006 C.Bemporad “THE TAMING OF MEG” News on Calibration Methods Cockcroft-Walton Accelerator  -sources on wire  -lines from neutron capture.
1 EMCal design MICE collaboration meeting Fermilab Rikard Sandström.
Crab Cavities in IR1 and IR5 Some considerations on tunnel integration What will be the situation in the tunnel after the LHC IR Phase-1 Upgrade. What.
Experimental Area Meeting V. Bobillier1 Good connection to earth (in many points) of every metallic parts to be installed in the cavern is very.
Forward TOF Prototyping Ryan Mitchell GlueX Collaboration Meeting November 2005.
MEBT & RT CH Section Thomas Page Fermilab Accelerator Advisory Committee May 10 th – 12 th, 2006.
COBRA Magnet Test Milestone AssemblyDesignManufactoring DesignAss.TestWinding & Cryo. Deliv. PSI Test Platform Calibration Mapping device.
Malte HildebrandtMEG Review Meeting, 14th February 2007 Report of Run Coordinator Run 2006 Summary Malte Hildebrandt MEG Review Meeting, 14th February.
The PEPPo e - & e + polarization measurements E. Fanchini On behalf of the PEPPo collaboration POSIPOL 2012 Zeuthen 4-6 September E. Fanchini -Posipol.
P.-R Kettle MEG Review July Beam Transport & Target Systems BTS Success Novosibirsk 24/5/ : A 300 A.
Peter-Raymond Kettle MEG Review February MEG Commissioning & Engineering Run 2007.
SHMS Optics and Background Studies Tanja Horn Hall C Summer Meeting 5 August 2008.
2 1/March/2015 日本物理学会大70回年次大会@早稲田大学 東大ICEPP 内山雄祐 他 MEG II collaboration.
MEG positron spectrometer Oleg Kiselev, PSI on behalf of MEG collaboration.
1 W.Ootani ICEPP, University of Tokyo MEG experiment review meeting Feb , PSI W.Ootani ICEPP, University of Tokyo MEG experiment review meeting.
MEG DC (report June 04) DC report june_04,J.E. a)Foil stability and quench related problems b)How to get more stability c)Frame design d)Measurement of.
PSI July 2002MuEGamma Review Meeting1 Beam Line Status update 1.  E5 Test Beam Overview : Aims + RequirementsAims + Requirements Zone Layout + Measurement.
Flavio Gatti,Frascati-PSI, Jan 31 th, 06 1 TC status. Flavio Gatti UNIVERSITY and INFN of Genoa, Italy.
GIF in EHN1- layout, construction and schedule Adrian Fabich, EN-MEF-LE GIF users meeting, 12 th February 2014.
1 MICE Hall and Infrastructure - Progress since CM18 Chris Nelson MICE CM19 Oct 2007.
Test beam setup: status report 31/03/2009 M. Alfonsi (CERN)
Run 12: STAR Status and Schedule Update RHIC Coordination Meeting October 18, 2011 Bill Christie BNL Outline Status update Schedule update and issues Summary.
Peter-Raymond Kettle Tokyo - Topical Meeting, March Beam Monitoring Basis for Discussion only Beam Rate Beam Rate Beam Profile Beam Profile Beam.
MICE Status & Plans MICE-UK paul drumm 15 th September 2004.
Lau and Niels, NA62 TD meeting, 17 March Complete the crane consolidation in TCC8 Reinstall front-end after alignment checks Consolidation of T10.
RSVP AGS Upgrade Projects MECO RSVP Preliminary Baseline Review Brookhaven National Lab April 6-8, 2005 D. Phillips.
7 November 2003 Status of CNGS NBI presented by K. Elsener 1 Status of CNGS Konrad Elsener CERN – Accelerators+Beams Division.
Peter-Raymond Kettle MEG Review February BeamBeam LineLine StatusStatus.
Overview of the experiment Collaboration (about 30 physicists at this meeting) Budget Realistic schedule and general status (few words) of each sub-detector.
RSVP AGS Upgrade Projects MECO RSVP Preliminary Baseline Review Brookhaven National Lab April 6-8, 2005 D. Phillips.
COMET. μ-e conversion search from muonic aluminium J-PARC pulsed proton beam to produce pulsed muon beam Forbidden in the Standard Model  clue to the.
P.-R. KettleMEG Review January MEG – Beam Line Studies Present Status & Overview since July 2002.
Working group on photon vetoes Meeting on June 7 th : 1.Status of Geant4 simulations 2.Discussion on LAV structure 3.Discussion on readout 4.News on Spaghetti.
1 COBRA Magnet Status W.Ootani MEG Experiment Review Meeting, Jul W.Ootani MEG Experiment Review Meeting, Jul
Proton Driver Design Keith Gollwitzer Fermilab February 19, 2014.
Xenon Delivery Japan 1 MCHF 575 kCHF granted Additional grant 656 kCHF Last 50l subject to negotiation.
P.-R. KettleMEG-Review July MEG Beam Line Studies  E5 Z-Branch Collaborative Effort !!! Effort !!!  E5 Z-Branch Collaborative Effort !!! Effort.
DON LYNCH NOVEMBER 6, AGENDA November 4, BABAR Magnet Update Global Design Concept – Update Outer HCal Structural Analysis (2 nd pass) sPHENIX.
A. Baldini PSI July 05 Overview of the experiment MEG is being built (Beam line, Magnet, LXe, DC, TC, Elect., Software) Delays in some items: O(months)
Interaction Region Design and Detector Integration V.S. Morozov for EIC Study Group at JLAB 2 nd Mini-Workshop on MEIC Interaction Region Design JLab,
Tuesday 9 th January Project Status Report Project Achievements Project Schedule Issues Finance Summary Risk Register Photos.
1 Implementation at RAL Iouri Ivaniouchenkov on behalf of Elwyn Baynham, Tom Bradshaw, Tony Jones, Jim Rochford Engineering Department, RAL MICE Collaboration.
MEG Review Meeting June Peter-Raymond Kettle Beam Line Line Status StatusBeam Line Line Status Status.
ESS Front End diagnostic
ELENA installation progress F. Butin / ELENA collaboration.
Peter-Raymond KettleMEG Fortnightly Meeting 16/5/20071 Beam Schedule Update.
g beam test of the Liquid Xe calorimeter for the MEG experiment
Polarized Injector Update
Technical Design for the Mu3e Detector
V. Bagnoud PHELIX, Plasma Physics department GSI Darmstadt
HIE-ISOLDE Report Jose Alberto Rodriguez on behalf of Yacine Kadi and the HIE-ISOLDE project team.
- STT LAYOUT - SECTOR F SECTOR A SECTOR B SECTOR E SECTOR D SECTOR C
Luminosity Monitor Status
The COMET Experiment Ajit Kurup, Imperial College London, on behalf of the COMET Collaboration. ABSTRACT The COherent Muon to Electron Transition (COMET)
N-TOF EAR2 - Vertical beam design & construction - Irradiation facility proposal S. Girod EN-EA.
TC status & remaining tasks
I Alexander Nass for the JEDI collaboration
Interaction Region Design Options e+e- Factories Workshop
K. Tilley, ISIS, Rutherford Appleton Laboratory, UK Introduction
Higgs Factory Backgrounds
as a prototype for Super c-tau factory
IR Beam Transport Status
F.Pasdeloup, H.Prin, L. Williams
Presentation transcript:

P.-R. KettleMEG Review July MEG Beam Line Studies

P.-R. KettleMEG Review July Outline of Topics to be Addressed Status at the time of the last Review Status at the time of the last Review Beam Time April/May 2003 “Z-Branch” Beam Time April/May 2003 “Z-Branch” Beam Transport Solenoid BTS Beam Transport Solenoid BTS Future Future Summary/Conclusions Summary/Conclusions Beam Line Schedule Beam Line Schedule Area Layout Area Layout Status at the time of the last Review Status at the time of the last Review Beam Time April/May 2003 “Z-Branch” Beam Time April/May 2003 “Z-Branch” Beam Transport Solenoid BTS Beam Transport Solenoid BTS Future Future Summary/Conclusions Summary/Conclusions Beam Line Schedule Beam Line Schedule Area Layout Area Layout

P.-R. KettleMEG Review July Status at the Last Review Milestone achieved on schedule Milestone achieved on schedule Viable Solution for the MEG Beam Line FOUNDViable Solution for the MEG Beam Line FOUND using “Z”-Branch with separate stages for using “Z”-Branch with separate stages for Particle Separation & Momentum Degradation Particle Separation & Momentum Degradation via 2 triplets + WIEN Filter + Solenoid/Degrader system via 2 triplets + WIEN Filter + Solenoid/Degrader system Rudimentary work on Transport Solenoid BTS Rudimentary work on Transport Solenoid BTS had just started had just started initial length ~180cm? with B~0.5T? initial length ~180cm? with B~0.5T? Warm or Cold? etc. Warm or Cold? etc. Solenoid + Degrader & Stop Distribution measurements Solenoid + Degrader & Stop Distribution measurements planned planned Final part Phase C of “Z”-Branch Measurements Final part Phase C of “Z”-Branch Measurements April/May 2003 April/May 2003 Milestone achieved on schedule Milestone achieved on schedule Viable Solution for the MEG Beam Line FOUNDViable Solution for the MEG Beam Line FOUND using “Z”-Branch with separate stages for using “Z”-Branch with separate stages for Particle Separation & Momentum Degradation Particle Separation & Momentum Degradation via 2 triplets + WIEN Filter + Solenoid/Degrader system via 2 triplets + WIEN Filter + Solenoid/Degrader system Rudimentary work on Transport Solenoid BTS Rudimentary work on Transport Solenoid BTS had just started had just started initial length ~180cm? with B~0.5T? initial length ~180cm? with B~0.5T? Warm or Cold? etc. Warm or Cold? etc. Solenoid + Degrader & Stop Distribution measurements Solenoid + Degrader & Stop Distribution measurements planned planned Final part Phase C of “Z”-Branch Measurements Final part Phase C of “Z”-Branch Measurements April/May 2003 April/May 2003

P.-R. KettleMEG Review July Measurements: Phase B – post Triplet 2 & Collimator Phase B – post Triplet 2 & Collimator Phase C – post Solenoid Phase C – post Solenoid Several unexpected problems encountered & Solved !!! Measurements: Phase B – post Triplet 2 & Collimator Phase B – post Triplet 2 & Collimator Phase C – post Solenoid Phase C – post Solenoid Several unexpected problems encountered & Solved !!! “Z-Branch” Measurements April/May2003

P.-R. KettleMEG Review July April/May 2003 Beam Test cont. Total of 4 Weeks of Beam Time: of Beam Time: 1 week Phase B 1 week Phase B 3 weeks Phase C 3 weeks Phase CPROBLEMS: 3 Days Accelerator Down 3 Days Accelerator Down  Planned for Solenoid Fringe-field Solenoid Fringe-field distorts optics between distorts optics between Triplet 2/Collimator & Solenoid Triplet 2/Collimator & Solenoid  Extra vacuum pipe between Collimator & Solenoid SOLVED !!! WIEN Filter DOWN for nearly ALL Phase C measurements WIEN Filter DOWN for nearly ALL Phase C measurements due to HV-insulation Problems at Cable feed-through (OIL) due to HV-insulation Problems at Cable feed-through (OIL)  Measurements done without Separator  FULL e + beam NaI found to have NO Magnetic Shielding – solenoid stray field NaI found to have NO Magnetic Shielding – solenoid stray field  Built Magnetic Shielding Box SOLVED !!! CONSEQUENCE 2-Day  -Beam Test Cancelled CONSEQUENCE 2-Day  -Beam Test Cancelled

P.-R. KettleMEG Review July Results “Z-Branch Measurements” Triplet 2 1 Solenoid WIEN Filter Colli. Trip. µ+µ+µ+µ+ e+e+e+e+ e+e+e+e+ µ+µ+µ+µ+ Phase A Integrated Rate 4cm 1800µA N µ ~1.3·10 8 µ + /s (2.3·10 8 µ+/s 6cm Tg.) Integrated Rate 4cm 1800µA N µ ~1.3·10 8 µ + /s (2.3·10 8 µ+/s 6cm Tg.) P-Spectra: P-Spectra:  -Kinematic Edge (29.79 MeV/c) (29.79 MeV/c) Theoretical func. P 3.5 folded with Gaussian ΔP/P + Const. Cloud µ + contribution contribution “U-Branch” “Z-Branch” P cent =(28.2±0.1)MeV/c ΔP/P =(7.9±0.6)% FWHM P Beam =(28.2±0.9)MeV/c Consistent with TURTLE & P-Slit settings/Calib. “Z-Branch”

P.-R. KettleMEG Review July Phase B Separation Quality Triplet 2 1 Solenoid WIEN Filter Colli. Trip. µ+µ+µ+µ+ e+e+e+e+ e+e+e+e+ µ+µ+µ+µ+ Phase B µ+µ+µ+µ+ e+e+e+e+ Integrated Rate 4cm 1800µA N µ ~8.5·10 7 µ + /s (1.5·10 8 µ+/s 6cm Tg.) Integrated Rate 4cm 1800µA N µ ~8.5·10 7 µ + /s (1.5·10 8 µ+/s 6cm Tg.) µ/e Separation 11.8cm 7.2σ !!! µ/e Separation 11.8cm 7.2σ !!! LowThreshold50mV Integrated Rate After Separator 4cm 1800µA N µ ~9.4·10 7 µ + /s (1.7·10 8 µ+/s 6cm Tg.) N e /N µ > 9 N e ~ 8.7·10 8 e + /s Transmission Factors T Sep = (71±5)% T Colli = (90±5)% Integrated Rate After Separator 4cm 1800µA N µ ~9.4·10 7 µ + /s (1.7·10 8 µ+/s 6cm Tg.) N e /N µ > 9 N e ~ 8.7·10 8 e + /s Transmission Factors T Sep = (71±5)% T Colli = (90±5)%

P.-R. KettleMEG Review July Phase C Post Solenoid Remember !!! PSC only a Test Solenoid PSC-Solenoid 20cm Bore Beam Line 32 cm Bore Remember !!! PSC only a Test Solenoid PSC-Solenoid 20cm Bore Beam Line 32 cm Bore Triplet 2 1 Solenoid WIEN Filter Colli. Trip. µ+µ+µ+µ+ e+e+e+e+ e+e+e+e+ µ+µ+µ+µ+ Integrated Rate After Solenoid 4cm 1800µA N µ ~6.1·10 7 µ + /s (1.1·10 8 µ+/s 6cm Tg.) Beam Spot: σ X ~ 5.3 mm σ Y ~ 6.5 mm Transmission Factor Solenoid T Sol = 71 % Integrated Rate After Solenoid 4cm 1800µA N µ ~6.1·10 7 µ + /s (1.1·10 8 µ+/s 6cm Tg.) Beam Spot: σ X ~ 5.3 mm σ Y ~ 6.5 mm Transmission Factor Solenoid T Sol = 71 % Single Node SNM Double Node DNM Previous Excitation Curve DNM confirmed DNM focus Z A DNM focus Z A Previous U-Branch A A With larger Bore i.e. BTS T>71%

P.-R. KettleMEG Review July Degrader & Stopping Distribution Measurements µ+µ+µ+µ+ CH 2 Tg e+e+e+e+ Foils CH 2 at focus Michel Range Curve using NaI: Measurement  Simulation Fix Degrader 600 µ Geant say 580µ Nearly all Stopped in 400µ R ~ 870 µ CH 2 Degrader Target AIR Target Thickness vs. NaI Rate VAC Target Gives R Mean = 1150µ Equiv GEANT + TRIM 88% STOP in 400µ Tg !!! Solenoid Fix Degrader Var. Tg 88% stopped in 400µ CH 2 Tg.

P.-R. KettleMEG Review July Beam Transport Solenoid BTS Design in conjunction with Novosibirsk + PSI Magnet Group + Tokyo + PSI Magnet Group + Tokyo Superconducting solution Chosen Superconducting solution Chosen Present Design under study L CRYO = 2800 mm L COILS = 2630 mm D BORE = 320 mm B CENT = T Optics + further simulations underway BTS COBRA BTS COBRA

P.-R. KettleMEG Review July Future Priorities: Finish simulations for design BTS  end JulyFinish simulations for design BTS  end July Complete BTS Design together with Novosibirsk, PSI, TokyoComplete BTS Design together with Novosibirsk, PSI, Tokyo  Manufacture + Delivery by late Spring 2004  Manufacture + Delivery by late Spring 2004 Start Design for new Triplet 1 Wagon + Quads (µE4 Beam)Start Design for new Triplet 1 Wagon + Quads (µE4 Beam)  ready for Insertion Shutdown 2003/2004  ready for Insertion Shutdown 2003/2004 Start Design of Target System for Experiment & choose optimalStart Design of Target System for Experiment & choose optimal Degrader positioning Degrader positioning Continue Data Analysis of Beam DataContinue Data Analysis of Beam Data New vertical Separator requested ( MEG, µLAN, µSR) New vertical Separator requested ( MEG, µLAN, µSR)  vertical WIEN Filter MANDATORY for MEG  vertical WIEN Filter MANDATORY for MEG

P.-R. KettleMEG Review July Summary/Conclusions Satisfactory Beam Line Solution has been achieved for MEG with a complete test of components up to COBRA injection Separator Transmission of (71±5)% achievedSeparator Transmission of (71±5)% achieved Rate of 8.5·10 7 µ + /s at 1.8mA with 4cm Target at I/P SolenoidRate of 8.5·10 7 µ + /s at 1.8mA with 4cm Target at I/P Solenoid (1.5 ·10 8 µ + /s at 1.8mA 6cm Tg Proposal) (1.5 ·10 8 µ + /s at 1.8mA 6cm Tg Proposal) µ/e Separation of 11.8cm at Collimator  7.2σ achievedµ/e Separation of 11.8cm at Collimator  7.2σ achieved Using a small Bore Solenoid a Transmission of 71% obtainedUsing a small Bore Solenoid a Transmission of 71% obtained rate 6.1·10 7 µ + /s at 1.8mA with 4cm Target rate 6.1·10 7 µ + /s at 1.8mA with 4cm Target (1.1·10 8 µ + /s at 1.8mA 6cm Tg PROPOSAL!!!) (1.1·10 8 µ + /s at 1.8mA 6cm Tg PROPOSAL!!!) Spot-size post Solenoid of σ X =5.3mm, σ Y =6.5mm achieved Spot-size post Solenoid of σ X =5.3mm, σ Y =6.5mm achieved equivalent to spot-size in Proposal at Target equivalent to spot-size in Proposal at Target 88% of ALL µ + STOPPED in Thin Target of PROPOSAL 88% of ALL µ + STOPPED in Thin Target of PROPOSAL Lots more work still needed e.g. BTS, Target System Lots more work still needed e.g. BTS, Target System

P.-R. KettleMEG Review July Time Schedule Beam line : Test Milestone AssemblyDesignManufacture Studies Solenoid BTS Triplet 1 Target Milestone Choice “U”/”Z” + Method Method JanuaryFebruaryMarchAprilMayJune Shutdown PMC + Laser Hut + Sindrum 2 removal removal Insertion Triplet 1 COBRA installation COBRA installationBTS Beam Line Commission- ing starts

P.-R. KettleMEG Review July  E5 Area Layout Following Slides from Stefan Ritt

P.-R. KettleMEG Review July Permanent installation of MEG experiment Concurrently run other experiments No need of rail system if – –Beam line elements are removed – –Concrete wall in front of MEG detector COBRA + most electronics on platform LXe storage tanks on separate platform Calorimeter on small rail system 500 kg crane on top of platform “curtain” and A/C around platform Permanent installation of MEG experiment Concurrently run other experiments No need of rail system if – –Beam line elements are removed – –Concrete wall in front of MEG detector COBRA + most electronics on platform LXe storage tanks on separate platform Calorimeter on small rail system 500 kg crane on top of platform “curtain” and A/C around platform Ideas for  E5 area

P.-R. KettleMEG Review July Area Layout optional wall small rail electronics LXe storage compressor LN 2 line Trigger & DAQ HV

P.-R. KettleMEG Review July Platform Design COBRA RACKS floor cover (removable) “double floor”

P.-R. KettleMEG Review July COBRA LXe Calorimeter curtain (transparent plastic) removable cover (wood) crane

P.-R. KettleMEG Review July Electronics HV splitter DRS splitter DRS signal HV fiber

P.-R. KettleMEG Review July Current design status (June 24 th )