DEPARTMENT OF PUBLIC WORKS Presentation to Joint meeting of Portfolio Committees on Home Affairs and Public Works on INFRASTRUCTURE EXPANSION FOR DHA 19.

Slides:



Advertisements
Similar presentations
Town of Dryden, NY :: Hamlet of Varna – Community Development Plan Public Workshop Project Scoping/Issues Identification December 1, 2010.
Advertisements

On the Customs front, massive changes have taken place under the Customs Modernisation Programme which was launched two years ago. As with Revenue, Customs.
SA Health Car Park Reform. Project Implementation Guiding Principles >Minimise impact to staff, patients and families >Ensure proactive engagement with.
FEASIBILITY STUDIES INFORMATION SESSION. OVERVIEW  Background and approach the feasibility studies  Guidelines ♦Discussion of terms of reference ♦Sustainability.
Bath and North East Somerset – The place to live, work and visit BUDGET FAIR 2014 Cllr David Bellotti Cabinet Member for Community Resources.
1 DEPARTMENT OF PUBLIC WORKS PROGRESS REPORT ROAD MAINTENANCE, JOB CREATION AND POTHOLES by ACTING DDG: PROJECTS (OBED MOLOTSI) 01 November 2011.
Public Border Operators Association Border Infrastructure Project Updates Canada – United States Transportation Border Working Group Meeting April 19 –
SAVANNA CITY - Gauteng’s largest privately initiated development Background information to the Premier.
Helen Bowden Nurses Home “Jewel of Granger Bay” PROVINCIAL REGENERATION PROGRAMME INVESTOR CONFERENCE 26 March 2014.
South Coast Rail Project February 28, 2014 Stoughton Town Hall.
1 PRESENTATION TO THE PORTFOLIO COMMITTEE ON HOME AFFAIRS STATUS OF THE AMENDMENTS TO THE REFUGEE ACT AND RELOCATION OF REFUGEE RECEPTION OFFICES CLOSER.
1 Nottingham-Lincoln Stakeholder Board – Network Rail update Doreen Marsh – 26 th February 2015.
MTF Rail Development Forum
CANADA MORTGAGE AND HOUSING CORPORATION1. Municipal Infrastructure Lending Program Housing-Related Infrastructure HELPING MUNICIPALITIES BUILD STRONGER.
DEPARTMENT OF COOPERATIVE GOVERNANCE AND TRADITIONAL AFFAIRS PRESENTATION TO THE PORTFOLIO COMMITTEE Municipal Infrastructure Grant (MIG) Projects and.
MODERN VENTURES (Pty)Ltd t/a NORTHERN GATEWAY CITY PORTION 2 OF 36-NQ
Calais, ME-St. Stephen,NB Border Crossing Project A Case Study.
PC Meeting July 1, 2015 CUP 15-02/DR 15-06/DR
1 1 OPERATIONAL RESPONSE SERVICES: BORDER POLICING INFRA STRUCTURE/ OFFICE AND RESIDENTIAL ACCOMODATION: PORTS OF ENTRY Briefing by SAPS to the Portfolio.
New Decade - New Challenges Annual Conference September 2010 Water Services Training Group 14 th Annual Conference New Decade – New Challenges 9 th September.
Joint Transport Forum I Rapid Transit Line 2 Our Future Transport I West of England Sub Region.
Presented by Themba P Wakashe Director-General REPORT ON THE UNSPENT BUDGET 2009/10 TO STANDING COMMITTEE ON APPROPRIATIONS.
Capital Improvement Program. During the Annual Strategic Action Plan (SAP) evaluation, long-term needs and priorities are identified by City Council Capital.
STANDING COMMITTEE ON APPROPRIATIONS Presentation by Zandile Mathe Deputy Director General: NWRI 11 February Briefing by Department of Water Affairs.
1 Portfolio Committees on Correctional Services and Public Works Kimberley Correctional Centre 18 August 2010.
SUSTAINABLE LIVELIHOODS – EPWP AND TOURIST GUIDES 23 AUGUST 2011.
PRESENTATION TO THE ROAD PAVEMENT FORUM 09 November 2010 Progress & Update since the Road Construction & Maintenance Summit.
EPWP PRESENTATION TO PORTFOLIO COMMITTEE. Principles informing IDT’s role Adding value to government development agenda Delivery of measurable sustainable.
Public Border Operators Association Border Infrastructure Project Updates United States – Canada Transportation Border Working Group Meeting October 27.
Limpopo - Health1 Report to the Select Committee on Finance on the Provincial Budgets and Expenditure Review 2001/ /08 and Conditional Grants and.
PUBLIC MEETING November 19, 2003 Lower Manhattan Redevelopment D015183, PIN NYCD NYSDOT, REGION 11 Route 9A Project.
DEPARTMENT OF LABOUR Expenditure – 30 JUNE MAIN DIVISIONS OF THE VOTE.
1 Re Kgabisa Tshwane Programme. 2 Background October 1997 Cabinet decision that Departments headquarters must locate in the inner city of Tshwane June.
Presentation to Portfolio Committee on Police on SAPS Communication Projects By: Mr Sithembiso Freeman Nomvalo
MANGAUNG HOST CITY PRESENTATION TO LOCAL GOVERNMENT AND SPORTS PORTFOLIO COMMITTEE GEORGE MOHLAKOANA PARLIAMENT 29 AUGUST 2006.
1 PRESENTATION TO SELECT COMMITTEE DATE: 14 MAY 2013.
Presentation of the Property Rates Debt to the Port Folio Committee on Cooperative Governance & Traditional Affairs 25 October 2011 Presented by: Cathy.
1 PRESENTATION TO THE PORTFOLIO COMMITTEE ON THE OVERVIEW OF THE NDPW PRESENTED BY THE TOP MANAGEMENT COMMITTEE 26 MAY 2004.
Click to edit Master subtitle style 2/16/12 LEASE MANAGEMENT 2011/12 Financial year PRESENTATION TO THE PORTFOLIO COMMITTEE ON POLICE
Roads and Transport Limpopo 02 August Infrastructure Budget allocation for 2011/12 Upgrading of roads=R770,273m Preventative maintenance= R375,
October 2011 Schlumberger Site Assessment 36 Old Quarry Road Ridgefield.
Briefing to the Portfolio Committee on the Comparison on Procurement Methodologies 6 June 2006.
1 DEPARTMENT OF PUBLIC WORKS P ROGRESS REPORT ON THE LEBOMBO PORT OF ENTRY 22 FEBRUARY 2011.
EPWP Progress Reports to Portfolio Committee Presented by: Stanley Henderson DDG: EPWP 01 March
THUBELISHA HOMES CLOSURE REPORT Presented to the Portfolio Committee on 8 July 2009.
DPW PRESENTATION TO PORTFOLIO COMMITTEE ON CORRECTIONAL SERVICES 09 FEBRUARY 2010.
INFRASTRUCTURE EXPANSION IN RELATION TO THE DEPARTMENT OF HOME AFFAIRS (DHA) Presentation to Portfolio Committees of Home Affairs and Public Works 19 September.
1 BUDGET VOTE 5: DEPARTMENT OF PUBLIC WORKS Inez Stephney Research: Portfolio Committee on Public Works 18 June 2009.
EPWP Phase II Portfolio Committee Cape Town Feb 2009.
DEPARTMENT OF PUBLIC WORKS Presentation to Portfolio Committee on SAPS PROVISION OF INFRASTRUCTURE AT LEBOMBO LAND PORT OF ENTRY 17 June
QUARTERLY PERFORMANCE OF THE MUNICIPAL INFRASTRUCTURE GRANT (MIG) – 2005/06 AND 2006/07 FINANCIAL YEARS Presentation to the Select Committee On Finance.
BRIEFING ON SCHOLAR TRANSPORT TO THE PARLIAMENTARY PORTFOLIO COMMITTEE ON TRANSPORT By Mr George Mahlalela Director General 12 April April 2011.
Department of Transport Joint Budget Committee Hearings Medium Term Budget Policy Statement 2005 Theme 3: Employment and Economic Development 1 November.
National Department of Public Works Republic of South Africa National Department of Public Works Republic of South Africa 25 MAY 2004 JAMES MASEKO DIRECTOR-GENERAL.
1 Select Committee on Economic Development Progress relating to the implementation of Integrated National Electrification Programme (INEP)
Strategic Planning in Cambridgeshire and Peterborough Councillor Peter Moakes Chair, Joint Strategic Planning & Transport Member Group John Williamson.
Industrial Parks Revitalization Programme Presented to the Portfolio Committee on Trade and Industry 12 April
2014 Adjustment Appropriation
Housing Regeneration Projects Update to SPC
North West provincial Treasury presentation on Conditional Grants and Capital Expenditure as at 30 June 2008.
Presentation of the 4th Quarter Financial Performance of the Department to the Standing Committee on Appropriations (SCOA) 24 August
Mr Ntandazo Vimba and Henri Marais
BUDGET PRESENTATION TO THE SELECT COMMITTEE ON SOCIAL SERVICES
Building DHA as a Security Department
PRESENTATION TO THE PORTFOLIO COMMITTEE ON HOME AFFAIRS
PORTFOLIO COMMITTEE ON SOCIAL DEVELOPMENT 13 MARCH 2019
POVERTY ALLEVIATION INTERVENTIONS
National Department of Public Works Immovable Asset Management
Building a secure Home Affairs
HOME AFFAIRS IDENTIFICATION SYSTEM (hanis)
Presentation transcript:

DEPARTMENT OF PUBLIC WORKS Presentation to Joint meeting of Portfolio Committees on Home Affairs and Public Works on INFRASTRUCTURE EXPANSION FOR DHA 19 September 2012 By Mandla Mabuza: DDG:PROJECTS

Table of Contents Lebombo Background Scope of work Future developments Skilpadhek Background Scope of work

CONTEXT OF DEVELOPMENT OF PORT OF ENTRIES The strategic management of Border Environment remains with BCOCC It is acknowledged that in 2007 SARS assumed the leadership of BCOCC The development of commercial port of entries ie; Lebombo, Skilpadhek, Vioolsdrift, Golela were prioritised for acceleration to meet the objectives of 2010 World Cup The Vioolsdrift, Golela, are fully completed with Lebombo partially completed (phase 1) and Skilpadhek to be fully completed by end of 2012

BACKGROUND OF LEBOMBO 1.The project to redevelop Lebombo was initiated to develop a One Stop Port of Entry Facility to be shared by both South Africa & Mozambique. 2.The scheme or master plan received concurrence as the preferred model by BCOCC, led by SARS on the advise of the International Consultants under SARS. 3.The structure was designed to be positioned on the border line of the two countries based on multi-level floors to cater for passenger cars, pedestrians and buses. 4.The freight path was to cut across the high slope to lead to the Freight Clearing Facility on the Mozambican side 5.These main features formed the original scope of work for the One Stop Border Post. 6.DPW as the infrastructure Department developed the design further to the stage of contract documentation and costing.

LEBOMBO PORT OF ENTRY 1.The estimate costs of the structure above including the Freight Path, Freight Facility, Railway Station added to R 1,473,059,160 in The Department could not receive funding commitment from National Treasury to continue with the One Stop Border Post development. 3.As a result DPW opted to consult all stakeholders to address the need for a freight bypass road, and covert the temporary unit structures into a permanent pedestrian facility – this work was to form part of Phase 1 of the development.

BYPASS ROAD The Bypass Road development was completed and handed over in April The government of Mozambique equally completed their part of the bypass road. In discussions with BCOCC stakeholders four Inspection Canopies were built to enable inspection of trucks on a routine basis. These canopies were not fitted with any ablution facilities, and the requirements for ablution became evident when Police used the canopies as permanent stations for searching vehicles. The development of ablution facilities and supporting infrastructure remains in the scope of the next development phases.

FREIGHT PROCESSING AREA View of the Freight Processing Building Driveway to Freight Inspection Canopy The Freight Processing Building supports the bypass road. Occupation by User Department has been confirmed. The trucks volume has increased and this further warrants the extension of the parking area which will form part of the next phases of construction.

PEDESTRIAN FACILITY The building now known as the Pedestrian Facility was originally conceptualised a temporary structure for operations when the Construction of the One Stop Building Facility commenced. When it was confirmed that the amount required would not be secured, the facility was converted to process pedestrians on the basis of joint operations between SA/Mozambique. The layout and specification was well work-shopped with Stakeholders and completed as such. An official request by the Accounting Officer of DHA to reconfigure the internal layout was received by the Department in July 31st Entrance/ Exit to Mozambique Entrance/ Exit to South Africa Existing Queuing System

Pedestrian Path to Mozambique Elevation of Pedestrian Facility The pedestrian facility is currently vacant. The DHA has confirmed that they would occupy the facility once the alterations are completed to address operational needs of all users. In consideration of the DPW procurement processes the Project can only be completed in April PEDESTRIAN FACILITY

JOB CREATION( YOUTH) The program was piloted at Lebombo to allow unskilled and unemployed youth to enter the job market by training them in the area of Horticulture and cleaning services Recruited from Nkomazi Municipality by joint task team consisting of EPWP and Municipality The program has progressed to stage of forming independent cooperatives from those who showed commitment and discipline during the first 12 months of training and employment Through EPWP this corporative will have direct contracts as informed by DPW procurement policies It is envisaged that contract position of Supervisor will be finalised soon

FUTURE DEVELOPMENT - PROJECTS Requested re-configuration of the Pedestrian Facility will be executed in the next phase – it will include Bullet Proof Glass for SAPS, Ablution Facilities Upgrade of Perimeter fence and associated civil works Relocation of Government Vehicle Garage Extension of Bypass Road and Truck Parking Area including ablution facilities at canopies and dust control mechanisms. Upgrade of the current Operational Building (emigration building) to process outgoing passenger vehicles. Conversion of old Ablution Block to immigration building to process incoming passenger vehicles The development of the operational buildings will follow the joint operation needs for both Countries unless informed otherwise by DHA

PROPOSED REFUGEE CENTERS 1.Total budget allocated for the current financial year is R110m ring-fenced under BCOCC 2.Only Lebombo Refugee Reception Centre in terms of identification of site has been explored. Beitbridge and Maseru border posts will be our next centres of focus. 3.We are awaiting approval from Inkomazi Municipality and Provincial Dept of Economic Development and Tourism purchase/lease/swop of existing Tourism land and building in Komatipoort. 4.R30 million has been budgeted for no 2 above

TRAFFIC GROWTH There is evidence of increased movement of heavy trucks into Mozambique transporting goods from the north of Limpopo in addition to traffic from Gauteng It further warrants the expansion of parking space for trucks at Lebombo It further motivates needs to address the challenges of dust at the truck processing area

SKILPADHEK PORT OF ENTRY To provide : Status of Construction of Skilpadhek Border Post And Delays of the Project

CONTEXT OF DEVELOPMENT The Skilpadhek development was informed by potential growth of freight traffic connecting South Africa to SADC through Botswana It was conceptualised as a two stop port of entry The old buildings are within the development path of the traffic circle and will be demolished once relocation to new operational building has being completed Because of its remoteness the development of residential area remains necessary, though a challenge of securing land for government use remains. Process to acquire land from the local Tribal Authority is underway

PROJECT STRUCTURE The development of Skilpadhek was through three major contracts being; 1. The Civil Contract now complete, 2.The Housing Complex, 3.Main Border Operation Contract, which is currently 89% complete Pedestrian Control Building= 98% Complete Toilet North= 95% Complete Pedestrian Walkway East= 98 % Complete Pedestrian walkway: West= 60% Complete Gate Control East= 78% Complete Gate Control West= 70% Complete Light Vehicle & Bus Buildings= 100% Complete Operational Building= 100% Complete Official Vehicles Parking= 100% Complete Construction of new roads= 92% Complete

CIVIL CONTRACT The contract covers the Bulk Water Supply & Sewer Works. Overall project status is 100% complete, practical completion was taken in 2010 Construct Bulk Water Main and bore holes= 100% Sewer Pump Station and Line=100% Reservoir (Rehabilitation Work)=100% Sewer & Sewer Line manholes=100% Sewer Treatment Works=100%

THE FOLLOWING IMPACTED ON THE PROJECT 1.The civil infrastructure for Operational Area was delayed by acquisition of a tavern and a motel which were private businesses. The tavern and the motel were eventually acquired and demolished to make way for development 2.Relocation of Electrical (by Eskom) and Telecommunications infrastructure (by Telkom) in the area earmarked for development. The process of acquiring these private businesses was completed 12 months after site was handed over to the contractor for construction. 3.Non performance of nominated sub-contractors, which were later replaced 4.Negligence by appointed consultants failing to identify the existence of the mine led to a cancellation of the Residential Contract, the matter remain the subject of investigation by SIU