Universities Space Research Association Page 1 HAWC High-resolution Airborne Wideband Camera How Are We Coming along? Bob Pernic Project Manager Al Harper.

Slides:



Advertisements
Similar presentations
MICE Superconducting Solenoids: Status and Update RAL: T W Bradshaw M Courthold J Rochford M Hills D Baynham Oxford: J Cobb W Lau S Yang MICE.
Advertisements

Overview of GRETINA I-Yang Lee Lawrence Berkeley National Laboratory GRETINA Auxiliary Detector Workshop Washington University January 2006.
HAWCPol / SuperHAWC Software & Operations J. Dotson July 28, 2007.
GLAST LAT ProjectLAT Engineering Meeting, April 1, 2003 GLAST Large Area Telescope: Performance & Safety Assurance Darren S. Marsh Stanford Linear Accelerator.
MICE Collaboration meeting at CERN March 28 – April 1, 2004 MICE Cooling Channel --- AFC Module work group report Wing Lau – Oxford.
Global Magnet Systems including Field Mapping MICE Project Board 28 th June 2011 M Courthold – RAL R Preece - RAL.
LarTPC Electronics Meeting Current Work at MSU Fermilab Dan Edmunds 23-February-2010.
HARPS-NEF PDR December 6 & 7, HARPS-NEF Program Project Manager Tim Norton.
Spectrometer Solenoids and Coupling Coils Primary Activities and Risks Going Forward Spectrometer Solenoids Completion of SS#2 magnetic mapping Completion,
LSU 01/18/2005Project Life Cycle1 The Project Life Cycle Project Management Unit, Lecture 2.
GlueX Solenoid Update George Biallas May 12, 2010 GlueX Collaboration Meeting.
RF Cavity / Coupling Coil Module
Spectrometer Solenoid Update Steve Virostek Lawrence Berkeley National Lab Roy Preece Rutherford Appleton Lab October 28, 2011 MICE Collaboration Meeting.
Electrical Integration WBS Eric J. Mannel Columbia University Electronics Project Engineer VTX and FVTX.
PACS IBDR 27/28 February 2002 PACS DEC/MEC1 Detectors & Mechanisms Controllers (DEC/MEC) J.-M. Gillis Centre Spatial de Liège (B)
PACS IBDR 27/ BOLC/BOLA1 BOLC / BOLA SAp/DAPNIA/DSM/CEA C. CARA WE Design Team: A. BOUERE - N. DEVIN - G. DHENAIN - E. DOUMAYROU M. SEYRANIAN -
ASPERA-3 Sep. 25, 00 Monthly Status Report ASPERA Monthly Status ReportMonthly 9_25/ Page 1 Monthly Status Report Report due 9/25/00 Schedule statused.
Universities Space Research Association Page 1 HAWC Optical and Photometric Specifications 27 July 2007.
PACS IIDR 01/02 Mar 2001 Instrument Interfaces1 PACS FPU Opto-mechanical Design Overview and Interfaces J. Schubert MPE.
ASPERA-3 April. 25, 01 Monthly Status Report ASPERA Monthly Status ReportMonthly 4_25/ Page 1 Monthly Status Report Report due 4/25/01 Schedule statused.
Linac Marx Modulator Update Trevor Butler 5/20/2015.
AIDA FEE64 development report August 2010 Progress after Texas CAD work Manufacturing 25th August
ASPERA-3 Apr. 25, 00 Monthly Status Report ASPERA Monthly Status ReportMonthly 4_25/ Page 1 Monthly Status Report Report due 4/25/00 Schedule statused.
Electrical Integration CM38 Steve Griffiths & Ian Mullacrane.
CMS ECAL End Cap Meeting CERN 19 June to 23 June 2000 A.B.Lodge - RAL 1 ECAL End Cap High Voltage Cards and 2000 Electrical/Thermal Model. Progress on.
Evaporative Heater Design, qualification and planning M.Olcese PRR SCT off-detector cooling PRR SCT off-detector cooling March March 2005.
October 4-5, Status of ARRA funded AIPs Electron Lens Scope, Cost, and Schedule Wolfram Fischer October 4, 2010 Electron Lens.
Hall D Online Meeting 27 June 2008 Fast Electronics R. Chris Cuevas Jefferson Lab Experimental Nuclear Physics Division 12 GeV Trigger System Status Update.
Ronald Lipton PMG June Layer 0 Status 48 modules, 96 SVX4 readout chips 6-fold symmetry 8 module types different in sensor and analog cable length.
THE PROJECT LIFE CYCLE PROJECT MANAGEMENT LIFE CYCLE LSU 01/18/2005 PROJECT LIFE CYCLE 1.
3.1.1 Optics, Optical Corrector, Mechanical Systems M. Johns, C. Claver.
PACS IIDR ESTEC 01/02 March 2001 System Engineering 1 PACS Instrument Intermediate Design Review (IIDR) Reinhard Katterloher System Engineering DDVP, Model.
Spectrometer Solenoid Update Steve Virostek Lawrence Berkeley National Lab MICE Collaboration Meeting #28 Sofia, Bulgaria.
M. Gilchriese U.S. Pixel Mechanics Overview M. G. D. Gilchriese Lawrence Berkeley National Laboratory April 2000.
DBSP-R Upgrade Progress Review The DBSP-R Team DBSP-R Progress Review.
ASPERA-3 Mar. 25, 00 Monthly Status Report ASPERA Monthly Status ReportMonthly 3_25/ Page 1 Monthly Status Report Report due 3/25/00 Schedule statused.
Jan 15, 2004WFC3 TIPS – John W. MacKenty1 WFC3 TIPS Presentation January 15, 2004 Optical Stimulus.
P. Shanahan Nov 15, 2003 Page 1 MINOS WBS 2.3: Electronics, DAQ and Database Status Accomplishments since May review Near Detector Electronics production.
UK Update Package Managers Meeting 001 Roy Preece 13 th January 2014.
Solar Probe Plus A NASA Mission to Touch the Sun March 2015 Instrument Suite Name Presenter's Name.
MICE Coupling Coil Testing at Fermilab All Experimenters Meeting Ruben Carcagno March 19, R. Carcagno - MICE CC Testing at Fermilab3/19/2012.
Managed by UT-Battelle for the Department of Energy SCL Vacuum Control System Upgrade Derrick Williams
1 SOFIA Science Instrument Trimesterly Review T1 ‘09 (Incremental Review) Harvey Moseley, Dominic Benford, Johannes Staguhn, George Voellmer NASA / GSFC.
1 FVTX Monthly/Quarterly Report January 2009 Cost Summary Schedule Summary Current technical status of each WBS item.
Pixel power R&D in Spain F. Arteche Phase II days Phase 2 pixel electronics meeting CERN - May 2015.
Mar 18, 2003PFIS CDR1 Control System Summary of Changes Since PDR All the motors, drivers, sensors, switches, etc. have been chosen Built up a mechanism.
1 FLITECAM December 11, 2008 Ian McLean (Principal Investigator) UCLA Infrared Laboratory University of California, Los Angeles.
1 FLITECAM April 28, 2009 Ian McLean (Principal Investigator) UCLA Infrared Laboratory University of California, Los Angeles.
SRR and PDR Charter & Review Team Linda Pacini (GSFC) Review Chair.
March 25, FVTX Monthly/Quarterly Report June, 2009 Technical Status, Cost & Schedule Melynda Brooks, LANL.
Original 1998 EOS Program Cal/Val Remote Sensing Instrument Suite.
1 Airborne Science Program EMASHSI Kick Off Meeting Interfaces NASA Ames Research Center University of California Santa Cruz Airborne Science & Technology.
IPHC-LBL-BNL video conference 19 Jan 2007 HFT development MimoStar2 based telescope.
BSMIan Pain, UK ATC SPIRE Instrument Intermediate Design Review April 23, RAL 1 Beam Steering Mirror Sub-System IIDR Overview Ian Pain UK ATC Colin.
Preparations to Install the HBD for Run 6 Craig Woody BNL PHENIX Weekly Meeting January 26, 2006.
1 Kazuhiro Yamamoto Institute for Cosmic Ray Research The university of Tokyo LCGT internal review (Cryogenic payload) 30 January 2012.
LCLS-II Prototype Cryomodule Vacuum Vessel and HGRP Tom Peterson 4 December 2014 Design Review.
1 BNL LHC Hi-Lumi QXF Vertical Test Facility Status Update M. Anerella, H. Hocker, P. Joshi, P. Kovach, A. Marone March 28, 2016.
Status of Vertical Test Stand at RRCAT P Shrivastava, P Mohania,D.Baxy, Vikas Rajput S C Joshi, S Raghavendra,S K Suhane RRCAT, Indore November 26, 2012.
G R 2004 Plan Update LIGO Systems meeting 22 Jan 04 dhs.
S A Griffiths CM42 June 2015 Electrical & Control.
WBS 1.03 Readout Systems Scope, Cost and Schedule
Brief Status SPS Prototype PSB Prototype Installed in LS1
LCLS-II Cost Details E. Daly / C. Hovater / M. Wiseman with help from Accel Ops and Engineering 03-AUG-2017.
LIU Wire Scanner Milestones June 2017
David Montanari / Johan Bremer Jun 11, 2015 Rev. 1
Mini-drawers, FE-ASIC , Integrator
WP02 PRR: Master Oscillator and RF Reference Distribution
Control System Summary of Changes Since PDR
Test Beamline System Requirements and Charge to PDR Committee
Presentation transcript:

Universities Space Research Association Page 1 HAWC High-resolution Airborne Wideband Camera How Are We Coming along? Bob Pernic Project Manager Al Harper Principal Investigator April 2009 Review

Universities Space Research Association Page 2 Development Status Test Cryostat :Retired Flight Cryostat :Operational Housekeeping System :Operational ADR :Operational OMS :Operational Detector :Operational Electronics :Operational. Software :General User interfaces coming along nicely. Data reduction software in development. Internal Optics :Operational Fore-optics and calibration system: Detailed design underway Flight System Integration:Work in progress

Universities Space Research Association Page 3 Airworthiness Status (Similar to recent previous reviews) Cryostat, ADR, & OMS Assemblies: approved Electronics, Detector, & Optics Assemblies: Resubmission on hold Revised drawing package:Being updated System Safety Analysis:SSA initiated Electronics CADR:80% completed

Universities Space Research Association Page 4 December 2008 Status SubsystemTechnicalBudgetScheduleComment Cryostat Operational Optics Operational Detector Operational Electronics Fabrication of full complement complete Software No outstanding issues Integration & Testing Just completed two months test with fully integrated flight systems Airworthiness We understand the requirements ICP (Integration Commissioning Plan) Thinking about it.

Universities Space Research Association Page 5

Universities Space Research Association Page 6 Fore-optics Design

Universities Space Research Association Page 7 March/April 2009 Cold Tests (Preliminary results; tests still underway.) Electronics: Integrated, tested, and debugged complete data acquisition system (full complement of 384 channels). Noise performance meets specifications. Battery power supply for analog electronics failed because of short in manufacturer-supplied battery pack. We built up an AC power supply for current lab tests and are investigating battery problem. In lab, AC power supplies do not seem to increase noise. We may be able to fly with AC supplies, but need battery backup, at least for early flights. Encountered noise problem with externally supplied sync signal. We diagnosed and fixed the problem. Current HK and OMS cables have known grounding problems. Need to repair and/or replace before next tests. Cryogenic systems Shorted temperature sensor in middle JFET drawer initially prevented operation of two detector rows. Developed work-around by disabling one detector and re-wiring both heater circuits to use a single sensor. Performance of ADR heat switch has decreased. Adjusted cycle parameters to compensate. We are achieving full cycles and see little effect on ADR hold time. Suspect diffusion of helium gas through side-walls of switch assembly. Goddard cryogenics group will refurbish the switch before next cold tests. Little improvement in thermal performance of mechanisms after installation of superconducting motors. However, both new and old motors meet basic operational requirements. Detector performance and optics Point-spread functions for all bands. Complete set of multi-temperature iv curves to determine detector model parameters. Hot-plate signals vs. bias for all bands and pupils. Noise vs. bias for all bands and pupils. Successfully tested electrically modulated point sources to be used in fore-optics boresight system. New 200-mK baffle reduced detector backgrounds from scattered light. However, there are still some low-level ghost images from diffraction of light from out-of-field point sources. Computer systems and software New master computer and new parallel interface cards have improved system performance. System functions well with full 384- channel data electronics system. Data acquisition software now working in client/master mode. Overall operation has been reliable. Debugging and user-interface development are proceeding. Prototype data pipeline components tested with laboratory data.

Universities Space Research Association Page 8 Issues to be addressed prior to next round of tests Fix electrical shorts in cold JFET drawer Fix ground problems in HK and OMS cables Rebuild interface from external sync source to data electronics based on improved design developed during current cold tests Fabricate box for flight AC power supplies Fabricate spare Timing and Control, Auxiliary Analog, and Chopper Interface boards Put power Data Electronics power distribution board, interface connectors, and cooling system into final flight configuration Resolve issues with batteries Refurbish ADR heat switch Review performance of superconducting motors (less improvement over copper-winding motors than anticipated) Review design of 200-mK baffle. Investigate external field stop. Continue to develop/refine data acquisition and data pipeline software

Universities Space Research Association Page 9 Issues to be addressed prior to next round of tests Mitigate electrical shorts in the cold JFET - GSFC will assist. Although stray light from 200-mK baffle appears to be eliminated - further data reduction is required to determine effectiveness Electronics are functional and noise levels appear as expected. Some minor changes may be required Heat generated by Optical Mechanical System’s Super conduction Motors is problematic. Have entered into discussion of issues with the motor manufacturer to mitigate. Continue to develop/refine data acquisition software

Universities Space Research Association Page 10 HAWC Trimester Look Back Overview HAWC MilestoneCompleted Yes/No HAWC Critical Path Item Yes/No Comments Run fully integrated systems tests Yes Results of tests look good. Some systems require further attention Detailed design of warm optics. No Delay caused by reduction in budget Complete MCS integration tier 4 NoYesProject office dependent Continue data pipeline and analysis software YesNoWork in progress Continue airworthiness certification YesNoStarting this summer as scheduled

Universities Space Research Association Page 11 HAWC Trimester Look Ahead Overview HAWC MilestoneCompleted Yes/No HAWC Critical Path Item Yes/No Comments Write report on latest round of system tests No Some data reduction has been taking place while testing was in progress Minor debug electronics No Work in progress Complete detailed design of warm optics. No Work in progress Complete S.W.ClientNoYesTo be completed next GFY Work in progress Complete MCS integration tier 4 NoYesNot scheduled at this time Data analysis softwareNo Work in progress NASA flight certificationNo Work to begin the first of this year Modifications of OMS & Geneva mechanisms NoYesSome minor modification needed

Universities Space Research Association Page 12 HAWC Budget GFY09 Funding available for year2009$900,000 Total invoiced this year Approximate expenditures to date Projected Expenditures at end of FY$900,000 Projected carry over $0

Universities Space Research Association Page 13 HAWC Milestone Schedule

Universities Space Research Association Page 14 Summary Based upon our new funding levels, HAWC will be: - Moved to NASA/Dryden in mid 2012, to commence EMC testing and airworthiness certifications. (We are still grasping with the effects of the newly proposed schedule budget). -We expect to continue hardware,software and document development into Ready for science in Commissioned as Facility Science Instrument in 2013.