CDF → ORKA: Preliminary Cost and Schedule Estimates Jonathan Lewis ORKA Task Force 2 March pm Jonathan Lewis ORKA Meeting 2 March 2012date corrected by PHG 11am Backup Slides 11 ff contain more on CDF Decommissioning and Display - PHG
Status J. Lewis--CDF Decomminssioning Status2
Scope Remove CDF Demolish all external muon walls Dismantle central calorimeter Refit plugs Remove trackers Excludes dismantling Dismantle cable bridge Refurbish Solenoid Minor fixes to collision hall Ignores filling 706’ area of assembly hall Return to collision hall J. Lewis--CDF Decomminssioning Status3
Should I stay or should I go? J. Lewis--CDF Decomminssioning Status4
Assumptions and Caveats This is a very raw first pass Attempt to include all labor Not fully scheduled Many hanging tasks Mostly my estimates Input from Dave Erikson on time per foot to cut welds Input from Dervin Allen on some demolition tasks from earlier scheduling work Included labor for 1.5 year assumed duration Full time building manager Full time supervisor 50% physicist J. Lewis--CDF Decomminssioning Status5
More caveats Some short cuts Iron workers treated as straight labor Probably want fixed-price contracts Minimal M&S WAGs for crane rentals, etc. Lots of things neglected No ES&H Assumes truck drivers, etc. covered by overhead All costs are unburdened! Given this level of understanding: 100% Contingency J. Lewis--CDF Decomminssioning Status6
Costs J. Lewis--CDF Decomminssioning Status7 WBSTask Nominal Duration (days) Labor (hrs) Cost (k$) 1CDF D&D - (Decommission & Dismantle) Project Management Project Milestones Project Reviews Project Management and Oversight Experimental Facilities Detector Roll Out Remove Cable Bridge Refurbish Collision Hall Detector Roll In Counting Rooms Second Floor Counting Room Muon Systems CMP - (Central Muon Upgrade) CMX - (Central Muon Extension) IMU - (Intermediate Muon System) Tracking Detectors Silicon COT - (Central Outer Tracker) TOF - (Time-of-Flight) Calorimeters Central Plug Central Detector Endwalls Refurbish Solenoid (WAGs)
Labor Labor TypeCost ($/hr)Time (hr)Total Cost (k$) Engineer - Mech Scientist Technical Specialist Technician - Elec Technician - Mech Technician - ES&H3500 Electrician66161 Machine Shop7600 FESS Engineering10800 Welder7600 Iron Worker Total J. Lewis--CDF Decomminssioning Status8
Conclu$ion $3M bottom-up cost matches top-down guess More to do Need to work out schedule J. Lewis--CDF Decomminssioning Status9
From: Jonathan Lewis Sent: Monday, March 05, :49 PM To: Peter H Garbincius Subject: Re: Jonathan - please send me your slides from Friday's discussion of CDF Decommissioning & ORKA Here it is. While dismantling the central detector and the plugs is a big job, I know this is low. Another difference from previous estimates is that I have neglected disposal costs. My current understanding is that wire is not covered by the metals moratorium, so the cable is pretty much free to dispose of. Most of the steel would go to the railhead. The rest can go to a regular landfill, so that cost is pretty low. I'll work on revising the labor estimates in the next couple of weeks and get back to you. Regards, Jonathan(added by PHG) J. Lewis--CDF Decomminssioning Status10
Backup: CDF Decommissioning and Display Jonathan Lewis 2 March 2012
Equipment Recovery Done or in progress Pisa: Crates, HV, Pulsars for Atlas, Magic, etc. CMU: BSU PMTs for Tauwer (cosmic taus) JLab: PES, CPR PMTs for Super Big Bite Iowa: Bad CLC PMTs for novel calorimeter test SNU: L3 Computers for LQCD CD: Newest L3 computers for CDF Grid Michigan: Crates, racks, etc. for KOTO PREP: 10 pallets of NIM, Camac, HV Yet to come ASDQs for mu2e PMTs for test beam CSP counters for LBNE test TSU counters for LAPD Misc. counters and PMTs to Dubna for detector development Plug HV for Prep J. Lewis--CDF Decomminssioning Status12
J. Lewis--CDF Decomminssioning Status13 Gas racks gone Scrap Mezzanine ready for demolition MGs and test magnet ready for removal 1 st floor CR being cleared Status 11/8
Issues Proposed experiments create significant uncertainty for D&D Protoplasma ORKA Cable bridge plan assumed 20-year display phase Removing bridge before detector makes detector removal trickier Will wait until decision whether CDF will be rolled out Scaling back display plan Not putting plug on rails Lab-wide task force Evaluating interference between ORKA and IARC Considering early roll-out to prepare for ORKA J. Lewis--CDF Decomminssioning Status14
Coordination with IARC Electrical Freeing up experimental power substation Moving conduit for doorway Mechanical Coordinating moves of sprinkler and chilled water pipes for interferences with interconnects, etc. Mezzanine removal Planning (Dervin Allen) Tours for A&E, contractors, etc. Locating utilities, electrical circuits Reduced generator needs during utility work Evaluating access, connections Truck access CDF roof access etc. etc. etc J. Lewis--CDF Decomminssioning Status15
CY2012 CDF Building Improvements on D&D Budget Main Stairwell Remove abandoned chilled water pipes Enclose elevator pump 2 nd floor Improve exits Isolate conference rooms and egress paths from assembly area Collision hall Sprinklers Fire doors Exit lighting J. Lewis--CDF Decomminssioning Status16
Plans for Display Theatre Place for visitors to assemble Meet scientist? Movie? Trigger room Electronics on display Multi-touch table: Exercise in sorting events Control room Flashing screens look almost like we are running Interactive terminals: Middle school shift crews Stations for SVX, COT, Calorimeter Muons Mix monitoring plots, etc. for integrated view Collision hall North and west sides blown open Plastic covers, view of COT face, etc. South and east, closed up in running configuration J. Lewis--CDF Decomminssioning Status17
Display Effort Working with Public Affairs and Education Making posters to document our achievements Mix of hardware and physics Ben Kiliminster coordinating Interactive activities geared mostly toward middle school Cosmic-ray test stand, etc. CDF people: Ben Kilminster, Anna Mazzacane, JDL Life safety improvements in tour areas Doors, walkways Remove obstructions Remove halon, sprinkler mods J. Lewis--CDF Decomminssioning Status18
J. Lewis--CDF Decomminssioning Status19 Planned Collision Hall Layout
February-March Configure hall Open east plug, close SW IMU and S wall, open N wall to max Harvest components COT ASDQ boards, TOF PMTs, Diamond BLMs East Plug Caen crates Tours 2/14, 24 – EDIT school Mezzanine demolition Stairwell plumbing
April Assembly pit cleanout Shelves, cabinets, COT & SVX chillers 2 nd floor construction Elevator pump enclosure
May Move sprinkler pipes for IARC door Cable carrier plumbing and cables(?) First floor cables(?)
June Tours 6/11 Close plug Open 1200 ton door Remove N wall, pit steel Remove Halon squibs
July-August Remove top and bottom CSP counters New CH sprinklers New CH lighting Other CH construction (doors, etc.) Return pit steel Pull NE Arch Open west plug Install artifacts on transporter Tours 8/7?
September Install N wall Close shield door Paint CH floor Final tour configurations Plexiglass covers, etc.