Modification MOD_24_12 Amendments to the MIUN Calculator to address instances of Excessive Area.

Slides:



Advertisements
Similar presentations
1 Credit for Redispatch Small Group Review of Unconstrained MFs NAESB BPS Meeting December 14-15, 2011.
Advertisements

INTRA-DAY TRADING: Conference Call COD for Interconnector Units in WD1 Ending Overlap Optimisation Period (EOOP) 29 November 2011.
Background T&SC V9.0: The Market Operator shall not grant the status of Under Test for the purposes of this Code to Autonomous Generator Units, Pumped.
Mod_34_11 : Transition to SEM Intra-Day Trading 6 December 2011.
MOD_17_12 Report on Offered Capacity in Implicit Auctions.
Make Whole Payments Modification Proposals Modifications Committee Meeting 04 December 2014.
AUGUST 7-9, 2013 | LENOX, MA Andrew Gillespie MARKET DEVELOPMENT (413) Review of Market Rule 1: Section.
Proposal to Change the UNC AQ ‘Backstop Date’ to accommodate the 2010 Seasonal Normal Review DESC – 2nd October 2009 NOTE: Instances where TBC is stated.
Overview of Make Whole Payments Modifications Committee Meeting February 2015.
March 13, 2013 Day-Ahead Market (DAM) Clearing Process follow-up from February WMS Matt Mereness, ERCOT Manager DAM & CRR.
MPID 223 (Failure to Follow Synchronising Instruction) JGCRP 12 th November 2014 (Anne Trotter)
Law of Variable Proportions
Modifications Committee Mod_18_10: Intra-Day Trading 25 November 2010.
1 1 Slide © 2000 South-Western College Publishing/ITP Slides Prepared by JOHN LOUCKS.
Graphical Solutions Plot all constraints including nonnegativity ones
© 2007 Pearson Education, Inc. Publishing as Pearson Addison-Wesley 1 Software Design Processes and Management.
Spreading the Indirect Costs over the BOQ This Candy facility allows you to manage the spread of Indirect Costs over bill items in a controlled manner.
Mod_18_10 Intra Day Trading Conference Call Commercial Offer Data for Interconnector Units in Ending Overlap Optimisation Period (EOOP) for WD1 MSP Software.
Short Term Testing Mod 65_08 Modification Committee 25 th November 2010.
MARKET SYSTEM RELEASE UPDATE Modifications Committee Meeting 31 January 2012.
INTRA-DAY TRADING Development of Modification(s) 1st February 2011.
Day Ahead Market Working Group March 31, Agenda Review minutes - March 24 Coral Proposal - Working Group Discussion Loads/LDCs and DAM.
The Entry Capacity Transfer & Trade Methodology Statement Transmission Workstream
MARKET SYSTEM RELEASE UPDATE Modifications Committee Meeting 25 September 2012.
FERC Order No. 698 Procedures for Providing Hourly Consumption Data Spectra Energy Pipelines June 20, 2008.
INTRA-DAY TRADING Modification Development 5 April 2011.
Flowgate Allocation Option Parallel Flow Visualization Business Practices Subcommittee Meeting June , 2010.
INTRA-DAY TRADING DESIGN Changes required to the MIUN Calculation for SEM Intra-Day Trading 27 March 2012.
1 Mod_18_10 : Intra Day Trading in the SEM Working Group 4 August 19 th 2010 SEMO High-Level Impact Assessment.
PJM©2013www.pjm.com Economic DR participation in energy market ERCOT April 14, 2014 Pete Langbein.
Mod_18_10_v2 : SEM Intra-Day Trading 6 December 2011.
11 OUTPUT AND COSTS © 2012 Pearson Addison-Wesley The Firm and Its Economic Problem A firm is an institution that hires factors of production and organizes.
Chapter 5 Production. Chapter 6Slide 2 Introduction Focus is the supply side. The theory of the firm will address: How a firm makes cost-minimizing production.
Chapter 6 Production. Chapter 6Slide 2 Topics to be Discussed The Technology of Production Isoquants Production with One Variable Input (Labor) Production.
STEP 4 Manage Delivery. Role of Project Manager At this stage, you as a project manager should clearly understand why you are doing this project. Also.
A local search algorithm with repair procedure for the Roadef 2010 challenge Lauri Ahlroth, André Schumacher, Henri Tokola
Law of Variable Proportions
Entry Capacity Trading Transmission Work Stream, 5 April 2007.
MARKET SYSTEM RELEASE UPDATE Modifications Committee Meeting 27 March 2012.
Intraday Trading March RAs raised a Modification (18_10) in March 2010, proposing the implementation of “intra-day trading” in the SEM. The Modifications.
Impact Assessment Mod_17_12 : Report on Offered Capacity in Implicit Auctions 24 October 2012.
Resource Analysis. Objectives of Resource Assessment Discussion The subject of the second part of the analysis is to dig more deeply into some of the.
Trades and Transfers Workshop, 6 th November 2007.
Market Operations Standing Committee MOSC October 19, 2005 Pat Doran.
1 UNC Review Group 175 – Encouraging Participation in the Elective Daily Metered Regime 26 th June 2008.
SLIDE 1 FCAS CAUSER PAYS: STAGE 1 DISPUTE MEETING BACKGROUND 15 MARCH 2016 PRESENTED BY LOUISE THOMSON.
University Of Palestine Faculty Of Applied Engineering & Urban Planning Civil Engineering Department PROJECT MANAGEMENT Scheduling Resources and Costs.
Chapter 13 Basis Adjustments to Partnership Property
ENGINEERING MANAGEMENT (GE 404)
Algorithm An algorithm is a finite set of steps required to solve a problem. An algorithm must have following properties: Input: An algorithm must have.
Unsecured Bad Energy Debt and Unsecured Bad Capacity Debt Version 2
Correction of Minor Material Drafting Errors
Part B Unsecured Bad Energy Debt and Unsecured Bad Capacity Debt
Review of the requirements regarding Unsecured Bad Debt within I-SEM
MOD_27_18 Martin Kerin 06th September 2018
Mod_25_18 Unsecured Bad Energy Debt and Unsecured Bad Capacity Debt
Mod_38_18 Limitation of Capacity Market Difference Payments to Loss Adjusted Metered Quantity. 12th December 2018.
Credit Cover Signage and Subscript Correction
Use of Technical Offer Data in Instruction Profiling / QBOA Version 2
Use of Technical Offer Data in Instruction Profiling / QBOA Version 2
Optimisation of Entry Capacity Modification Proposal
Workgroup meeting October 2014
Mod_32_18 Working Group 2 Dublin, 13 March 2019.
Recovery of Costs due to Invalid Ex-Ante Contracted Quantities in Imbalance Settlement 25th January 2018.
Correction to No Load Cost - “and” vs “or”
Mod 09_19 - Removal of locational constraints from Imbalance Pricing
Interconnector trading in SEM 7th June 2007
Correction to COP and clarification to CNLR
Enabling Large Scale Utilisation of Class 3
and Forecasting Resources
Presentation transcript:

Modification MOD_24_12 Amendments to the MIUN Calculator to address instances of Excessive Area

Summary of the current MIUN Calculation Process Start Retrieve Input Data Rescale IUNs Create Interconnector Profile Calculate Available Energy Allocate Energy to IUs End Retrieves latest input data: IUNs, MIUNs, ATC, Interconnector Registration Data (e.g. Ramp Rate) Where ATC changes occur or there is a Deadband breach (if applicable), scale the input IUNs to ensure that a feasible Interconnector profile can be derived Profile the Interconnector as a whole, using the Original IUNs, Interconnector Ramp Rate and (if applicable) Deadband limits. In each Trading Period, calculate the area under the Interconnector profile curve. Allocate the area to Interconnector Units, fixing previously determined MIUNs first, then allocating the remainder to the Units without previous MIUNs calculated (i.e. the new Units bidding in the most recent Gate Window).

Currently, previously determined MIUNs may not be fixed if there is a change in ATC, or if the net Interconnector flow is within Deadband limits (if applicable). As part of its ongoing extension of testing, SEMO has identified a further scenario in which previously determined MIUNs may not be fixed. This scenario is known as “Extreme Ramping” and is characterised by: the Interconnector profile being constrained by the Interconnector Ramp Rate ramping over multiple Trading Periods (“Run Through”) to achieve ramping to a peak/trough of IUNs there is a change in the dominant direction of ramping between gates (EA1, EA2, WD1) “Excessive Area” occurs (i.e. the area under the Interconnector profile cannot be allocated to Interconnector Units whilst ensuring that MIUNs are fixed and |MIUN|<=|IUN|) This new scenario has never occurred in live operations. However, whilst the scenario is likely to be rare, a solution needs to be implemented to allow fixing of MIUNs between runs for these scenarios. Description of MIUN Issue Identified

“Extreme Ramping” Example – After EA1 Run EA1 IUNs EA1 Interconnector Profile / MIUNs EA1 IUNs are ramping up to 500MW. IUNs change from 200MW (TP2) to 400MW (TP3). This is greater than the Interconnector Ramp Rate and means that the target value cannot be reached until later than implied by the IUNs Interconnector dispatch profile is calculated from the sum of EA1 IUNs and is limited by the Interconnector Ramp Rate. 400MW target in TP3 is actually achieved in TP4. 500MW target in TP4 is not achieved until the end of TP4. Area under curve is allocated to the EA1 Units (i.e. MIUNs). EA1 Interconnector Ramp Rate = 5MW/min.

EA1 & EA2 IUNs EA2 Interconnector Profile / MIUNs EA2 IUNs are in a different direction to EA1. The change in net position will affect the Interconnector profile (e.g. net IUNs=0 in TP2) Interconnector dispatch profile is calculated from both EA1 and EA2 IUNs. EA2 IUNs affect the points at which ramping to 500MW starts (beginning of TP2 in EA1, beginning of TP3 after EA2). The issue arises when the area under the curve is allocated to IUs (see next slide): EA1 MIUNs first Then to EA2 “Extreme Ramping” Example – After EA2 Run EA1EA2 Interconnector Ramp Rate = 5MW/min.

EA2 Interconnector Profile / MIUNs “Extreme Ramping” Example – After EA2 Run EA1 Area – TP6 EA1 - TP6 area is 500MW. EA1 MIUNs = 500MW. EA1 MIUNs need to be fixed in subsequent runs. EA2 Area – TP6 EA2 - TP6 area is 491.7MW. EA1 MIUNs = 500MW, to be fixed. There are no EA2 IUNs (hence no energy can be allocated to these Units). “Excessive Area” occurs, as 8.3MW ( ) cannot be allocated to any Unit. Currently, the MIUN Calculation would reduce the EA1 MIUNs to ensure that Excessive Area does not occur, i.e. EA1 MIUNs would not be fixed. TP6 illustrates the issue identified. Important Note: this scenario is likely to be rare, as it relies both on Extreme Ramping and a change in direction at a subsequent gate occurring at the same time. EA1 EA2

Summary of Proposed Solution StartRetrieve Input Data Rescale IUNs Create Interconnector Profile Calculate Available Energy Allocate Energy to IUs End Excessive Area? No Adjust Profiling End Points if possible, set new MIUNs=0 if no feasible profile Yes

Proposed Solution The proposed solution aims to ensure that: previously determined MIUNs are fixed a feasible Interconnector profile is produced |MIUN|<=|IUN| in all cases The solution is as follows: 1.Each instance of Excessive Area is identified within the MIUN Calculator run. 2.Attempt to resolve each instance (in reverse chronological order) by iteratively adjust profiling points during the ramping period that causes the Excessive Area. Where profiling points can be adjusted to both eliminate the Excessive Area and generate a feasible profile, the adjusted profiling points are accepted. Where profiling points cannot be adjusted to both eliminate the Excessive Area and generate a feasible profile, the input IUNs to the MIUN calculation shall be set to zero for the Units for which MIUNs have not previously been determined. 3.Once all instances of Excessive Area are addressed as described in 1) and 2), the available energy (i.e. the area under the profile curve) is allocated in priority order to: Units for which MIUNs have previously been allocated (i.e. fixing of previous allocations); and the new Units for which MIUNs have not previously been determined, such that |MIUN|<=|IUN| in all cases.

New Terminology Last Completed MIUN Run (e.g. EA1) Interconnector Ramp Rate = 5MW/min. Current Run Start : Within the current run, the start of the period of continuous ramping within which an instance of Excessive Area occurs Current Run Stop : Within the current run, the end of the period of continuous ramping within which an instance of Excessive Area occurs Current Run – Initial Profile (e.g. EA2) Current Run Start Current Run Stop Last Run Start : Within the most recently completed run, the end of the period of continuous ramping within which an instance of Excessive Area occurs Last Run Stop : Within the current run, the end of the period of continuous ramping within which an instance of Excessive Area occurs Current Run Start Current Run Stop Interconnector Ramp Rate = 5MW/min. Remaining Area : Area under the Interconnector profile - sum(Original MIUNs) Excessive Area : where 1.Remaining Area>0 and sum(positive IUNs with no MIUNs)<Remaining Area, or 2.Remaining Area Remaining Area

Excessive Area profile and proposed solution “Extreme Ramping” Example – Proposed Solution The proposed solution: Eliminates Excessive Area Fixes previously determined EA1 MIUNs Allocates remaining area to new Units (EA2) Current Run Start – start of TP3 Current Run Stop – within TP6 Last Run Start – start of TP2 Last Run Stop – end of TP4 Proposed solution would move the ramp profiling end point (Current Run Stop) towards the previous ramp profiling end point (Last Run Stop) until the Excessive Area is eliminated and a feasible profile is produced. Moving the ramp profiling end point to the start of TP6 addresses Excessive Area, enables fixing of previous MIUNs (EA1) and maximises the amount of energy that can be allocated to EA2 Units. Adjusted EA2 profile Initial EA2 profile EA1 profile EA1 Initial EA2 Adjusted EA2 Current Run Start Current Run Stop Last Run Stop Last Run Start

Summary This Modification seeks to ensure that the MIUN calculation rules address instances where Excessive Area occurs so that: previously determined MIUNs are fixed; |MIUN|<=|IUN| in all cases; and a feasible Interconnector Dispatch Schedule is produced. The solution works by adjusting profiling end points of ramping periods that cause each instance of Excessive Area (addressing each such instance in reverse chronological order, i.e. latest first). If approved, it is proposed that the solution will be implemented as soon as can be delivered by our vendor (Amor) and tested adequately by SEMO.

Discussion and Vote