1/01/2008P.Z. Takacs1 RTM Testing Issues B-27 session discussion PZ Takacs 22 March 2012.

Slides:



Advertisements
Similar presentations
ZTF Mechanical Walkthrough Matthew Hoff ZTF Technical Meeting 1.
Advertisements

Results of Acceptance Tests of Hyper Suprime-Cam CCDs Yukiko Kamata, Hidehiko Nakaya, Satoshi Miyazaki National Astronomical Observatory of Japan.
1 HICIAO-Assembly-Procedure Prepared for HICIAO CDR Author: Vern Stahlberger Institute for Astronomy Date:
Manchester 09/sept/2008A.Falou & P.Cornebise {LAL-Orsay}1 CALICE Meeting/ Manchester Sept 2008 SLAB Integration & Thermal Measurements.
ModICE Modular Integrated Connector Enclosure
Installation. Indoor Unit Installation Typical Installation.
Corner Raft Conceptual Design Corner Raft Conceptual Design Kirk Arndt, Ian Shipsey Purdue University LSST Camera Workshop SLAC Sept , 2008.
Vibration Sensors for Cooling Towers Challenges Cooling towers offer the vibration analyst many challenges in sensor selection, mounting and environmental.
Status of the LARP Phase II Secondary Collimator Prototype 30 September 2013 LHC Collimation WG Meeting Tom Markiewicz/SLAC BNL - FNAL- LBNL - SLAC US.
AMS-02 tracker mechanics status of assembly and integration at UniGe Outer planes: - Tests of evaporator (cooling loop) integration - Tools to develop.
AMS-02 tracker mechanics status of assembly and integration Inner tracker integration completion: - Assembly and cabling - Temperature and magnetic field.
Cryostat Assembly 17 September 2008 Martin Nordby, Rafe Schindler, Gary Guiffre, Rick Van Berg.
Integration and Test 14 October 2008 Martin Nordby.
Status of the LARP Phase II Secondary Collimator Prototype 14 October 2013 LHC Collimation WG Meeting Tom Markiewicz/SLAC BNL - FNAL- LBNL - SLAC US LHC.
Cryostat Structural, Thermal, and Vacuum Systems 14 October 2008 Martin Nordby, Gary Guiffre, John Ku, John Hodgson.
Network Storage and Appliance Box Build By: Cubatic Engineering 01/09/2015.
Automated HIC assembly A. Di Mauro ITS-MFT mini-week
DELTA Quadrant Tuning Y. Levashov, E. Reese. 2 Tolerances for prototype quadrant tuning Magnet center deviations from a nominal center line < ± 50  m.
Eddington Kick-Off. Vienna, September 17th, 2001 T.Muñoz/C.Laviada (INTA) 1 EddiCam: The Eddington Photometric Camera Preliminary Design Layout.
SAM PDR1 SAM LGS Mechanical Design A. Montane, A. Tokovinin, H. Ochoa SAM LGS Preliminary Design Review September 2007, La Serena.
LSST Electronics Review BNL January 25-26, LSST Electronics Review BNL January 25-26, 2012 Electronics Development Plan and Vertical Slice Test (VST)
MICE RFCC Module Update Allan DeMello Lawrence Berkeley National Laboratory MAP Winter Collaboration Meeting at JLab, Virginia February 28, 2011.
ZTF Cryostat Finite Element Analysis Andrew Lambert ZTF Technical Meeting 1.
Corner Raft Test Station Kirk Arndt, Ian Shipsey Purdue University LSST Camera Workshop SLAC Sept , 2008.
I&T and Operating and Support Hazards Martin Nordby Chief Mechanical Engineer LSST Camera Safety Review August 18, 2015 R1.
Hybrid Integrated Circuit
LSST Electronics Review – BNL, January LSST Electronics Review BNL January Power & Voltage Plan R. Van Berg Electronics Mini-Review.
Update on alignment kit and stave 250 frame M.Gibson (RAL) 1.
GLAST LAT ProjectDOE/NASA Mechanical Systems Peer Review, March 27, 2003 Document: LAT-PR-0XXXX Section 5.1 Grid Box Design 1 GLAST Large Area Telescope:
MARS 2 Design Review-Optomechanical Review 07 Nov 2002 GLW1 MARS 2 Mechanical Design Review.
LSST Camera Cryostat Design & Integration DOE Program Review SLAC June 2006 Rafe H. Schindler Experimental Group E - SLAC.
Vacuum system.
LARP LHC PHASE II COLL RC1 TESTS - S. Lundgren 06 June 2006 No 1 /17 LARP Phase II Secondary Collimator RC1 Collimator Test Program Plan Forward Revised.
10/26/20151 Observational Astrophysics I Astronomical detectors Kitchin pp
LSST Electronics Review – BNL, January LSST Electronics Review BNL January Electronics Development Plan Goals and Plans for
G5 Beam Instrumentation D. Gassner, E. Pozdeyev 4-09.
Oct 17, 2001SALT PFIS Preliminary Design Review1 Southern African Large Telescope Prime Focus Imaging Spectrograph Mechanical Mechanism Design Michael.
MICE RFCC Module Update Allan DeMello Lawrence Berkeley National Laboratory MICE CM29 at RAL, UK February 17, 2011.
Hybrid Mechanical/Thermal Design Ray Thompson / Manchester FP420 meeting Torino 11/12 July 06.
DBSP-R Upgrade Progress Review The DBSP-R Team DBSP-R Progress Review.
MFT WG5: ladder disk and global assembly Stéphane BOUVIER & Sébastian HERLANT MFT WG7: Mechanics and Thermal studies Jean-Michel BUHOUR & Emili SCHIBLER.
THEMIS Instrument PDR 1 UCB, April 19-20, 2004 Spin Plane and Axial Boom Preamps & Sensor Cable Fabrication Critical Design Review Daniel Schickele University.
LMQXFA Cold Mass Assembly Antonios Vouris Fermilab February 3, 2016.
PACS IBDR MPE 27/28 Feb 2002 AIV 1 PACS IBDR Test Cryostat and OGSE Gerd Jakob MPE.
PS Module Ron Lipton, Feb A bit of History During much of the conceptual design phase of the outer tracker we had focused on the “long barrel”
LARP Collaboration Meeting Racetrack Coil Fabrication
SEPT 20, 2006 T. Brown, M. Cole, P. Fogarty, P. Goranson, K. Freudenberg, D. Williamson NCSX STAGE 2 COIL TO COIL ASSY.
LSST Camera Electronics Overview September 16, 2008 R. Van Berg for the LSST Electronics Team.
DOE CD-2/3a Review of the BTeV Project – December 14-16, BTeV Pixel Detector Pixel Module Assembly and Half-Plane Assembly Guilherme Cardoso James.
Cloudland Instruments Hawkeye Mechanical Design Snapshot Compiled April 8th, 2016.
FP420 Hybrid Mechanical Design Ray Thompson / Manchester Manchester Xmas O7 Ray Thompson Julian Freestone, Andy Elvin.
HGC Cassettes Jim Freeman September 17, Director's Review -- Calorimetry – HGC Cassettes Jim Freeman, 2015 Sept 17.
Cryomodule Interconnect Installation Issues A Comparison of XFEL to LCLSII Karen Fant 7/29/2015.
Prototype Cryomodule FDR Ken Premo 21 – 22 January 2015 High Power Coupler Design.
Integral Field Spectrograph Opto-mechanical concepts PIERRE KARST, JEAN-LUC GIMENEZ CPPM(CNRS),FRANCE.
BM&N STS ladders assembly in VLHEP
Cosmic Microwave Technology, Inc.
Rose Navarro HMI Lead Thermal Engineer
ComCam Hardware and Interfaces James Howard ComCam CAM LSST 2017 Project & Community Workshop 2017 Aug 15.
ATLAS pixel module assembly flow
4x8 Mosaic Camera Development
LARP Phase II Secondary Collimator RC1
Ladder Assembly All tools and jigs produced Glue dispensing works
Overview of Mechanical Design
Performance of an Automated Water Based Cooling System for CBM MuCh
Mechanics: (Tim).
Hawkeye Mechanical Design Snapshot
Test box for ProtoDUNE SP – Integration Test
Beam Finder Wire (BFW) Status
SNS PPU Cryomodule Space Frame
Presentation transcript:

1/01/2008P.Z. Takacs1 RTM Testing Issues B-27 session discussion PZ Takacs 22 March 2012

1/01/2008P.Z. Takacs2 Common RTM test stand at BNL & SLAC What metrology will be common to both BNL and SLAC? Optical testing instrumentation required:  Lamp, monochromator, integrating sphere, XYZ stage, dark box, cryostat, handling fixtures and cart, docking station.  Tests required: QE, dark counts, flat field, Fe55, etc. Requirements for BNL and SLAC cryostat for RTM testing. Make as similar as possible. Design of a shipping container for completed RTM. Handling device for loading RTM into cryostat and shipping container. Procedures for loading RTM into cryostat. Procedures for loading RTM into shipping container. Cart for cryostat transport.

Test stand layout in RTM assembly lab 1/01/2008P.Z. Takacs3

4 Raft integration cleanroom

back end e lectronics Raft-Sensor Assembly (RSA) Tower Cage Science Raft Tower Module (RTM) WBS WBS, SCOPE, & DELIVERABLES front end e lectronics WBS WBS Raft Baseplate CCD Sensors(9) Sensor pigtails(18) FEE-BEE pigtails(12) deliverable Total Qty 28 ETU – 2 First Article – 2 Camera Integration & Test – 3 Production - 21 and Raft Control Crate WBS

RTM REQUIREMENTS Focal plane flatness of mm or better for each raft tower module (± wrt nominal height of above kinematic mount spheres) Includes out-of- flatness of the individual CCDs as well as their mounts and the supporting raft surface mm tolerance zone

7 Logic Path - II Given that there must be a cold preamp to achieve the required noise performance, the next question is how much of the electronics chain should be cold and how much warm (i.e. inside vs. outside of the cryostat)? One way to gauge that is to examine the size of the cabling plant at various points along the electronics chain – the numbers on the left show the raw number of conductors at each point along the RTM FEC RCC Raft-Sensor Assembly (RSA) Front End Cage (FEC) Raft Tower Module (RTM) Sensor Head Assembly (SHA) Raft Control Crate (RCC) 9 CCDs 189 x 74 = 13,986  21 x 120 x 6 = 15,120  21 x (4+24) = 588 

8 Preliminary Design Review Tucson, Arizona August 29 th – September 2 nd, 2011 Raft key requirements − Complete 144-Mpixel imager − Support sensors mechanically to meet strict coplanarity and piston tolerances. − Thermal management of sensors and electronics. − Protect sensor surfaces from condensable contamination. − Provide bias, timing, and control signals for CCD operation. − Low noise analog signal processing. − Digitization, multiplexing of pixel data. Raft-Sensor Assembly (RSA) Raft Control Crate (RCC) Front End Cage (FEC) optical power, control, cooling pixel data RequirementValue Imaging surface location ±.00675mm above KM ball centerline Sensor temperature-100C Electronics temperature< -100C (FEC), -40C (RCC) Heat removal (IR + electronics)50W ave Read noise7 e- rms Data rate288MByte/sec detail

9 Preliminary Design Review Tucson, Arizona August 29 th – September 2 nd, 2011 RSA + FEC elements

10 Preliminary Design Review Tucson, Arizona August 29 th – September 2 nd, 2011 RSA + FEC RSA FEC Ball-in-vee kinematic mount FEC – RCC connectors

11 Preliminary Design Review Tucson, Arizona August 29 th – September 2 nd, 2011 RSA + FEC: exploded Copper cage sidewalls CCDs Front end boards Pre-tensioning arm Conductance barriers Thermal conduction planes Mounting feet Raft baseplate

S6 - RTM Assembly 12 Assembly of RSA with FEB electronics and cage structure Test Stand equipment: DesignProcurementLabor Worktable 4’x ESD monitor ESD-safe chair Jigs and tools for assembly

S7 - RTM Dewar Integration 13 Installation and removal of RTM into large cryostat Design of large cryostat with front and rear access flanges. Pack for shipping. Test Stand equipment: DesignProcurementLabor Worktable 4’x ESD monitor ESD-safe chair Jigs and tools for assembly Large cryostat Fe55 source and actuator Vacuum gauges and valves Dry N2 backfill CryoTiger units Vacuum pump Vacuum gauge

S8 - RTM EO Testing 14 Electro-optical testing of complete RTM system Test Stand equipment: DesignProcurementLabor Worktable 4’x ESD monitor ESD-safe chair Dark box Monochromator, Lamp, Shutter, Filters Integrating sphere, 12” Picoammeter XYZ stack Diode laser source Optical attenuator

T8 - RTM assembly 15 1.Collect FEBs and cage parts from storage. Log in ID numbers. Assembly is done at S6 in C10K area. 2.Install thermal conductance strips to FEBs. 3.Install FEBs, conductance barriers, and heat sinks onto RSA. 4.Install tower sides. 5.Install hold-down arms and pretension. 6.Remove assembly tooling. RTM assembly is mounted in a handling fixture at this point. 7.Quick check of electronics functions. 8.Log in with serial number. 9.Move assembled RTM in handling fixture to dry storage with RSA covered. RTM hardware and electronics parts will have been measured and tested earlier. Requires tooling to cover RSA and hold it in place while tower is assembled. Special tooling will be needed to assemble cage with boards onto RSA. Requires a handling fixture to be attached at end of assembly.

T9 - RTM testing 16 1.Move assembled RTM to staging station, S7, in C100 area. 2.Prepare large cryostat for RTM installation on large cart. 3.Remove handling fixture from RTM and transfer to installation fixture. 4.Install RTM into cryostat. 5.Make all necessary electrical connections to back flange. Check continuity if necessary. 6.Attach back flange to back of cryostat. 7.Attach window flange to front of cryostat. 8.Make connections to vacuum pump and cryocooler. 9.Move RTM on large cart to flatness station, S5. 10.Measure flatness while warm at 1atm to see if any changes during assembly. 11.Pump down and cool down. Monitor flatness and vital signs. 12.Measure flatness when cold. 13.Move RTM on cart to EO test station S8 for final calibration tests. 14.Connect cryostat cables to CCS and RTS2 systems. 15.Perform QE, dark noise, flat field, CTE, etc. tests on full raft surface with actual electronics. 16.Thermal cycle the RTM and perform burn-in tests. 17.Move RTM and large cryostat into C100 area to S6. 18.Warm up and purge with dry N2. 19.Remove RTM assembly from cryostat and place in shipping container for storage. Need large cryostat with 2-ended design. Install on large handling cart. Design to mate with flatness docking station at S5 and dark box on S8. Cryostat contains Fe55 mechanism. Cryocooler dual head connections through side wall of dewar. Back flange contains all electrical connections to RTM. RTM control by CCS software during testing. RTS2 interfaces to CCS? Need to have flatness station and S8 components in working order. Calibrate QE equipment against NIST standard occasionally. Need shipping container.

17 RTM Assembly - sequence summary PLANARIZE (if Diff Screws are req’d) ASSEMBLE, MACHINE, DISASSEMBLE Make surfaces coplanar INSTALL BOARDS, HEATSINKS, CONDUCTANCE BARRIER INSTALL HOLD- DOWNS, COMPLETE TESTING in instrument cleanroom in machine shop in assembly cleanroom

18 RTM Assembly Procedure – details Protective 2-pc tooling sides added to Raft to prepare for sensor package installation Clearance undercut Two holes each side

19 Build-up Raft Tower Module Raft-Sensor assy is mounted to bench top

20 Begin FEB installation 1/4–circle multi-position board holder tooling Board with two thermal conductance Cu strips micro-D connectors (2 sizes) nano-D connector x3

21 Connector mating detail Nano-D connector Creased Kapton conductance barrier

22 Add heatsinks Stand up right-hand boardAdd heat sinks (4 pieces)

23 Heat sink details soldered joint Flexible Leaf assy (custom fabrication ) (12 leaves, mm [.005 in] thk each) Hanger Pin

24 Continue board installations... ab c

25 Install Tower Side 3 “Y+” (thermal path) tool Tower Side 3 Attach tower side to tool piece Attach tool to existing tooling Install hardware (attaches boards and heat sinks to Side 3) Internal parts are now supported

26 conductance barrier clamp tool Side 4 Remove ¼-circle support plate Replace with tool and Side 4 “Y-” (thermal path) Install hardware Install conductance barrier clamps

27 Install Sides 1 & 2 (mechanical) Dowel pins Was pre-machined as matched set with thermal sides, then disassembled Establishes coplanar thermal transfer surface to cryoplate Pinned and keyed to impose identical re- assembly

28 Install hold-down arms

29 Complete hold-down assys

30 Tests and Inspection – incoming sensors Flatness of image surface Height of image surface wrt mount surface Alignment pin diameters and location –Dia mm ±0.005 –Pin position held relative to silicon by mfgr –pins prohibit neighbor collisions, during and after CCD installation on raft Functional check in dewar (for first units)

31 CCD Image Sensor (one mfg option) Studs or diff. screws FLEXI (Kapton) with nano-connector ALIGNMENT PINS (Invar; Ø4.000 mm) H-FRAME (CeSiC)

32 Tests and Inspection - planarizing Planarize sensors –Use OGP Quest 300 laser –REAL TIME measurement and adjustment Place planarized Raft-Sensor assy in cold test dewar Measure both warm and cold with Keyence measuring device to verify flatness and thermal stability; maybe first few assemblies only Remove from dewar and re-install protective tooling around assy

33 Tests and Inspection – RTM performance Remove protective tooling Install RTM in dewar –Check hold-down mechanism Run cold tests –Check electronics –Check thermal response Record results traceable to serialized RTM

34 Registry of tower to raft

Extra slides 35

Add Diff Screws to Sensor Pkg – if used 100 & 80 thd/inch Advance/retract 63.5 μm per turn 5.7 deg. per μm Wave spring between head and stud eliminates hysteresis

Sensor Package being withdrawn from handling jig onto Raft surface

Alignment Pin Engagement 0.9 mm 5 mm

Raft Assy ready for planarization Hardware (bellevilles and M6 nuts) added to screws Ready for planarizing, if required

Quest 300 measuring machine Measurement uncertainty: – X,Y linear = (1.2+4L/1000) μm – Z linear = (1.0+5L/1000) μm, using TTL laser – (L measured in mm) Can be improved using optical flat in field of view Range (X, Y, Z, inches) – Standard = 12,12,10 – Enhanced Z = 12,12,12

Multiple flexible shafts drive all differential screws Simultaneous screw engagement with one lever Once engaged, no Z-force imposed on screw REAL TIME measurement