On-line Sorting Technology for CCA-Treated Wood
Funding Received from Sarasota County through the Florida Department of Environmental Protection Innovative Recycling Grants Program
Objective n Construct and Operate an On-Line System for Sorting Treated From Untreated Wood
Background n Research conducted found CCA-treated wood in C&D waste piles ä 6% in 1996 (12 C&D facilities) ä 9 to 30% in 1999 (3 C&D facilities)
Background (From SFPA) U.S. Statistics for Southern Pine Production
Conceptual Design
Conceptual Design (con’d)
Tasks n Task 1: Obtain Permit and Construct Shelter n Task 2: Design and Construct Conveyor n Task 3: Lab Test and Develop Detector (Laser, LIBS vs X-ray, XRF) n Task 4: Install and Field Test Conveyor and Detector n Task 5: Operate Sorting System and Document Performance
Overall Timeline
Task 1: Obtain Permit and Construct Shelter
Outline n Specifications and location of shelter n Construction process ä Shelter construction contractors ä Project management n Project schedule
Shelter Description n Metal fabricated building n 30 by 40 feet, 15 foot eave height n Portal frame with open sides, 1:12 sloped roof n Engineered concrete slab
Approximate Size and Roof Line
Portal Frame
Portal Frame and Open Sides
Open Sides and Height
Site Layout Parking Office Trailer Shelter Bin Wood In Wood Out Proposed Parking Machine Shop C&D Materials Processing Area C&D Material Storage Bins Entrance
Shelter Location
Construction Process n Metal fabricator - shelter design n County engineer - concrete design ä Slab ä Anchor bolts n Electric - separate subcontractor
Anchor Bolt Detail
Available Electric
Shelter Contractor Quotes n Uni-Built, Tampa, FL n Dura-Steel, Vernon, FL n Trident, Sarasota, FL n Ranged $9,000 - $17,000
Project Management n Review plans and permit documents n Coordinate inspection schedule of foundations, structural steel and electrical system n Review work in-place prior to scheduled inspection by Building Department n Prepare written summary of field inspections
Review and Concrete/Electrical Design Building Contractor Develops Design Drawing 2 Wk 5 Wks Permit Review 1 Wk PO/Contract Finalized 6 Wks Fabrication and Delivery Concrete Slab Erect Building Install Electric Schedule and Timeline July 28 August 4 21 September Wks October
Task 2: Design and Construct Conveyor
Conveyor (Task 2) n Preliminary Quotes ä American Conveyor, Miami, FL ** ä Powerscreen, Lakeland, FL
Conveyor (Task 2) Most Recent Design
Conveyor (Task 2)
Task 3: Lab Test and Develop Detector
LIBS vs XRF n Funds will be used for LIBS n Research with XRF will continue if equipment “borrowing” arrangement can be made
Laser-induced Breakdown Spectroscopy (LIBS)
LIBS Spectrum of CCA-treated Wood
LIBS-based Sorting
Sample Configuration of LIBS Probe
Field-deployable Laser: Big Sky Laser
Compact Spectrometer: Ocean Optics
On-line Sorting Technologies
XRF n ASOMA ----> Now Spectro ä Contact Harold Soisson ä Model 400
XRF n Co XRF ----> Distributors of EDAX ä Contact Steve Cox ä Model, CT-2000 Note: As detection limit 5 mg/kg
Questions? More information at: sarasota/index_sara.htm Link from: