Cost, Schedule & Funding Closeout Jan. 29-31 Joint DOE/NSF CD2/3a Review 1 DOE/NSF Review of the Dark Energy Survey (DES) Project SC 6/7 Cost, Schedule.

Slides:



Advertisements
Similar presentations
OFFICE OF SCIENCE Kurt W. Fisher Review Committee Chair Office of Science, U.S. Department of Energy 1 Closeout Report.
Advertisements

Executive Session Director’s CD-1 Follow-Up Review of the APUL Project November 2-3, 2009 Dean A. Hoffer.
OFFICE OF SCIENCE 1 Closeout Presentation and Final Report Procedures.
DOE/NSF U.S. CMS Operations Program Review Closeout Report Fermi National Accelerator Laboratory March 10, 2015 Anadi Canepa, TRIUMF Anna Goussiou, University.
M. Reichanadter, SLACLCLS FAC Meeting - April 29, 2004 LCLS Organization & Execution M. Reichanadter LCLS FAC Meeting April 29, 2004 LCLS.
Mark Reichanadter LCLS FAC April 20-21, 2006 Meeting of the LCLS Facilities Advisory Committee LCLS Project Management M.
OFFICE OF SCIENCE Review of Critical Decision 2 for the Large Liquid Argon Detector for Neutron Physics (MicroBooNE) at Fermi National Accelerator Laboratory.
Mark Reichanadter LCLS FAC April 16-17, 2007 Report to the LCLS Facilities Advisory Committee LCLS Project Management M.
1 ®  Overview Benefits of a Good Construction Schedule Baseline Schedule Development Schedule Updating and Maintenance Managing Project Changes USACE.
FRA’s Earned Value Management System Overview for Self Assessment Surveillance March 07-09, 2011 Dean Hoffer Head, Office of Project Management Oversight.
Mark Reichanadter LCLS FAC Oct12-13, 2004 Meeting of the LCLS Facilities Advisory Committee LCLS Organization & Execution.
© 2005 Prentice Hall14-1 Stumpf and Teague Object-Oriented Systems Analysis and Design with UML.
October 24, 2000Milestones, Funding of USCMS S&C Matthias Kasemann1 US CMS Software and Computing Milestones and Funding Profiles Matthias Kasemann Fermilab.
Project ManagementDay 1 in the pm Project Management (PM) Structures.
NCSX Management Overview Hutch Neilson, NCSX Project Manager NCSX Conceptual Design Review Princeton, NJ May 23, 2002.
NEDM Construction Project Cost & Schedule Philosophy Vince Cianciolo, ORNL Physics Division Internal Cost & Schedule Review 02/11/2005.
OFFICE OF SCIENCE Dark Energy Survey (DES) Project at the Fermi National Accelerator Laboratory June 22-23, 2010 Department of Energy/ National Science.
1 BROOKHAVEN SCIENCE ASSOCIATES Project Performance & Risk Management Aesook Byon, Deputy Project Director NSLS-II PAC Meeting February 8-9, 2011.
BROOKHAVEN SCIENCE ASSOCIATES National Synchrotron Light Source II Project Management Jim Yeck Deputy Director (Project Management)
1 BROOKHAVEN SCIENCE ASSOCIATES CFAC Review Martin Fallier Director, Conventional Facilities Conventional Facilities Value and Risk Management May 8, 2008.
1 BROOKHAVEN SCIENCE ASSOCIATES CFAC Review Marty Fallier Director for Conventional Facilities CD-2 Planning May 8, 2007.
OFFICE OF SCIENCE 1 Closeout Presentation and Final Report Procedures.
BROOKHAVEN SCIENCE ASSOCIATES National Synchrotron Light Source II Project Management Jim Yeck NLSL II Deputy Director (Project Management)
OFFICE OF SCIENCE 1 3. Cost Estimate Gines, Fisher 2.Are the estimated cost and proposed schedule ranges realistic, consistent with the technical and budgetary.
Muon Ionization Cooling Experiment: U.S. Muon Accelerator Program Perspective and Approach Mark Palmer May 7, 2013.
7/26/2006 Wyatt Merritt 1 DECam Preparations for Critical Decision 2/3a Preparations for CD2 Preparations for CD3a DECam MOUs.
1 BROOKHAVEN SCIENCE ASSOCIATES NSLS-II Project Baseline Jim Yeck NSLS-II Deputy Project Director NSLS-II PAC Meeting November 20, 2007.
Executive Session Director’s CD-3b Review of the MicroBooNE Project January 18, 2012 Dean Hoffer.
July LEReC Review July 2014 Low Energy RHIC electron Cooling Kerry Mirabella Cost, Schedule, Personnel.
January LEReC Review 12 – 13 January 2015 Low Energy RHIC electron Cooling Kerry Mirabella Cost, Schedule, Personnel.
John Peoples for the DES Collaboration BIRP Review August 12, 2004 Tucson1 DES Management  Survey Organization  Survey Deliverables  Proposed funding.
LBNE Working Group Meeting December 20, :00– 5:00 PM Snake Pit.
OFFICE OF SCIENCE 2.3 Infrastructure and Installation Sims, Edwards 1.Does the conceptual design and planned implementation satisfy the performance specifications.
W.J. Foyt LUSI DOE Review July 23, 2007 Project Management 1 Project Management W. J. Foyt Project Scope Timeline Cost Estimate.
M. Reichanadter LCLS Project November 2008 FAC Meeting Slac National Accelerator Laboratory Report to the LCLS.
7/26/2006 Wyatt Merritt 1 DECam CD1 Documentation DOE Critical Decision Process Documentation Requirements.
U.S. Department of Energy’s Office of Science Dark Energy Survey (DES) Project Stephen Tkaczyk, Chair DOE/SC Review Committee September 10, 2008
3.1.1 Optics, Optical Corrector, Mechanical Systems M. Johns, C. Claver.
PU-PPPL Earned Value Management System Overview Thomas Egebo October 4-6, 2011 Princeton University Plasma Physics Laboratory EVMS Certification Review.
1 The DES Calibrations Effort Douglas L. Tucker (DES Calibrations Scientist) DES NSF/DOE Review, 8-9 June 2009 The DES Calibrations Effort has connections.
January LEReC Review 12 – 13 January 2015 Low Energy RHIC electron Cooling Kerry Mirabella Cost, Schedule, Personnel.
1 US Cost & Schedule Summary W. R. Edwards US Project Manager CD-2/3a Review January 8, 2008 BNL.
OFFICE OF SCIENCE 1 Closeout Presentation and Final Report Procedures.
DoE Review June 6, 2000 Cost Estimate  New Cost Estimate u Manpower Costs (Op. SWF) u Equipment Costs (Eq. M&S) u Contingency  Conclusions Mike Tuts.
Brenna Flaugher October 30, 2007 Preliminary Directors Review 1 Outline This talk will describe progress on DECam since the joint NSF/DOE CD-1 review in.
DUSEL Beamline Working Group Meeting March 09, :00 AM – Snake Pit (WH2NE) By Dean Hoffer - OPMO.
Brenna Flaugher Sept. 24 th Lehman Review1 Run IIB Silicon Upgrade: Cost and Schedule Lehman Review Sept. 24, 2002 Brenna Flaugher Run IIB Silicon Project.
Mark Reichanadter LCLS October 9-11, 2007 LCLS BCR Overview and EIR LOIs Project Progress / Status Revised Project Baseline.
LIGO-G M Advanced LIGO Cost, Schedule and Management Gary H Sanders NSF Review of Advanced LIGO Caltech, June 11, 2003.
Proton Driver Resources & Schedule (R&D Plan) Rich Stanek May 10, 2005.
Management February 20, Annual Review of the Muon Accelerator Program (MAP) Subcommittee members: Ron Prwivo, Ron Lutha, and Jim Kerby.
Power Upgrade Project SNS September 21-22, TBM Cost Estimate Cost Estimate Schedule Approach Tom Mann October 27, 2005.
Strykowsky 1Project Review November 2, 2005 NCSX Project Review November 2, 2005 Cost and Schedule Ron Strykowsky.
DES Review CCD Focal Plane and Camera Roger Smith George Ricker.
Budget Outlook Glen Crawford P5 Meeting Sep
Brenna Flaugher, PMG, April 6, 2007 DECam Funding Need Profile (Dec 06) (then yr $, Overhead included) This gave a technically driven schedule resulting.
Project X Collaboration Plan Steve Holmes Accelerator Advisory Committee Meeting May 6-8, 2008.
OFFICE OF SCIENCE Closeout Report by the Review Committee for the LHC-CMS Detector Upgrade Project Fermi National Accelerator Laboratory August 27, 2013.
DOE Review of LARP – Feb 17-18, 2014 DOE Critical Decision Process Ruben Carcagno February 17,
Cost and Schedule Breakout Session Paul Weinman Pacific Northwest National Laboratory.
NCSX Strykowsky 1Independent Project Review (IPR) June 8-9, 2004 NCSX Project Review June 8-9, 2004 Cost, Schedule, and Project Controls Ron Strykowsky.
Risk Management Lucas Taylor Fermilab Risk Manager 3 rd February Director's Review -- Risk Management L. Taylor, 3rd February 2016.
Cost and Schedule Paul Weinman Pacific Northwest National Laboratory.
Project Management W. J. Foyt
LCLS Linac Technical Design Review Charge
DOE: Transition from MIE to Early Operations Kevin Reil LSST Camera Commissioning Lead LSST Commissioning Plan Review January 24-26, 2017.
Management Breakout: MREFC Budget Summary Victor L
Linac Ops Budget Structure & Approach WBS 1 – LCLS Mgmt & Admin
Preliminary Project Execution Plan
Conventional Facilities
Presentation transcript:

Cost, Schedule & Funding Closeout Jan Joint DOE/NSF CD2/3a Review 1 DOE/NSF Review of the Dark Energy Survey (DES) Project SC 6/7 Cost, Schedule and Funding Committee Mark Reichanadter, SLAC Kem Robinson, LBNL

Cost, Schedule & Funding Closeout Jan Joint DOE/NSF CD2/3a Review 2 6. Cost Estimate - Findings DECam – –The DECam project team presented a TPC of $32.9M, which can be compared to a CD-1 TPC of $25.0M. Cost increases from CD-1: Increased equipment costs ($1.5M) Incorporated university labor into TPC ($1.1M) Incorporated R&D from CD-0 into TPC ($5.3M) –Includes $5.1M (32%) MIE contingency, $500K R&D contingency. –Cost basis is in $FY07. Costs are fully-burdened and include DOE/FNAL out-year escalation. –Installation/commissioning are not included in project. –HEP base program supports FNAL scientists. Zero cost to project. –Request CD-3a for ~$2.1M for long-lead procurements: CCD Processing 3Q-08, CCD Packaging 3Q-08, Hexapods 1Q-09

Cost, Schedule & Funding Closeout Jan Joint DOE/NSF CD2/3a Review 3 6. Cost Estimate - Findings DES-DM – –The DES-DM team presented a TPC of $7.6M using a mix of funding sources. –DES-DM includes software testing and commissioning, but zero contingency. CFIP – –CFIP is estimated at $390K for equipment upgrades and $470K for labor ($860K total). –Zero contingency included in the CFIP project. CTIO Director holds contingency outside the TPC. Summarizing, the DES Total Project Cost (TPC) is estimated at $41,436K

Cost, Schedule & Funding Closeout Jan Joint DOE/NSF CD2/3a Review 4 Cost and schedule estimates for the DECam, DEC-DM and CFIP are developed as separate projects. An integrated project schedule will greatly improve overall project coordination. DECam Cost – –Resource-loaded WBS and schedule are well developed. Estimates are supported with a documented cost basis. –Adequately developed to support CD-2, however cost contingency appears too low particularly in integration, telescope simulator and activities in Chile. –Cost estimates for CD-3a items (long-lead procurements) are adequate although some technical issues are unresolved. –~$2M of foreign procurements are exposed to currency risk. Strategies should be considered to mitigate risk. 6. Cost Estimate - Comments

Cost, Schedule & Funding Closeout Jan Joint DOE/NSF CD2/3a Review 5 DES-DM Cost – –Resource-loaded WBS and schedule were presented based upon technical judgment. –Estimate is primarily labor estimates supporting a software project. –Distributed labor and partial FTE’s will require strong management and coordination CFIP Cost – –Cost and schedule estimate are not resource-loaded. –Primarily an upgrade to an operating facility. 6. Cost Estimate - Comments

Cost, Schedule & Funding Closeout Jan Joint DOE/NSF CD2/3a Review 6 6. Cost Estimate - Recommendations 1.Reevaluate and update the DECam cost and contingency estimates based upon recommendations in this report. 2.Reevaluate and update the DES-DM cost estimates based upon recommendations in this report. 3.Recommend DECam for CD-2 after updating cost and contingency estimates. 4.Recommend DECam for CD-3a after satisfying earlier recommendations on CCD’s and hexapods.

Cost, Schedule & Funding Closeout Jan Joint DOE/NSF CD2/3a Review 7 7. Schedule and Funding – Findings DECam Schedule – –Logically-linked schedule containing ~1000 activities for delivery of the camera to CTIO. –Critical path identified and is driven by FY10 procurements Primarily filters, crate cooling system –CD-4 Milestone is 3Q Schedule float is 12 months. DES-DM Schedule – –Resource-loaded schedule containing ~800 activities –Total DES-DM development labor is ~44 years –Schedule follows a series of spiral development cycles –DES-DM complete w/acceptance tests 4Q Schedule float ~9 months. CFIP Schedule – –Summary schedule was presented. Roughly 12 months of float is available.

Cost, Schedule & Funding Closeout Jan Joint DOE/NSF CD2/3a Review 8 7. Schedule and Funding – Findings DECam – –The project team presented a funding-constrained schedule based upon a bottoms-up resource-loaded schedule. Zero funding is planned for the final year of the project (FY12). –MS Project and COBRA (DECam) are the primary scheduling tools chosen to monitor schedule progress. –Monthly Status and Earned Value Reporting have been in place for 5 months, and the DOE/Director’s EVMS review concluded DECam was in compliance for self certification. DES-DM – –Proposal submitted to NSF for $2.94M to support project. CFIP – –Infrastructure improvements using operating funds

Cost, Schedule & Funding Closeout Jan Joint DOE/NSF CD2/3a Review 9 DES funding profile summarizing the three subprojects is shown below: 7. Schedule & Funding – Findings

Cost, Schedule & Funding Closeout Jan Joint DOE/NSF CD2/3a Review Schedule and Funding – Comments The Committee judged that the schedule maturity for the DES projects to be at the appropriate level to support CD-2. –Schedule contingency of 12 months (DECam) and 9 months (DES- DM) is considered adequate. –Schedule contingency is not costed. Delays draw from contingency should be estimated by the project for planning purposes. Although the project has identified the primary project activities overall integration should be improved. An integrated DES project schedule with identified subproject linkages will facilitate coordination of the entire DES project. Obligation profile is front-loaded and early use of contingency will need to be carefully managed. –Long-lead procurements are important to retire risk

Cost, Schedule & Funding Closeout Jan Joint DOE/NSF CD2/3a Review Schedule & Funding - Comments DECam project team should work closely with Fermilab to minimize potential CR effects on the project’s procurement plans. –FNAL PMG will play important role. Effective use of milestones on all projects to monitor overall progress. Commendable. Each project has identified the critical path activities and is actively managing float. FTE estimates or manpower profiles provided for most areas of the DES project.

Cost, Schedule & Funding Closeout Jan Joint DOE/NSF CD2/3a Review Schedule and Funding – Recommendations 1.Develop an integrated DES project schedule which effectively connects the three projects. 2.Recommend DECam for CD-2 and CD-3a

Cost, Schedule & Funding Closeout Jan Joint DOE/NSF CD2/3a Review 13 6/7 Cost, Schedule & Funding LOI’s EIR Lines of Inquiry and Responses 1. Work Breakdown Structure / Satisfactory 2. Project Cost and Resource Loaded Schedule / Satisfactory w/updates to cost estimate 3. Key Project Cost and Schedule Assumptions / Satisfactory w/updates to contingency assessment 4. Critical Path / Satisfactory 6. Funding Profile / Satisfactory 7. Project Controls / EVMS / Satisfactory