MICE Target Development Chris Booth Sheffield 8 th June 2006.

Slides:



Advertisements
Similar presentations
1 MICE Target Status Chris Booth 3 rd March 2004.
Advertisements

MICE RF and Coupling Coil Module Outstanding Issues Steve Virostek Lawrence Berkeley National Laboratory MICE Collaboration Meeting October 26, 2004.
MICE Target Report Video Conference 15/03/07 Chris Booth Sheffield 15 th March 2007.
MICE Target Report Chris Booth (for target team) Sheffield 23 rd April 2009.
The MICE Target Lara Howlett University of Sheffield.
Progress on Target Design Chris Booth Sheffield 2 nd August 2004.
MICE Target Status Chris Booth 30 th March Chris BoothUniversity of Sheffield 2 The challenge ISIS beam shrinks from 73 mm to 55 mm radius during.
Target Status Report Lara Howlett University of Sheffield.
MICE TARGET HARDWARE C. Booth, P. Hodgson, R. Nicholson, P. J. Smith, Dept. of Physics & Astronomy University of Sheffield, England. 1 - The MICE Experiment.
Muon g-2 Muon g-2 Experiment Quarterly Report Aria Soha All Experimenter’s Meeting March 2, 2015.
Status of the LARP Phase II Secondary Collimator Prototype 30 September 2013 LHC Collimation WG Meeting Tom Markiewicz/SLAC BNL - FNAL- LBNL - SLAC US.
MICE Target Report Chris Booth (for target team) Sheffield 7 th May 2009.
MICE Target Schedule Chris Booth Sheffield 12 th June 2006.
Progress on Target Design Chris Booth Sheffield 14 th July 2004.
P J SmithUniversity of Sheffield1 MICE Target Electronics Paul J Smith University of Sheffield Fermilab 10 th June 2006.
MICE Target Status Chris Booth Sheffield 10 th May 2006.
TARGET WORKSHOP – SHEFFIELD HALLAM UNIVERSITY Monday 2 March 2009 The ISIS – MICE interface Eddie McCarron Contents 1.Target alignment with ISIS beam centre.
Target Specifications & History (to avoid reinventing a broken wheel!) 2 nd December 2009 Chris Booth The University of Sheffield.
Target Update – Mico Meeting Monday 21 st April 2008 General Expect to obtain new coils for stators anytime New Shafts at RAL for metrology. Will be back.
Stator Plan & Schedule Chris Booth 2 nd March stators to construct for mid-April. One complete coil assembly recovered from ISIS drive. Coils recoverable.
MICE Target Review Chris Booth Sheffield 12 th June 2006.
A Tale of Two Targets … 7 th September 2009 Chris Booth The University of Sheffield.
Target Assembly and Installation Update 20 th August 2009 Paul Hodgson The University of Sheffield.
Update Hardware for conductive cooling of the quench resistors has been fabricated at LBNL. Preparation for installation to start this week. Installation.
1 MICE Magnets Contents: Background Refurbishment Testing Installation & survey Current status Upstream beamline Open issues & concerns MICE Beamline Review,
Status of the LARP Phase II Secondary Collimator Prototype 14 October 2013 LHC Collimation WG Meeting Tom Markiewicz/SLAC BNL - FNAL- LBNL - SLAC US LHC.
DESIGN AND OPERATIONAL EXPERIENCE OF THE MICE TARGET Target Drive The linear electromagnetic drive that has been designed to meet these requirements consists.
LARP Rotatable Collimator Prototype Assembly completed and all mechanical tests successful: Cooling tubes twist, under vacuum, as jaws turn, with R~1 m.
LARP Rotatable Collimator Prototype Assembly completed and all mechanical tests successful: Cooling tubes twist, under vacuum, as jaws turn, with R~1 m.
MICE Target Report Video Conference 05/07/07 Chris Booth Sheffield 5 th July 2007.
Target Design – Status and Plans Chris Booth Sheffield 12 th January 2005.
Spectrometer Solenoid Update Steve Virostek Lawrence Berkeley National Lab Roy Preece Rutherford Appleton Lab October 28, 2011 MICE Collaboration Meeting.
MICE Target Mechanical Design l Jason Tarrant – STFC »Working on upgrade of Target Mechanics l Contents »Main features of upgrade design »Progress & schedule.
MICE RFCC Module Update Allan DeMello Lawrence Berkeley National Laboratory MAP Winter Collaboration Meeting at JLab, Virginia February 28, 2011.
Status and Integration of the Spectrometer Solenoid Magnets Steve Virostek Lawrence Berkeley National Lab MICE RAL June 15, 2007.
MICE Target Mechanism P J Smith University of Sheffield MICE CM 18 RAL June 2007.
S A Griffiths Target Review Jan 2009 Target Electrical / Control Schematic HexBridge Power electronics Interface PSU Capacitor Bank Local Control Interface.
Chris BoothMICE-UK I.C. 16th January Useful meeting held at RAL last Thursday. Representatives of MICE, ISIS & others with Sheffield electronic &
1 Progress On The Design And Manufacture Of The New Stator Geoff Barber Imperial College.
VELO workshop, Amsterdam, april ‘00M.Ferro-Luzzi Difficulties with current mechanical design recent FEA results: to obtain sufficient stiffness of center.
MICE Target – Design Update and Test Plans Chris Booth Sheffield 22 nd October 2005.
MICE MICE Target Mechanism Control Electronics Upgrade P J Smith – University of Sheffield James Leaver – Imperial College 2 nd March 2009.
Status of installed target Preparation of “demonstrator” target Chris Booth Sheffield 25 th January 2008.
LARP LHC PHASE II COLL RC1 TESTS - S. Lundgren 06 June 2006 No 1 /17 LARP Phase II Secondary Collimator RC1 Collimator Test Program Plan Forward Revised.
MICE Target - Risk Lara Howlett University of Sheffield.
Target Status Target installed in ISIS “Demonstrator” target in R78 Chris Booth Sheffield 7 th February 2008.
Target Status CM19 RAL October 2007 P J Smith – University of Sheffield.
Spectrometer Solenoid Fabrication Status and Schedule Steve Virostek Lawrence Berkeley National Lab MICE RAL October 20, 2008.
MICE Target Mechanical Design l Status of Target ref. Schedule »Drawings –Drawing list created (see next slide) includes inventory –Drawings being released.
MICE Target Development Lara Howlett University of Sheffield.
Status of Target Design Chris Booth Sheffield 28 th October 2004.
MICE RFCC Module Update Allan DeMello Lawrence Berkeley National Laboratory MICE CM29 at RAL, UK February 17, 2011.
MICE Target Installation Chris Booth & Paul Smith Sheffield 26 th July 2007.
Status of and Installation Plan for DC Gas Control System and Target Work Scheduling Meeting 4 August 2006 PSI W. Molzon, Feng Xiao.
Target tests 1 st – 2 nd Nov. Chris Booth Sheffield 7 th December 2006.
Target Commissioning Target installed in ISIS “Demonstrator” target in R78 Initial commissioning plans Chris Booth Sheffield 11 th February 2008.
PHIN Fabrication of a photo-injector for the CTF3 accelerator and for the NEPAL test stand WP 4 of the JRA2 PHIN 1.Status of the construction of RF guns.
Target Status Report Chris Booth & Paul Hodgson Sheffield 18 th Sept ember2008.
Chris BoothUniversity of Sheffield 1 Target Status & Progress 1 st February 2006 Disappointingly slow progress over last 2 months. However, progress is.
MICE Target – Status & Plans Chris Booth Sheffield 28 th February 2006.
Target Status 27 th August 2009 Chris Booth The University of Sheffield.
The Target Drive For The MICE Experiment Control and Infrastructure Optical Readout and Drive Electronics Target Drive A linear electromagnetic drive has.
Chris Booth Sheffield 29th March 2006
Stator Plan & Schedule Chris Booth 2nd March 2009
Target Installation Plan
MICE Target Report Video Conference 29/11/07
Status of Target Design
Overview of the TARGET Monolith Rough Vacuum
Polarized 3He target installation
Presentation transcript:

MICE Target Development Chris Booth Sheffield 8 th June 2006

Chris BoothUniversity of Sheffield 2 Progress since last Collaboration Mtg. –Review of components –Assembly tests at RAL in April –Developments resulting from tests –Increased effort for target Plans & schedule June to November

Chris BoothUniversity of Sheffield 3 Components Stator body Ceramic tube Glass readout tube Target shuttle Ceramic bearings Electronics Frame, jack, bellows, gate-valve

Chris BoothUniversity of Sheffield 4 Stator (1) Stator body from Manchester not built to specs. Micro-surgery allowed insertion of ceramic tube! We have learned how to make all components for future stators in house.

Chris BoothUniversity of Sheffield 5 Stator (2) Coil winding company provided satisfactory sample. 30 coils purchased, to construct new stator. Coils wound in-house also satisfactory. Will try new cooling and potting techniques in near future.

Chris BoothUniversity of Sheffield 6 Ceramic tube Test flanges & dummy stator built at RAL. Indium vacuum seals tested. Pronounced satisfactory!

Chris BoothUniversity of Sheffield 7 Optical readout enclosure Quartz glass tube and flange procured. Flange machined, tube fixed with cryostat cement.

Chris BoothUniversity of Sheffield 8 Shuttle Oxford assembled shaft, target, alignment fin, stop, magnets, readout vane (see picture) – many thanks! Magnets, readout vane supplied by Sheffield. For prototype, shaft produced from steel tube rather than titanium. Assembly cleaned in Oxford, delivered direct to RAL.

Chris BoothUniversity of Sheffield 9 Control electronics Cards now rack- mounted. Extensive tests with prototype drive. Several hours pulsing at 0.3 Hz (10 A). Some reliability & noise problems are being addressed.

Chris BoothUniversity of Sheffield 10 Bellows

Chris BoothUniversity of Sheffield 11

Chris BoothUniversity of Sheffield 12 Indium seals Ceramic bearings

Chris BoothUniversity of Sheffield 13 Beam pipe Gate valve Bellows Drive mechanism Support frame

Chris BoothUniversity of Sheffield 14 Assembly test: April First time many parts came together: –Stator first connected to electronics 20 th –Glass readout tube assembled 21 st –Target shuttle finished morning of 24 th –Some RAL parts and flanges not previously assembled.

Chris BoothUniversity of Sheffield 15 What did we learn? 1.Glass tube was very fragile! –Broken near metal flange. –Ground down and re-glued – vacuum tested ok. –New crack when tightened down onto full assembly. –Covered in epoxy! Amazingly, this appeared to seal ok!

Chris BoothUniversity of Sheffield 16 2.Target shuttle was distorted –Slot cut along thin-walled tube to take alignment vane caused shaft to distort. –Vane was twisted and slightly off-axis at one end. –Would not pass through ceramic bearing. –Slot & hole in bearing machined out to allow shaft and vane to pass. –Some play and roughness, but movement satisfactory.

Chris BoothUniversity of Sheffield 17 Titanium target Steel shaft Alignment fin Stop Magnets Optical readout vane

Chris BoothUniversity of Sheffield 18 3.Indium seals did not work! –Despite success with test pieces, could not pump down below 3  10 –3 mbar. –Flanges found to have too large diameter and chamfer; rebates incorrect so inadequate closure of seal. –Attempts to seal with extra indium. –Only partial improvement. –Prevented vacuum quality checks with mass spectrometer.

Chris BoothUniversity of Sheffield 19 4.Temperature sensitivity –Operation of drive (power-off to hold position) caused deterioration in vacuum. (Only 10-15°C temperature rise.) –Chilled water cooling (12°C) also worsened vacuum. –Partial recovery on return to ambient temperature. –Movement of ceramic tube disturbing (imperfect) seal?

Chris BoothUniversity of Sheffield 20 5.Optical readout block did not fit –Insufficient space for readout block around glass tube when drive in raised position. –Large guide flange removed – appears not to be necessary. –Flange could also be machined down to allow space.

Chris BoothUniversity of Sheffield 21 Large flange

Chris BoothUniversity of Sheffield 22 6.Extremely difficult to align optics –Higher refractive index of quartz tube? –RAL restrictions on use of laser in hall. –Adjustment system not suitable for 3D alignment in both position and angle 7.Shaft length checked - OK –relative positions of target (raised) & gate valve, target (lowered) & beam-pipe, readout vane & top of tube etc were all correct.

Chris BoothUniversity of Sheffield 23 Solutions to problems 1 & 6 Delicate glass tube, difficult alignment Replace glass tube with steel plus flat glass windows –Robust, much simpler optics. –Redesign optical mounts to allow off-line alignment and accurate relocation. –Involve RAL engineer in design (in conjunction with Richard Nicholson). –Meeting yesterday in Sheffield.

Chris BoothUniversity of Sheffield 24 2 Distorted shuttle shaft Oxford redesigned target shuttle –Target, shaft, stop, alignment fin machined out of single piece of titanium. –Cross-shaped (or square?) cross-section. –Strong, no tendency to twist. –Only magnets and readout fin to be added. –New (or modified) ceramic bearings will be required – design to allow insertion of shaft through lower bearing for easier assembly. –Some questions have just arisen as to whether the shaft can be machined to this design! The design is under review.

Chris BoothUniversity of Sheffield 25 3 & 4 Leaks at indium seals Flanges for indium seals to be re-ground or re-made –Vacuum and temperature tests are being performed at RAL. –Importance of careful quality control –Vacuum & temperature cycling tests will also be performed in Sheffield –In longer term, consider need for bonded ceramic-metal.

Chris BoothUniversity of Sheffield 26 Conclusions of Tests Despite problems, a lot was learned. Practical details of assembly for first time. Improved design of major components. No proper vacuum tests. No reliability or vibration tests. Review held (with ISIS) 16 th May. Will repeat assembly in hall in July, full mechanical & electrical test in September. Will not install in ISIS for June – perform thorough off-line checks for October access.

Chris BoothUniversity of Sheffield 27 Increased Effort for Target Work Daresbury lab electronic engineer (Steve Griffiths) –High power driver electronics Capacitor bank power supply >100 A hex bridge using IGBTs Oxford workshop effort –Shuttle shaft construction Mechanical engineer (Martin Baldwin) (RAL) –Replacement chamber with optical windows –Readout alignment mounting (with RN at Sheff.) Sheffield Physicist/Engineer (advertise soon!) –Thermal modelling of stator – improved cooling –Electromagnetic modelling – more efficient drive?

Chris BoothUniversity of Sheffield 28 Plans & Schedule (1) Indium seal tests (RAL) Build new shaft (Oxford) Design/build top chamber/readout (Sheff/RAL) Build new stator (Sheffield) Vacuum tests (Sheffield) Optical isolation of control boards (Sheffield) Optical drive of hex bridge (Sheffield) Improved control & monitoring (Sheffield) Acceleration & temperature tests (in vacuum) (Sheffield) Reliability tests (Sheffield) Mechanical test at RAL 17 th -21 st July

Chris BoothUniversity of Sheffield 29 Plans & Schedule (2) Build & test IGBT hex bridge driver (Daresbury) Build second shaft (Oxford) Build second (improved?) stator (Sheffield) Build second top chamber/readout (Sheff/RAL) New quadrature board for optics (Sheffield) Improved controller hardware & software (Sheffield) ISIS interface boards (Sheffield) Temperature monitoring hardware & s/w (Sheffield) Acceleration tests (at 80 A) (Sheffield) Temperature, reliability tests (at 80 A) (Sheffield) Mechanical & electrical test at RAL 18 th -22 nd September Installation in ISIS October

Chris BoothUniversity of Sheffield 30