Using The MRP System. Critical Aspects of Using the MRP System 1. The MRP Planner1. The MRP Planner The persons directly involved with the MRP system.

Slides:



Advertisements
Similar presentations
How to release MRP planned orders through OBPM MO/PO create and maintain through OBPM Jim Simunek
Advertisements

Material Requirements Planning
To Accompany Ritzman & Krajewski Foundations of Operations Management, © 2003 Prentice Hall, Inc. All rights reserved. Chapter 15 Resource Planning.
1 Unit 4B - Logics and Calculation of Material Requirement Planning.
EYYUP ORAK Material requirements planning (MRP) is a computer-based inventory management system designed to assist production managers in.
15 – 1 Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall. Inventory and MRP 15 For Operations Management, 9e by Krajewski/Ritzman/Malhotra.
Consumption-based Planning
Master Production Scheduling (MPS) – Basic Techniques pom
6. Material Requirements Planning (MRP)
Material Requirements Planning (MRP)
© The McGraw-Hill Companies, Inc., Chapter 15 Materials Requirements Planning.
Module 10 Setup for Production.
DOM 301 : Operations Management Practice
The MRP II Hierarchy. Long-Range Planning At the top of the hierarchy we have long-range planning. This involves three functions: resource planning,
1 Chapter 15 MRP and ERP. 2 Dependent demand: Demand for items that are subassemblies or component parts to be used in production of finished goods. Dependant.
MRP, MRP II, and ERP.
Material Requirement Planning (MRP)
Material Requirements Planning
1 1 Slide © 2001 South-Western College Publishing/Thomson Learning Anderson Sweeney Williams Anderson Sweeney Williams Slides Prepared by JOHN LOUCKS QUANTITATIVE.
MRP Material Requirements Planning. MRP …is a planning and scheduling technique used for batch production of assembled items. … is a computer-based information.
Material Requirements Planning (MRP) Computer-based information system for ordering and scheduling of dependent-demand inventories, i.e. what is needed,
Copyright © 2011 by The McGraw-Hill Companies, Inc. All rights reserved. McGraw-Hill/Irwin Manufacturing Planning and Control MPC 6 th Edition Chapter.
Session 12 System Transactions
13-1MRP and ERP. 13-2MRP and ERP  Material requirements planning (MRP): Computer-based information system that translates master schedule requirements.
McGraw-Hill/Irwin Copyright © 2007 by The McGraw-Hill Companies, Inc. All rights reserved. 14 MRP and ERP.
Materials Requirements Planning
Operations Management Material Requirements Planning
1 Slides used in class may be different from slides in student pack Chapter 16 Materials Requirements Planning  Material Requirements Planning (MRP) 
MRP Systems MRP – Material Requirements Planning Commonly used method in industry to coordinate the production scheduling of end items and their associated.
Murat Kaya, Sabancı Üniversitesi 1 MS 401 Production and Service Systems Operations Spring Material Requirements Planning (MRP) Slide Set #10.
Material Requirements Planning
Chapter 15 MRP and ERP.
1 Materials Requirements Planning. 2 Material Requirements Planning Defined Materials requirements planning (MRP) is a means for determining the number.
Lecture 9 Materials Requirements Planning Books Introduction to Materials Management, Sixth Edition, J. R. Tony Arnold, P.E., CFPIM, CIRM, Fleming College,
Hierarchy of Production Decisions
To Accompany Ritzman & Krajewski Foundations of Operations Management, © 2003 Prentice Hall, Inc. All rights reserved. Chapter 12 Resource Planning.
McGraw-Hill/Irwin Copyright © 2009 by The McGraw-Hill Companies, Inc. All Rights Reserved. MRP (Material Requirement Planning) (Method under Dependent.
Materials Planning & Control. Introduction With the development of ‘integrated materials management’ and ‘supply chain management’, material managers.
1 MRP and ERP Chapter Transparency on aggregate to master plan.
Master Production Scheduling
To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Sixth Edition © 2002 Prentice Hall, Inc. All rights reserved. Chapter 15.
To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Seventh Edition © 2004 Prentice Hall, Inc. All rights reserved. Resource.
MGMT Materials Management Systems Materials Requirements Planning Chapter 4.
15 – 1 Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall. Resource Planning Chapter 15.
Introduction to Materials Management Chapter 4 – Material Requirements Planning.
Resource Planning Chapter 15.
Materials Requirements Planning
Manufacturing Systems Engineering
© The McGraw-Hill Companies, Inc., Chapter 15 Materials Requirements Planning.
Material Requirements Planning Chapter 2. MRP in MPC.
11-1  Material requirements planning (MRP): Computer-based information system that translates master schedule requirements for end items into time-phased.
Murat Kaya, Sabancı Üniversitesi 1 MS 401 Production and Service Systems Operations Spring Master Production Scheduling (MPS) Slide Set #9.
© 2008 Prentice Hall, Inc.14 – 1 Material Requirements Planning (MRP)
Material Requirements Planning (MRP)
1 © 2006 The McGraw-Hill Companies, Inc., All Rights Reserved Chapter 16 Materials Requirements Planning.
Material Requirements Planning
McGraw-Hill/Irwin Copyright © 2007 by The McGraw-Hill Companies, Inc. All rights reserved. 10 MRP and ERP.
MRP and ERP Chapter 14 Dr. H. Kemal İlter, BE, MBA, DBA
Facility Inventory Old Facilities Modern Facilities Classroom Size
McGraw-Hill/Irwin Copyright © 2009 by The McGraw-Hill Companies, Inc. All rights reserved.
Chapter 16 Materials Requirements Planning
MRP and ERP.
CHAPTER 14 MRP and ERP.
MATERIAL Requirements planning MRP
Material Requirements Planning (MRP)
MRP and ERP.
14 MRP and ERP.
Resource Planning Chapter 16
Material Requirement Planning (MRP)
Material Requirements Planning and Enterprise Resource Planning.
Presentation transcript:

Using The MRP System

Critical Aspects of Using the MRP System 1. The MRP Planner1. The MRP Planner The persons directly involved with the MRP system outputs are planners.The persons directly involved with the MRP system outputs are planners. Planners have the responsibility for making detailed decisions that keep the material moving through the plant.Planners have the responsibility for making detailed decisions that keep the material moving through the plant. Computerized MRP systems often encompass tens of thousands of part numbers.Computerized MRP systems often encompass tens of thousands of part numbers. To handle this volume, planners are generally organized around logical groupings of parts (such as metal parts, wood parts)To handle this volume, planners are generally organized around logical groupings of parts (such as metal parts, wood parts)

Critical Aspects of Using the MRP System The primary actions taken by an MRP planner are: Release orders (i.e. launch purchase or shop orders when indicated by the system)Release orders (i.e. launch purchase or shop orders when indicated by the system) Reschedule due dates of existing open orders when desirableReschedule due dates of existing open orders when desirable Analyze and update system planning factors for the part numbers under her controlAnalyze and update system planning factors for the part numbers under her control Find key problem areas requiring action now to prevent future crisesFind key problem areas requiring action now to prevent future crises Use the systems to solve critical material shortage problems so actions can be captured in the records for the next processingUse the systems to solve critical material shortage problems so actions can be captured in the records for the next processing

Critical Aspects of Using the MRP System Order Launching Process of releasing orders to the shop or to vendors (purchase orders)Process of releasing orders to the shop or to vendors (purchase orders) This process is prompted by MRP when a planned order release is in the current time period, the action bucket (if there is a nonzero quantity in the first week’s entry of the POR row, called action bucket, the computer issues an action notice).This process is prompted by MRP when a planned order release is in the current time period, the action bucket (if there is a nonzero quantity in the first week’s entry of the POR row, called action bucket, the computer issues an action notice). Order launching converts the planned order into a scheduled receipt reflecting the lead time offset.Order launching converts the planned order into a scheduled receipt reflecting the lead time offset. Order launching is the opening of shop and purchase orders; closing these orders occurs when scheduled receipts are received into stockrooms.Order launching is the opening of shop and purchase orders; closing these orders occurs when scheduled receipts are received into stockrooms. Procedures for opening and closing shop orders have to be carefully defined so all transactions are properly processed.Procedures for opening and closing shop orders have to be carefully defined so all transactions are properly processed.

Critical Aspects of Using the MRP System The orders indicated by MRP as ready for launching are a function of lot sizing procedures and safety stock as well as timing.The orders indicated by MRP as ready for launching are a function of lot sizing procedures and safety stock as well as timing. A key responsibility of the planner is managing with awareness of the implications of these effects.A key responsibility of the planner is managing with awareness of the implications of these effects. When an order is launched, it is sometimes necessary to include a shrinkage allowance for scrap and other process yield situations.When an order is launched, it is sometimes necessary to include a shrinkage allowance for scrap and other process yield situations.

Critical Aspects of Using the MRP System Allocation and availability checking A step prior to order launching that involves an availability check for the necessary component or components.A step prior to order launching that involves an availability check for the necessary component or components. The planner role is key here.The planner role is key here. If the components are not available for an order, the best course action might be to release a partial order.If the components are not available for an order, the best course action might be to release a partial order. Most MRP systems first check component availability for any order that a planner desires to launch.Most MRP systems first check component availability for any order that a planner desires to launch. If sufficient quantities of each component are available, the shop order can be created and then the system allocates the necessary quantities to the particular shop order (Shop orders are assigned by the computer, in numerical sequence).If sufficient quantities of each component are available, the shop order can be created and then the system allocates the necessary quantities to the particular shop order (Shop orders are assigned by the computer, in numerical sequence).

Critical Aspects of Using the MRP System Allocation and availability checking After availability checking and allocation, picking tickets are typically created and sent to the stockroom.After availability checking and allocation, picking tickets are typically created and sent to the stockroom. The picking ticket calls for a specified amount of some part number to be removed from some inventory location, on some shop order, to be delivered to a particular department or location.The picking ticket calls for a specified amount of some part number to be removed from some inventory location, on some shop order, to be delivered to a particular department or location. When the picking ticket has been satisfied (inventory moved), the allocation is removed and the on-hand balance is reduced accordingly.When the picking ticket has been satisfied (inventory moved), the allocation is removed and the on-hand balance is reduced accordingly.

Critical Aspects of Using the MRP System 2. Exception codes2. Exception codes Used “to separate the vital few from the trivial many”.Used “to separate the vital few from the trivial many”. If the manufacturing process is under control and the MRP system is functioning correctly, exception coding typically means only 10-20% of the part numbers will require planner review at each processing cycle.If the manufacturing process is under control and the MRP system is functioning correctly, exception coding typically means only 10-20% of the part numbers will require planner review at each processing cycle. Exception codes are in two general categories.Exception codes are in two general categories. The first, checking the input data accuracy, includes checks for dates beyond planning horizon, quantities larger or smaller than check figures, nonvalid part numbers, or any other desired check for incongruity.The first, checking the input data accuracy, includes checks for dates beyond planning horizon, quantities larger or smaller than check figures, nonvalid part numbers, or any other desired check for incongruity. The second category of exception codes directly supports the MRP planning activity.The second category of exception codes directly supports the MRP planning activity.

Critical Aspects of Using the MRP System Include are the following kinds of exception (action) messages or diagnostics:Include are the following kinds of exception (action) messages or diagnostics: Part numbers for which a planned order is now in the most immediate time period (action bucket).Part numbers for which a planned order is now in the most immediate time period (action bucket). Open order diagnostics when the present timing and/or amount for a scheduled receipt is not satisfactory. Such a message might indicate that an open order exists that's not necessary to cover any of the requirements in the planning horizon. The most common type of open diagnostic shows scheduled receipts that are timed to arrive either too late or to early and should, therefore, have their due dates revised to reflect proper factory priorities.Open order diagnostics when the present timing and/or amount for a scheduled receipt is not satisfactory. Such a message might indicate that an open order exists that's not necessary to cover any of the requirements in the planning horizon. The most common type of open diagnostic shows scheduled receipts that are timed to arrive either too late or to early and should, therefore, have their due dates revised to reflect proper factory priorities.

Critical Aspects of Using the MRP System A third general type of exception message indicates problem areas for management; in essence, situations where level 0 quantities can’t be satisfied unless the present planning factors used in MRP are changed. One such exception code indicates a requirement has been offset into the past period and subsequently added to any requirement in the first or most immediate time bucket. This condition means an order should have been placed in the past. Since it wasn't, lead times through the various production levels must be compressed to meet the end-item schedule. A similar diagnostic indicates the allocations exceed the on-hand inventory-a condition directly analogous to overdrawing a checking account. Unless more inventory is received soon, the firm will not be able to honor all pick tickets issued, and there will be a material shortage in the factory.A third general type of exception message indicates problem areas for management; in essence, situations where level 0 quantities can’t be satisfied unless the present planning factors used in MRP are changed. One such exception code indicates a requirement has been offset into the past period and subsequently added to any requirement in the first or most immediate time bucket. This condition means an order should have been placed in the past. Since it wasn't, lead times through the various production levels must be compressed to meet the end-item schedule. A similar diagnostic indicates the allocations exceed the on-hand inventory-a condition directly analogous to overdrawing a checking account. Unless more inventory is received soon, the firm will not be able to honor all pick tickets issued, and there will be a material shortage in the factory.

Critical Aspects of Using the MRP System 3. Bottom-up Replanning3. Bottom-up Replanning Used to solve material shortage problems.Used to solve material shortage problems. Solution might be made by compressing lead times throughout the product structure using the system and bottom-up replanning (i.e. issuing an immediate order to the vendor securing a promised shorter lead time, order more parts and negotiate a reduction in lead time)Solution might be made by compressing lead times throughout the product structure using the system and bottom-up replanning (i.e. issuing an immediate order to the vendor securing a promised shorter lead time, order more parts and negotiate a reduction in lead time)

System Dynamics It is essential that the MRP system mirror actual shop conditions; that is both the physical system and the information system have to cope with scrap, incorrect counts, changes in customer needs, incorrect bills of material, engineering design changes, and poor vendor performance.It is essential that the MRP system mirror actual shop conditions; that is both the physical system and the information system have to cope with scrap, incorrect counts, changes in customer needs, incorrect bills of material, engineering design changes, and poor vendor performance.

System Dynamics Transactions during a periodTransactions during a period Gross requirements Scheduled receipts 50 On hand inventory (10) Planned order releases 5050 LT=2 FOQ=

System Dynamics Lets assume that during week 1 the following changes occurred, and the transactions were processed: Actual disbursements from the stock for this part during week 1 were only 20 instead of the planned 50.Actual disbursements from the stock for this part during week 1 were only 20 instead of the planned 50. The scheduled receipt for 50 due in week 1 was received on Tuesday, but 10 units were rejected, so only 40 were actually received into inventory.The scheduled receipt for 50 due in week 1 was received on Tuesday, but 10 units were rejected, so only 40 were actually received into inventory. The inventory was counted on Thursday and 20 additional pieces were found.The inventory was counted on Thursday and 20 additional pieces were found. A scheduled receipt for 50 in week 3 is created.A scheduled receipt for 50 in week 3 is created. The requirement date for the 45 pieces in week 5 was changed to week 4.The requirement date for the 45 pieces in week 5 was changed to week 4. Marketing requested an additional 5 pieces for samples in week 2.Marketing requested an additional 5 pieces for samples in week 2. The requirement for week 6 has been set at 25.The requirement for week 6 has been set at 25.

System Dynamics ReschedulingRescheduling Gross requirements Scheduled receipts 50 On hand inventory (50) Planned order releases

Technical Issues Processing frequency Since conditions change and new information is received, the MRP records must be brought up to date so plans can be adjusted.Since conditions change and new information is received, the MRP records must be brought up to date so plans can be adjusted. Two issues are involved in the processing decision: how frequently the records should be processed and whether all the records should be processed at the same time.Two issues are involved in the processing decision: how frequently the records should be processed and whether all the records should be processed at the same time. Processing all the records in one computer is called regeneration.Processing all the records in one computer is called regeneration. This signifies that all part number records are completely reconstructed each time the records are processed.This signifies that all part number records are completely reconstructed each time the records are processed. The problem with processing less frequently is that the portrayal of component status and needs expressed in the records becomes increasingly out of date and inaccurate.The problem with processing less frequently is that the portrayal of component status and needs expressed in the records becomes increasingly out of date and inaccurate. More frequent processing of the MRP records increases computer costs but results in fewer unpleasant surprises (net-change systems).More frequent processing of the MRP records increases computer costs but results in fewer unpleasant surprises (net-change systems).

Technical Issues Safety stock and safety lead time Safety stock is a buffer of a stock above and beyond that needed to satisfy the gross requirements.Safety stock is a buffer of a stock above and beyond that needed to satisfy the gross requirements. Safety lead time is a procedure whereby shop orders or purchase orders are released and scheduled to arrive one or more periods before necessary to satisfy the gross requirements.Safety lead time is a procedure whereby shop orders or purchase orders are released and scheduled to arrive one or more periods before necessary to satisfy the gross requirements. Both safety stock and safety lead time are used in practice and can be used simultaneously.Both safety stock and safety lead time are used in practice and can be used simultaneously. Safety stock tends to be used in MRP systems where uncertainty about quantities is the problem (e.g. where some small amount of scrap, spare part demand, or other unplanned usage is a frequent occurrence). Safety lead time tends to be used when the major uncertainty is the timing rather than the quantity. For example, if a firm buys from a vendor who often misses delivery dates, safety lead time may provide better results than safety stock.Safety stock tends to be used in MRP systems where uncertainty about quantities is the problem (e.g. where some small amount of scrap, spare part demand, or other unplanned usage is a frequent occurrence). Safety lead time tends to be used when the major uncertainty is the timing rather than the quantity. For example, if a firm buys from a vendor who often misses delivery dates, safety lead time may provide better results than safety stock.

Technical Issues Gross requireme nts Scheduled receipts On hand inventory (15) Planned order releases 2310 Safety lead time=1 LT=1 L4L An MRP Record with Safety Lead time

Technical Issues Gross requirements Scheduled receipts 230 On hand inventory (37) Planned order releases Safety stock=80 LT=2 Lot size=230 An MRP Record with Safety Stock © Mc-Graw Hill