Why do we need a new pool? The original pool was built in 1973 with a 20 year life expectancy For many years, infants/toddlers have had very limited,
Purpose of Town Hall Meeting Share progress on improvement projects Discuss details of potential projects under consideration by POA Board Gather input.
Department of Public Works Robinson Park Recreation Center Renovation – Revised Selection Process for Design Services November 4, 2013.
Facilities & Capital Construction Program Overview Program Overview Project & Scope Schedule Alternative & Traditional Procedure Approaches E-Builder.
The Dirt Lot Initiative This proposed project was part of last year’s Capital Project Improvement Plan There has been an obvious risk associated with its.
2015 Municipal Budget Overview Borough of Montvale April 14, 2015.
Town of Carver Review of Proposed Plan for Fire and Police Facilities November 12, 2013 EDWARD J. COLLINS CENTER FOR PUBLIC MANAGEMENT.
RETROFITTING EXISTING SWM PONDS BETTER THE SECOND TIME AROUND Lise Soukup, P.E. Environmental Engineer City of Rockville, Maryland.
ACQUATICS FACILITY STUDY City of Vincennes Department of Parks & Recreation.
Quarryville and High School Project Cost Estimates September 2013.
Swimming Pool Feasibility study Town Hall Presentation 14 August 2013.
Business Planning j Through operational management.
Guidelines for RTF Measure Economics Estimation Methods (formerly Cost and Non-Energy Benefits Guidelines) Progress Update to the Regional Technical Forum.
Draft Rancho Colorados Swim & Tennis Club Master Plan Overview.
Water System Planning Study
CITY OF MONROE FISCAL YEAR BUDGET PRESENTATION EDWARD SELL, FINANCE DIRECTOR.
Objectively evaluate our property in the marketplace Owners Real Estate Companies Rental Companies Consider Future Options to: Maintain market competitiveness.
Reserve Study A Short and Long Term Budgetary Planning Vehicle
© Huron Consulting Services LLC. All rights reserved. © Huron Consulting Group Inc. All rights reserved. Neither Huron Consulting Group Inc. nor any of.
Pinole Valley High School (PVHS) Project Status
Arapahoe Estates Community Annual Meeting February 26, 2009.
Proposed Modifications to the Gated Community Ordinance Board of County Commissioners April 8, 2008.
Department of Public Works Arroyo Seco Casting Pond Renovations Contract Award to Mallcraft, Inc.
SUN CITY HILTON HEAD COMMUNITY ASSOCIATION, INC. PURRYSBURG POOL UPDATE.
Capital Reserves. What are Capital Reserves? A separate account set up by the Association to fund large, non-annual repairs – Stormwater pond repair,
Fiscal Committee Recommendations 2016 & 2017 Repair & Replacement Reserve Funding Amounts July 2015.
PA-1 Surface Water Control Structure Replacement Final Payment.
2011/12 FINANCIAL OUTLOOK April 2011 John Holme, Principal Finance Manager ACS.
Week 6 The Energy Walk Through. Possible elements of a walk through Understand on-site information collection and listing of essential data for collection.
1 DESIGN RESPONSIBILITIES Contract Information Supplied by Design Team Responsibility of the Precaster Option I Provide complete drawings and specifications.
POOL CONSTRUCTION THE 5 MAJOR STEPS 1. Plan2. Dig3. Build4. Finish 5. Swim!
Memorial Northwest HOA 2014 Budget. Budget Process Review & Evaluate prior year Budget & Actual Identify new requirements Map the spending to the GL accounts.
WEDGEWOOD COVE HOA STREET PAVING/RESURFACING PROJECT.
1. FY Proposed Budget Jamie Justice, Town Manager & Piet Swart, Finance Director April 26, 2016 Fiscal Year Proposed Budget 2.
TRUMAN MIDDLE SCHOOL Presented by Counsilman ▪ Hunsaker Facility Audit.
1 GCC Annual Meeting 2014 Call to Order Voting Presentation President’s Remarks Membership Report Financial Report Facilities Report Kitchen and Dining.
Facility Committee June 17, Othello Community Pool Features: Leisure amenities: including a 2,800-square-foot leisure pool, lazy river and spray.
South Greenville Recreation Center and Park Master Plan.
PORT OF TACOMA. Contract Increase & Award Pier 7 Structural Repairs Request authorization to expand the scope of existing A/E Contract No and.
THE FUTURE OF THE CARTER PARK POOL WHAT WE’RE DOING TONIGHT  Comprehensive Overview of How We Got Here  Review of Survey Results  Presentation.
PRESENTED AND PREPARED BY CITY OF MISSOULA PUBLIC WORKS DEPARTMENT.
Palisades Middle School: Fitness Center Board Presentation April 20, 2016.
Town of Enfield : Upgrading the Water Pollution Control Facility & Collection System Jay Sheehan, PE Michael Burns, PE.
Draft 1 – 2016/2017 Biennial Capital & Operating Budgets July 2016.
CITY COUNCIL OCTOBER 18, 2011 Central Park Gazebo Replacement.
1.  Quick Overview of the History and Need  What is Planned for the Fire Department  What is Planned for the Police Department  Financial Details.
EASTERN MUNICIPAL WATER DISTRICT Public Access Areas Renovation Project – Update Debbie Hoffman, PE Civil Engineer II March 23,
Planning & Community Development Department Rose Bowl Aquatic Center Master Plan 360 North Arroyo Boulevard Predevelopment Plan Review PPR City.
White Pigeon Community Schools
De Pere Aquatic Presentation
Overview of MSBA Building Process and Project Timeline
Belen Eagles Natatorium
Capital Improvements Plan
Bond and Override Report
What is an on-lot sewage system?
UTSA Capital Projects Update Facilities, Engineering & Projects
Town of Melbourne Beach
2018 Adopted Budget February Financial Plan
Finance Summer Training
Henderson Park Family Outdoor Aquatic Centre Renovation
PROJECT DELIVERY METHODS
Capital Project Update
Presented to the School Board -- July 21, 2011
Capital Construction Project Update March 12, 2019
Forest Rim Informational Meeting Deferred Maintenance
Q2 Updates on 2019 Board Priorities
Q2 Updates on 2019 Board Priorities
Presentation transcript:

Fox Point Homeowners Association October 30, 2013

Meeting Overview Why a new pool? Williams design plan HOA finances – how to pay for the project Project timetable

Pool Studies/Reports 2005 PHN Architects Pool Study 2006 Committee Report 2010 PHN Architects Pool Study 2011 Independent Aquatic Engineer Report 2011 Systems Assessments -- made it clear that our pool was at its “end of life”. Deck drainage and piping of entire pool area in need of total replacement due to failure (broken and clogged). Dye test revealed leaks in the pool wall, gutter and pit

2012 Renovation Application 2011 Board engaged architect to explore renovation versus replacement. Application to state started at $ K plus contingency -- $650K tipping point. IDPH additional requirements drove cost to $700K for renovation of main pool.

Why a New Pool? Renovation $700K+ to meet current codes. Building a new main pool structure was projected to be $1.0M. Renovation based on good sound concrete pool shell Lifespan of renovation years vs. new years Diving well not compliant with code and starting block depth shallow by current standards

New Pool Architect and Plan Selection Pool Subcommittee formed – Elaine Leighton, Tom Malia, Doug Zwiener, Keith Gritzek, Lynn Douglas, Geoff Ommen and Seth Gering (pool manager). Subcommittee interviewed 3 firms in summer 2013 (2 architects, 1 builder)– asked them to present their vision for the pool and a complete project proposal (budget estimate, plans, construction management through project completion) Subcommittee selected Williams Architects based on their experience, project management abilities with in-house aquatic engineering, and creative vision for pool project.

Scope of Work Revised Original $1.0M budget was to replace the L shaped pool shell and deck, keeping the existing tot pool and mechanical equipment. Existing mechanicals (filtration) would potentially work with new pool design but require additional components to meet code. New heaters required for main and tot pools. Better to replace all systems for efficiency and lower operational costs. To repair tot pool deck requires new tot pool (and shed/mechanicals).

Fox Point Pool Priorities Pool subcommittee met with Williams several times to identify the top user priorities. Competitive swimming with 6 lanes Deep water area for recreation and diving/water polo Diving board Lap lane available at all times Maximum usable deck surface area Tot pool

Design Options Subcommittee and Williams met several times to discuss design alternatives that would best suit our users. Exact same “L” shaped layout Rectangle pool with deep water Modified rectangle pool with step-in area Tot pool vs spray pad Optional features: drop/flume slides, high diving board, separate spray pad

Pool Design Elements Main rectangle pool Increases recreational deep water use Diving board easily removed Better sight lines for staff and parents Easier to clean and maintain Step-in area Easier access for older adults and parents with young kids Allows parents with younger and older children in pool together Feature will appeal to adults away from more active play Tot Pool

Williams Pool Design

Water Features

Initial Cost Estimates New main pool*$1.2M - $1.3M Step-in area$106K- $120K Shade structures$30K - $40K Tot pool/building**$252K - $283K TOTAL$1.6M - $1.7M * decks/drainage/mechanicals/fencing/lighting/electric/hose hydrants/rework filter room plus architect/legal/construction management **decks/drainage/mechanicals/fencing/lighting/electric/new equipment shed plus architect/legal/construction management

Tot Pool Estimate 1000 sq. foot pool$120,000 New mechanical shed 20,000 Decks/fencing 30,000 Lighting/power 11,000 Demo/earthwork 14,000 Utilities allowances 15,000 Design fees/contingencies 34,000 Sprays/bubblers 8,000 TOTAL$252,000

How Does Pool Impact Reserves? Starting Balance 1,829, Dues Allocation 170,000 Potential Capital Expenditures-Non-Pool (75,000) 2015 Dues Allocation 170,000 Potential Capital Expenditures-Non-Pool (75,000) Sub-total 2,019,000 Estimated Pool Expenditure(1,700,000) Remaining Post-Pool Reserves 319,000 Projected Reserve’s Replenishment Annual Dues Allocation 170,000 Average Non-Pool/Non-Lake Capital Expenditures (53,000) Annual Addition to Reserves: 117,000

Project Timetable Oct-Dec 2013 – Design Development/Construction Documents Jan-Mar 2014 – Submit application to IDPH/Obtain permit Apr-Jun 2014 – Bid and award construction contract Late August 2014 – Construction begins May 2015 – New pool opens