112/06/2012. Summary  Network infrastructure consolidation & upgrade 66 kV et 18 kV  UPS SILCON replacement project  Projects and maintenance work.

Slides:



Advertisements
Similar presentations
CERN IT Department CH-1211 Genève 23 Switzerland t Mobile services: Sunrise SWAP Rodrigo Sierra IT/CS.
Advertisements

Long shutdown 2013: Electrical distribution activities 09/03/2012 IEFC 2012 Workshop F. Duval on Behalf of EN/EL group.
LHC UPS Systems and Configurations: Changes during the LS1 V. Chareyre / EN-EL LHC Beam Operation Committee 11 February 2014 EDMS No /02/2014.
Consolidation program SPS Main Power Converters (Dipole & Quadrupole) K. Kahle / Q. King / G. Le Godec (TE-EPC) IEFC Workshop, 9 March 2012.
Fibres & copper Cabling activities LIU meeting 27/09/2013 F Duval 27/09/2013 F Duval Cabling acxtivities LIU 1.
INFRASTRUCTURE SYSTEMS & RADIATION EFFECTS J.P. Saraiva (CERN R2E Project) October 14, 2014 R2E & Availability Workshop.
Christophe Delamare EDMS Accelerator Consolidation Workshop GS/ASE activities.
The HiLumi LHC Design Study is included in the High Luminosity LHC project and is partly funded by the European Commission within the Framework Programme.
Preliminary Studies of the Electric Power Distribution for CLIC
CV activities on LHC complex during the long shutdown Serge Deleval Thanks to M. Nonis, Y. Body, G. Peon, S. Moccia, M. Obrecht Chamonix 2011.
1 EL Consolidation IEFC Workshop F. Duval on behalf of EN/EL
Consolidation of access systems for the injector Complex ATOP days 4-6 March 2009 P. Ninin & R, Nunes in behalf of the PS and SPS access project teams…
EN-EL and LS2 Gerard CUMER, EN-EL february Presentation outline 2 Part 1 : Overview of CERN’s electrical network Part 2 : Power Quality _ Statistics.
Barriere O, Le Roux P
112/09/2013. Summary  Events on the network  Incidents  Network reconfigurations  Network operation  Update on activities  Tests  Projects and.
Review of the Project for the Consolidation and Upgrade of the CERN Electrical Distribution System October 24-26, 2012 THE HIGH-VOLTAGE NETWORK OF CERN.
Accelerator Consolidation Workshop TE/EPC consolidation plan 2 Jean-Paul Burnet ACC consolidation day, 12/09/2013.
Safe-Room Status Intermediate ‘Conclusions’ M. Brugger (based on HSE discussion)
LS1 : EL Upgrades & Consolidation Chamonix– February 8 th 2012 F. Duval on behalf of EN/EL The goal of LS1 is to implement everything needed for a safe.
Follow-Ups and Notes. Project News LMC R2E (SEE Events) Update (see link)link RadWG SEE list (link) and Post-Mortem Database (link) synchronizedlink MCWG.
Review of the Project for the Consolidation and Upgrade of the CERN Electrical Distribution System October 24-26, 2012 THE HIGH-VOLTAGE NETWORK OF CERN.
 A brief history of time  In the years BC.  My years at CERN  Current position  What is a Technical Coordinator?  The different type of intervention.
Booster LV Electrical Distribution: Schedule and Quantities Aims: Modernisation of Booster electrical infrastucture To install necessary infrastructure.
Consolidation and Upgrade of the SPS Electrical Networks Current Status JP. Sferruzza, on behalf of EN/EL.
Injectors & LHC report K. Foraz on behalf of OSS members 14/06/2013LSC - K. Foraz1.
EN-CV interventions during YETS
How to keep the Injectors running for another 25 years S Baird (on behalf of EN/MEF/ABA) LHC Performance workshop Chamonix January 2010.
Activities related to Experiments during TS3 and YETS th November, 2015 M. Bernardini, M. Barberan With the support of S. Chemli and Experiments.
Consolidation activities for GS-SE Luigi Scibile GS-SE Accelerator Consolidation Workshop, EDMS:
ATC/ABOC Days, 22 January 2007 The safety electrical networks at CERN Anne Funken, TS-EL.
Cooling & Ventilation feed-back M. Nonis – EN/CV.
LHC-YETS Coordination meeting #9 24 th November, 2015.
LS1preparation & planning status A L Perrot on the behalf of EN/MEF R2E project meeting 11 th May 2012 EN.
Overview of the main events related to TS equipment during 2007 Definition Number and category of the events Events and measures taken for each machine.
Long shutdown 1 LHC Machine Status Report K. Foraz June 12 th, 2013.
On behalf on EN-EL October 1 st, 2015 YETS Works EN-EL [ CF excluded ]
Consolidation needs for the Electrical Distribution, Control Cables and Optical Fibres Equipment F. Duval.
Overview of the LHC Year End Technical Stop
Conclusions on UPS powering test and procedure I. Romera Acknowledgements: V. Chareyre, M. Zerlauth 86 th MPP meeting –
EN-EL Activities for LS2 LIU, Consolidation, Maintenance, Operation Nicolas Bellegarde on behalf of EN-EL.
R2E relocation & shielding LS1 preparation Anne Laure Perrot EN/MEF- LE Discussion with OP colleagues, 5 th July 2012.
Each converter 3 racks (fighting for 2?) Access from front and rear of each rack! 56 racks total + 6 racks Ethernet/control Existing RF equipment to be.
Injectors & LHC report S. Baird and M. Bernardini on behalf of OSS members 20/09/2013LSC - EN-MEF-OSS1.
Proposal for rerouting of buried electrical networks and optical fibres at Point 1 LS2 Committee meeting S. Bertolasi on behalf on EN/EL WP17.2 HL-LHC.
CV works in the non- LHC accelerator complex during 2008 and plans for 2009 ATOP days 2009.
R2E relocation & shielding activities: status report Anne Laure Perrot EN/MEF- LE On behalf of the R2E coordination team LS1 Committee – meeting #48, 27.
EDMS N° V.1 TE-EPC Activities during LS1 V. Montabonnet [TE-EPC]
Fire and Oxygen Deficiency Detection Systems Risk Analysis S. Grau GS-ASE-Alarm Systems R2E Workshop, Tuesday Session 2: Equipment inventory,
LS1 Day: The Injectors S. Baird EN/MEF Thanks to R Brown, N Gilbert, D McFarlane & V Chohan, IEFC workshop…. LS1 Day: The Injectors 1.
YETS & LS2 Works EN-EL / Power distribution
Linac4-PSB 160 MeV connection readiness review
EYETS Works EN-EL [ FC excluded ]
YETS & LS2 Works EN-El on LHC / Power distribution
LHC Hardware Commissioning Training
EYETS LHC 2016/2017 Works EN/EL/CF
K. Foraz on behalf of OSS members
TE-MPE LS1 review Vision from EN-EL(CF)
the high-voltage network of CERN ToMORROW
LV Safe Powering from UPS to Clients
Accelerator and Experiment Interface Session: LS2, LS3
PSB/PS/TT2/Linac2-3 YETS 2017–2018 & LS2 preparation meeting
SPS EN-CV Planning LS (initial draft)
the CERN Electrical network protection system
SPS activities during LS2 TE-EPC (Power Converter Group)
GIS PORTAL RACKS Integration of Equipment Racks in the Geographic Information Service (SMB/SE) Olivier Barrière.
YETS & LS2 Works EN-EL / Power distribution
TE-MSC activities in SPS during YETS
PS Booster Report from: David HAY, Cyrille BEDEL 12-Jan-2018
Business opportunities related to CERN electrical network
ILO Industrial Opportunities Days, 6-7 June 2019
Presentation transcript:

112/06/2012

Summary  Network infrastructure consolidation & upgrade 66 kV et 18 kV  UPS SILCON replacement project  Projects and maintenance work on substation 400 kV & 66 kV  Maintenance works on 18 kV, 3.3 kV and LV networks  Yearly tests  Other EN/EL consolidation & upgrade projects  Projects for other groups  R2E  Cables & fibres projects  Schedule  Workloads  Increase of manpower EN/EL activities during LS1 212/06/2012 LS1 Day - François Duval EN-EL

66 et 18 kV Networks Consolidation & Upgrade 3  power cables replacement18 kV SPS  New substation BE91in Prévessin (Safe feeding of CCC safety network for SPS)  Repowering CCC  66 kV Protection system consolidation (Prévessin and LHC )  Extension of the 66 kV substation Prevessin  New 66 kV feeder on Meyrin site + upgrade of the18 kV substation in the west area ME59  New power link18 kV ME9 –ME59 in Meyrin and Autotransfert modification accordingly  Upgrade main18 kV substation in Prévessin du BE  Consolidation of fire protection systems for power transformers and for the 400 kV substation  Consolidation of the18 kV substations BA4 et BA5  requirements  depending mainly on the injector schedule (2013 !)  Total budget = 20 MCHF 12 Juin 2012LS1 Day - François Duval EN-EL

66 et 18 kV Networks Consolidation & Upgrade 4 12 Juin 2012LS1 Day - François Duval EN-EL 2013 Upgrade sous station BE 2013 Upgrade sous station BE Réseau secours Prevessin et SPS Réseau secours Prevessin et SPS Sous station BE SPS consolidation SPS consolidation Rénovation protection 66 kV Rénovation protection 66 kV Nouvelles lignes 66 kV et 18 kV vers Meyrin Nouvelles lignes 66 kV et 18 kV vers Meyrin

66 et 18 kV Networks Consolidation & Upgrade 5 12 Juin 2012LS1 Day - François Duval EN-EL Nouvelles lignes 66 kV et 18 kV vers Prevessin Nouvelles lignes 66 kV et 18 kV vers Prevessin Nouvelle sous station 66 kV MEH Nouvelle sous station 66 kV MEH Nouvelles liaison 18 KV entre ME9 –ME Nouvelles liaison 18 KV entre ME9 –ME Upgrade sous station ME Upgrade sous station ME59

6 12 Juin 2012LS1 Day - François Duval EN-EL LS1 EN-EL activities Power distribution and Operation

Replacement of SILCON UPSs 7  All cryo and machine : 82 UPS  Any new UPS connections  Requests must be done before end of June Juin 2012LS1 Day - François Duval EN-EL UPS machine : 2 UPS in RE (x16) 2 UPS in UA (x8) 2 UPS each LHC point (US, UW ou UJ) (x8) UPS cryo : 2 UPS on LHC even points (US, UW) (x4) 2 UPS on surface even points (SA, SH) (x4) 2 UPS in PM18

Replacement of SILCON UPSs 8  Impact on other activities:  6 weeks per area (for 2 UPS)  Distribution downstream off during works  Possible refeeding from diesel network (subject to request justified by safety)  Transport and handling:  ~ 660 kg for an UPS and 2000 kg for battery sets (removal of old ones as well )  Lifts on Points 3, 5 et 7 too small for UPS : Width > 800 mm  Alcoves RE : A safety issue has to be considered: Charging batteries may lead to hydrogen production. Ventilation must be dimensioned so that the risk of explosion is eliminated (EN/EL, GS/ASE, HSE) 12 Juin 2012LS1 Day - François Duval EN-EL

66 & 400 kV Substations Maintenance & Projects 9  Maintenance  400 kV & 66kV substations  Tests of the protection and signals on the RTE interfaces  On-site maintenance of two 400 kV circuit breakers  Factory maintenance of three 400 kV circuit breakers  Maintenance of the 400 kV & 66kV transformers  Projects  Consolidation of the66 kV protection (BE & LHC )  Extension of the 66 kV substation  Consolidation of the fire detection of the 400 kV substation & its transformers  Schedule contraints 12 Juin 2012LS1 Day - François Duval EN-EL RTE (400 kV)Disconnected during 3-4 weeks ALPIQ (SIG)60 MVA max during 8 weeks after the LHC warm-up Réseau de transport 66 kVOff during 8 weeks AUTOTRANSFERTInoperable during 8 weeks Tests AUG LHCCannot be done during this time

1007/06/ & 400 kV Substations Maintenance & Projects

18 kV, 3.3 kV & LV Networks Maintenance 11  1/3 of the equipment 18 kV et 3.3kV : 400 cubicles  LHC General Services LV switchgears  LHC Safety Network LV switchgears  Replacement of all breakers dedicated to the LHC safety network switching  LHC Diesel PLC consolidation  LHC 18 kV & 400 V switchgears in the alcoves  Planning - requirements  Slots of 5 to 6 days for each LHC points (including the AUG tests on the last day)  No underground access for 2 to 3 days (safety network not available)  No handling operations for 5 days (distribution off  cranes off)  No 18 KV maintenance during 400/66 kV maintenance operations  No safety network maintenance while AUTOTRANSFERT is off  Necessary coordination with CRG & CV 12 Juin 2012LS1 Day - François Duval EN-EL

Yearly Test Campaigns 12  Diesel and safety network  AUTOTRANSFERT  AUG  Schedule - requirements  PS / SPS magnet tests and run CTF3 until december 2012  Warm-up LHC Cryo  To be scheduled:  end 2012 or early 2013  end 2013 or early 2014  end 2014 ?  No AUG tests during maintenance on 400 kV 12 Juin 2012LS1 Day - François Duval EN-EL

Other EL Consolidation Projects Juin 2012LS1 Day - François Duval EN-EL DescriptionConfirmed ?Technically defined? Consolidation following task force «48V LHC2» (LHC)yesyes (2012) obsolete LV switchgears (ME23, ME24)yes Replacement of obsolete switchgears (LHC, MEY)yes Replacement of LHC safety network PLC & Circuit breakers yes Consolidation of LHC Diesel PLCnono (LS2) Increase reliability of AUG in LHCyes Consolidation of EL SCADA systemyes

Projects for other groups EN/CV Juin 2012LS1 Day - François Duval EN-EL EL & CV meeting on 04/05/2012 New meeting to be scheduled asap DescriptionConfirmed ?Technically defined for EL? Upgrade pumping station PM32yes SU2 & SU8 TRANE motors replacementyes New cooling tower SHM LHC4yesno (on its way) New cooling tower LHC6 & LHC8yesno (on its way) New chiller SPS-BA3no Closing collimators area LHC7nono (Major issue) Upgrade ventilation PS : Design and supply the new power supply for the ventilation units. yesno Safety measures for LHC: deltap tunnel UX85: New power line yesno New chillers SU2 for Alicenono (on its way)

Projects for other groups TE/EPC Juin 2012LS1 Day - François Duval EN-EL DescriptionConfirmed ?Technically defined for EL? LHC filters protections from FIR to TENCH (new sepams ?) yes Converters replacement FMCM SR1 et SR5no Control cabling for transformers SMB ?yesno BEQ2 et BEQ3 protections from baycontroler to PLCyesno SVC : 18 kV cables LHC2 replacementyes New feeder18 kV SMB for SPS 3yesno SPS Mains Converters: Consolidation : Supply and installation of Earthing Switches and 18kV cables yesno EPC High Voltage Power Converter Test Bench: Construction in building 377 yes EPC Medium Power Converter Test Bench: Construction in building 287 yesno Last meeting 7 th of June 2012: Most of the requests clarified and will be defined soon. Most of the requests scheduled on 1 st semester 2014

Projects for other groups various Juin 2012LS1 Day - François Duval EN-EL DescriptionConfirmed ?Technically defined for EL? 513 Upgrade automatic Normal / Secoursyes HIE ISOLDEyes LV infrastructures for bungalows SMACCyesNo, but on its way(2012) LINAC 4yes Moving transformer  Civil Engineering on the Route Goward over the PS no Electrical power supplies to new cranes. HE consolidation yesno ELENA Extra Low Energy Antiproton (hall 193) no COMPASSno

R2E Relocation of equipment 17  Locations  UJ14, 16, US15, UJ56, USC55, UL55, UL557, UJ76, TZ76, PM76, US85, UL84.  Work scheduled during all LS1.  Contractors EMTE (Points 1, 7, 8) & SPIE (Point 5).  Impact on other activities:  Difficult access to the work zone, transport not easy, limited co-activity (pts 5 (UP, UL) & 7 (TZ))  Coordination:  Works done with MEF, MTE, EPC, CV, HE, EN-EL (consignation/déconsignation) 12 Juin 2012LS1 Day - François Duval EN-EL

R2E Interruption of Service 18  Locations  UJ14, 16 – UJ56 (+ adjacent tunnel area) – UJ76 (+ adjacent tunnel area) – US85 (+ adjacent tunnel area)  Impact on networks and personnel safety:  UPS network (EOD) : consignation schedule compatible with WARM-UP cryo & other works?  Converter network (ERD) en UJ14-15, UJ56, UJ76  Réseaux canalis racks – consignation schedule compatible with WARM-UP cryo & other works?  The safety network (ESD) & general services networks (EBD – plugs & Lighting) will be operational during works but during 2 weeks, including one week without any EL safety systems: 48 VDC, AUG and safety lighting. Presently scheduled : October / November Juin 2012LS1 Day - François Duval EN-EL

Replacement of water cooled cable hoses : 1907/06/2012  Locations: UA/RA47, 63, 67, 83 et 87  12.5 months. Contractor: FLOHE, Supply: FLOHE & Contitech m.  Impact on other activities:  Access to UAs & RAs, scaffolding around converters, access to RA tunnel close to DFBs  Coordination:  Works done with CV, EPC, MEF, HE, MTE & EN-EL (consignation/décons.)  Schedule  2 shifts will not be possible (limited FLOHE manpower) LS1 Day - François Duval EN-EL

basket 1, 2 Cable tray New cable baskets LHC 1, 3 et /06/2012  following ALARA 01/2012  Locations: R34, R36, R37 – 2 cable baskets on 550m.  3 full months. Contractor C209, supply C209.  Other areas: RB14, 16, R542, 561: câblofil/télex installation on the ground.  Impact on other activities:  Access to the tunnel pt 3, difficult transport activities.  Coordination:  Works done with MEF et EN-HE et EN-EL (Integration)  Schedule: Lead by RP. New cables to be installed in point 3 (TE-VSC) LS1 Day - François Duval EN-EL

12 Flexwell cables replacement PM /06/2012  Locations: SR4, SL42, SD4, PM45, UJ44, UJ46, RA43, RA47  4 full weeks. Contractor: EMTE, supply: CERN.  Impact on other activities:  Access to PM45, RA up to 12 cell including areas behind DFBs.  Coordination:  Works to be done with BE-RF, MEF, MTE, EPC (consignation/décons.)  Schedule:  to be defined with MEF et BE-RF (tests and connectors mounting). Removal of 10km and installation of 7.4 km of Flexwell cable 7/8. LS1 Day - François Duval EN-EL

TOTEM: modification of WCC circuits 2207/06/2012  circuits RQ 4, 5, 6, 7, 8, 9, 10  Locations: RR53 & 57  5 full months on both sides  Contractor FLOHE, supply: Technical Specification to be written.  Impact on other activities:  Access to RR53 et 57, transport. Works above converters.  Coordination:  Work to be done with MEF, HE, CV, TE-EPC, TE-MPE & EN-EL (Integration, consignation/décons.)  Schedule:  to be defined with MEF. RR53 DFB LS1 Day - François Duval EN-EL

 Many requests from other groups and from the experiments to be finalised (CRG, ASE, etc.)  Experiments requests were not included in LS1 EN-EL activities 2307/06/2012 LS1 Day - François Duval EN-EL

S 12 P1P1 S 23 P2P2 S 34 P3P3 S 45 P4P4 S 56 P5P5 S 67 P6P6 S 78 P7P7 S 81 P8P8 N ov. D ec. J an. F eb. M ar. A pr. M ay J un. J ul. A ug. S ep. O ct. N ov. D ec. J an. F eb. M ar. A pr. M ay J un EN Feb. 8th 2012K. Foraz - LHC Performance Workshop PT Splices Cryo Maint. -> 10K CSCM CSCM preparation Warm-up Powering Tests Cool-down Travaux 400 kV et 66 kV – Pas d’autotransfert – S CERN <60MVA Consignations pour R2E ?

Summary of HV, LV & Controls during LS Juin 2012LS1 Day - François Duval EN-EL Projects + Maintenance + Tests EL & other groups Workload for High Voltage, Low Voltage & Controls Sections Requirements / Resources > 1,2 In particular during 2 nd semester 2013)  More resources More requests are not affordable

Cables & Fibres: Requests from BE Juin 2012LS1 Day - François Duval EN-EL

Cables & Fibres: Requests from TE Juin 2012LS1 Day - François Duval EN-EL VSC requests were not fully considered yet

Cables & Fibres: Requests from PH Juin 2012LS1 Day - François Duval EN-EL

Cables & Fibres: Requests from IT Juin 2012LS1 Day - François Duval EN-EL

Cables & Fibres 30  The preparation work behind the cabling workload estimate 12 Juin 2012LS1 Day - François Duval EN-EL

Cables & Fibres Juin 2012LS1 Day - François Duval EN-EL requirements/resources The LS1 Project Leader decided

Cables & Fibres 32  Additional resources  AGH (12 project associates from Krakow)  Fellows & associates (+10 in 2011/2012)  2 installation contracts (doubled manpower)  FSU being prepared  Specialists + project managers required (skilled and experienced people) 12 Juin 2012LS1 Day - François Duval EN-EL

Cables & Fibres 33  Help from other departments & experiments We still want new people working with EL team in order to have coherent works done  Work supervisors  Knowledge and experience of cable laying or fibre blowing technologies  Experience in work site supervision  Knowledge of site works  Project managers  Project management  People management  Schedule & Budget management  Knowledge of dedicated softwares(GESMAR, Câblothèque) 12 Juin 2012LS1 Day - François Duval EN-EL

Cables & Fibres 34  But there are limits to the increase of manpower:  Lack of experience  Increase of manpower of contractors  CERN access, hotels, logistics bottle neck, Base vie?  Schedule/coactivity 12 Juin 2012LS1 Day - François Duval EN-EL

35  LS1 will be a very huge shutdown also for EN/EL  On the HV & LV infrastructure side, The program will be done with some additional resources  On the cables & fibres side, the situation is critical: prioritization is done but the effort is huge for the section in charge. Additional resources have been deployed from other departments: more are needed.  We are worried about the flow of requests which are still popping up in or elsewhere 12 Juin 2012LS1 Day - François Duval EN-EL EN/EL activities during LS1: Conclusion