Task Force on Safety of Personnel in LHC underground areas following the accident in sector 3-4 on 19-09-2008 Ghislain Roy, on behalf of the Task Force.

Slides:



Advertisements
Similar presentations
Improved anchoring of SSS with vacuum barrier to avoid displacement Ofelia Capatina (speaker), Katy Foraz (coordinates all the activities), Antonio Foreste,
Advertisements

LHC HARDWARE COMMISSIONING REVIEW May 2005 CRYOGENIC VACUUM SYSTEM Paul Cruikshank for AT/VAC.
LHC Performance Workshop - Chamonix January 2010 Session 4 - Safety for Personnel Underground - He Evacuation What can the Safety Coordination.
SAFETY FOLLOW-UP HL-LHC PROJECT WP17 – Infrastructures meeting S. La Mendola, Jose Gascon DGS/SEE 09 July 2015.
Laurent Tavian Thanks to contribution and helpful discussions with M. Jimenez, V. Parma, F. Bertinelli, J.Ph. Tock, R. van weelderen, S. Claudet, A. Perin,
The HiLumi LHC Design Study (a sub-system of HL-LHC) is co-funded by the European Commission within the Framework Programme 7 Capacities Specific Programme,
LHC HARDWARE COMMISSIONING SAFETY TRAINING DAY S. Claudet (AT-ACR-OP) With great help from G. Lindell (Safety commission) CRYOGENICS.
CV activities on LHC complex during the long shutdown Serge Deleval Thanks to M. Nonis, Y. Body, G. Peon, S. Moccia, M. Obrecht Chamonix 2011.
CLIC CES Webex 12 Nov Summary: – Set of fire safety measures defined in CERN Safety Report – Proposed Structure for CLIC/ILC Fire Safety Report Fabio.
Consolidation of access systems for the injector Complex ATOP days 4-6 March 2009 P. Ninin & R, Nunes in behalf of the PS and SPS access project teams…
The HiLumi LHC Design Study (a sub-system of HL-LHC) is co-funded by the European Commission within the Framework Programme 7 Capacities Specific Programme,
Joint ILC/CLIC Safety document ► Incentive for this document:  Share effort to define a coherent safety protocol for future linear colliders.  Insure.
Helium Spill Test in LHC tunnel to define length of restricted working areas  Actual situation  Evolution  How to continue  Set-up of the spilling.
LHC ACCESS SYSTEM 1Authors: P, Ninin, S. Grau & LHC access team EDMS: Access System during the LHC Injection tests P. Ninin, S. Grau - TS/CSE Workshop.
Workshop Chamonix XIV Shortcuts during installation and commissioning: risk and benefit H. Gruehagen, G. Riddone on behalf of the AT/ACR group 18 January.
LHC Access System August 2006 LHC Access System – Status and Planning August 2006 Elena Manola-Poggioli Eva Sanchez-Corral TS-CSE on behalf of the LHC.
July LEReC Review July 2014 Low Energy RHIC electron Cooling Edward T. Lessard ESHQ.
TS Workshop, Archamps, May 24 – May 26, 2005 The LHC Access System Status report – May 2005 P. Ninin & the Access project team TS/CSE.
LHC Fire & Gas Detection Rui Nunes ST/AA/AS. Rui Nunes ST/AA/AS - STTC 21 Feb 2000 Project Goals Install in LHC –Fire Detection –Flammable Gas Detection.
Status Report from LHC Safety System Task Force Emmanuel Tsesmelis / TS-LEA on behalf of the Task Force LEAF 11 May 2007.
LHC ACCESS SYSTEM 1 Authors: P. Ninin, L. Scibile, T. LadzinskiEDMS: Access Control and Safety System for the LHC Experiments P. Ninin L. Scibile.
1 EARLY SAFETY MANAGEMENT OF PROJECTS AND EXPERIMENTS HSE UNIT PH DSO EDMS No
Eric Thomas - Safety systems for LHC experiments 1 Safety Systems for LHC experiments Baseline specifications – Additional needs – Actions taken.
Safety systems (AL3) and systems relevant to Safety Steve Hutchins with thanks to: Karl Gunnar Lindell, Rui Nunes, Silvia Grau, Henrik Nissen, Patrice.
ST/MAforLHC April 2003Sixth ST workshop1 Summary of ST/MA deliverables for LHC Luigi Scibile for the ST/MA group.
05 Novembre 2003Chamonix XIV Workshop, January How to deal with leaks in the QRL and magnet insulation vacuum Paul Cruikshank for AT/VAC Germana.
Review of the operation scenarios and required manning of the activities P. Schnizer and L. Serio.
1st LTEX 22 June 2009D.LACARRERE1 Protection of UX85 EDMS No IP8 Current Status & Plans  UX85 Expt Area  RB84 (8-7 sector)  RB86 (8-1 sector)
7/23/ J.Coupard. 1) Cryogenic risks 2) Cryogenic phases from RT/floating to nominal and additional safety rules A. Sectors warmed-up to RT or considered.
Access system M. Gruwé (AB/OP) Thanks to TS/ASE group Extended LTC meeting March 3 rd 2008.
EN-CV interventions during YETS
Task Force on Safety of Personnel in LHC underground areas following the sector 34 accident of 19-Sep-2008 Status report LPC 07/05/2009 B. Delille, S.
The HiLumi LHC Design Study is included in the High Luminosity LHC project and is partly funded by the European Commission within the Framework Programme.
For more info:
Review of Safety Systems for the LHC Experiments & Experimental Areas Emmanuel Tsesmelis / TS-LEA LEMIC 20 March 2007.
The new approach to the CERN Safety Policy and Safety Organisation A. Goehring-Crinon & R. Trant.
PH Department in context Safety Officers in PH Department
Consolidation and Upgrade plans for the LHC Vacuum System
Review of the operation scenarios and required manning of the activities P. Schnizer and L. Serio.
Johan Bremer, 22th-26th September 2008 Cryogenics Operations 2008, CERN, Geneva, Switzerland 1 CRYOGENICS OPERATIONS 2008 Organized by CERN Safety aspects.
Long shutdown 1 LHC Machine Status Report K. Foraz June 12 th, 2013.
Hardware Commissioning  Preparation Documentation MTF Programme  Status The Review The commissioning activity in Resources  Outlook The new.
LHC Performance Workshop Chamonix 2009 Ralf Trant Laurette Ponce Summary of Session 02 Safety.
Eric Prebys/LARP 2/17/2016.  CERN has taken unprecedented steps to control information about this event, including altering the electronic LHC log to.
LHC Injectors Upgrade Project 1/12/2010 R. Garoby.
Work Organisation for Splice Consolidation Francesco Bertinelli 20 minutes presentation, 10 minutes discussion: 12 slides First LHC Splice Review, CERN,
Safety in LS1 Thomas Otto, TE DSO.
SAFETY SERVICES PROVISION I. Bejar Alonso. Transfer Executive Safety Tasks from SC to Departments In application of the document “Safety policy at CERN”
Conclusions on UPS powering test and procedure I. Romera Acknowledgements: V. Chareyre, M. Zerlauth 86 th MPP meeting –
TE-CRG Activities D. Delikaris, TE-CRG.
Service Agreements Emmanuel Tsesmelis CERN / TS-LEA RRB Scrutiny Group 31 August 2006.
Duy Phan, EN-STI-RBS. Description of the hazards  An Oxygen Deficiency Hazard (ODH) exists when the concentration of O2 ≤ 19.5 % (by volume)  Cold burns.
ESS Cryomodule Status Meeting – Elements of Safety | | Christine Darve Elements of Safety Applicable to the ESS 2013 January, 9 th Christine.
LHC experience with installation Katy Foraz March 6th 2008, Dubna GDE Meeting - ILC Conventional Facilities and Siting Workshop ***********************************
First Outcome of the Task Force on Safety of Personnel in LHC underground areas following the sector 34 accident of 19-Sep-2008 R. Trant on behalf of the.
Equipment simplified model SMR UR safety
HEL – Safety aspects Christelle Gaignant
HSE rules & regulations
Helium spill in LHC tunnel
LHC-TS3 Coordination meeting #3
Safety rules for works supervisors
Keeping LHC cold during LS periods Preliminary proposal
Hollow e- lens, Cryogenic aspects
Cryogenic Risk Assessment in LHC
Agenda Contents Different types of documents
Assumption for a given sector
ESHAC #8 Safety Readiness Review Thomas Hansson, ESH
Powering and Safety day Underground access during powering tests
Review of hardware commissioning
Presentation transcript:

Task Force on Safety of Personnel in LHC underground areas following the accident in sector 3-4 on Ghislain Roy, on behalf of the Task Force 2 february 2009Chamonix 2009

BETWEEN THE ACCIDENT AND TODAY… 2 february 2009Chamonix 20092

Immediate measures  Repowering of sectors took place one month after accident  Access conitions defined in the repowering procedure  Access forbidden even at very low current  Access to neighbouring areas forbidden (buffer zones)  Some restrictions to occupancy in SX buildings 2 february 2009Chamonix 20093

Measures for shutdown WG to define the working and transport conditions in the LHC tunnel during 08/09 shutdown based on risks of cryogenic nature. 1. Nominal conditions LHe, 1.9K, p<18bar, operational 2. LHe storageLHe, 3-5K, p<18bar 3. PIM coolingGHe, K, p<18bar 4. FloatingGHe, K, Patm 5. Warm 300K, Patm 2 february 2009Chamonix 20094

Specific cases  First active warm-up / cool-down of sector kNo access – No work  From second active warm-up / cool-down Restricted access mode Announce accesses and activities to CCC  Passive warm-up of whole sector Access allowed  Warm-up of standalone magnets and QRL K No access – No work 2 february 2009Chamonix 20095

TASK FORCE… 2 february 2009Chamonix 20096

Mandate  Establish the sequence of facts related to safety of personnel, based on e.g. AL3 data and FB emergency intervention records.  Analyse the LHC underground environment with respect to Safety of personnel and explain the development of the environment, in relation with original risk analyses (incl. tests) performed.  Recommend preventive and corrective measures for the Safety of Personnel in the LHC underground 2 february 20097Chamonix 2009

Membership  Safety and cryogenic experts;  Participants proposed by Departments  Safety Commission: R. Trant (Chair), B. Delille, C. Vollinger (scientific secretary)  Beams Dep. : G. Roy  Technology Dep. : L. Tavian  Physics Dep. : E. Thomas  Safety Commission :G. Lindell  Engineering Dep. : J. Inigo-Golfin 2 february 20098Chamonix 2009

Communication  Reporting to the Directorate  Informing  Department Heads concerned (BE, EN, TE, PH)  Relevant committees (SAPOCO / BFSP)  Sensitive information will be gathered, exchanged and interpreted by the TF :  Confidentiality – No Minutes  Working documents available on restricted EDMS site 2 february 20099Chamonix 2009

Organisation  Official mandate received 1 st week January 2009;  First meeting 21 st January 2009;  Two meetings per week (including this week)  Aim at concluding within 30 working days;  Preliminary conclusions to be presented to an external advisory committee of safety experts (e.g. from BNL, DESY, FNL, JFL). 2 february Chamonix 2009

Meeting agenda DateTopics 21 JanuaryIntroduction, mandate, organisation 23 JanuaryPresentation: R. Trant ; Brainstorming 28 JanuaryPresentations: R. Nunes, J. Inigo-Golfin, L. Tavian TF-recommendation to DN200 positioning 30 JanuaryPresentations: Ph. Lebrun, M. Chorowsky 2 FebruaryPresentation: B. Delille Discussion: R. Schmidt / J. Wenninger Summary of intermediate results: C. Vollinger 6 FebruaryPresentation: P. Bossus Till end FebruarySix more meetings 2 february Chamonix 2009

→ Recommendations Preventive and Corrective Measures :  Rules and procedures applicable  Eg. Accessibility of different areas in different operational conditions…  Modifications of systems and infrastructure  Ventilation doors ?  Resync ventilation and access sectorisation ?  Interlocks on powering ?...  New systems and infrastructure  « blast doors » ?... 2 february Chamonix 2009

Constraints  Powering tests access constraints  Must be known ASAP for shutdown planning  Long Shut Down works constraints  What can be done during this shutdown ?  What will be the ground rules for shutdowns ? eg emptying helium for sectors where transport activities take place… 2 february Chamonix 2009

FIRST QUESTIONS AND THOUGHTS… 2 february 2009Chamonix

Safety of personnel… Present within the installations :  Workers (staff, users, contractors) ( visitors ? )  Intervention teams (fire brigade… ) Assume no impact on Public or Environment Envelope scenario already included in Safety Reports (RPS, PUI) sent to FR and CH Safety authorities… 2 february Chamonix 2009

… underground areas… Tunnel areas  Arcs and straight sections  Cryomagnets and good fraction of cryogenic lines and installations Service areas  « Accesible while powering in tunnel areas »  Separate ventilation  Numerous installations and services, including cryogenics… Non-interlocked areas  Experimental areas (USA15, USC55, UX85, PX24) + PM32  Separate ventilation Each case is specific… scale/translate S34… 2 february Chamonix 2009

… following accident… As a consequence of accident  Fact finding on this accident  « What if » scenarios As a consequence of the consolidation decided in response to the accident  additional DN200 pressure relief valves.  any other measure (procedural or technical) taken as a consequence of the initial accident and which could modify the environment… 2 february Chamonix 2009

… accident of Taking into account the redefined MCI… … and any other scenario (fixed point, beam…) Scope limited to cryogenic accidents with release of cryofluids, caused by any source. 2 february Chamonix 2009

Four factors… 1. Oxygen Deficiency 2. Ambient and air temperature 3. Pressure wave 4. Noise from flushing 2 february Chamonix 2009

…and their effects What would have happened to a person in the LHC underground during the accident ?  In the D area ? ODH, T, blast, noise  In the S34 tunnel ? ODH front speed, shock wave, T  At P3 or at P4 ?  In a neighbouring sector ?  In caverns, at access points, at the surface, … ?? 2 february 2009Chamonix

Translate the accident What could have happened to e.g. Atlas with the same accident on the inner triplets ? Does this modify or supplement previous answers? Ditto for CMS ? Alice ? LHCb ? Bottom of TI2, TI8 ? Any other relevant locations? 2 february 2009Chamonix

« Equivalent scenarios » Brainstorm to find other possible (plausible) causes for loss of He containment:  Electrical origin ? : see 19 Sept  Beam loss ?  Tunnel collapse ?  Ceiling / wall / floor collapse due to water pressure, earthquake, unknown “caverns”  Any other mechanical origin ?  transport activities  break of fixed point  Fire provoking loss of He containment ?  Refer to studies done by Fabio  Chemical origin : any “good idea”… UPS batteries ?  Others 2 february 2009Chamonix

Risk assessments By subsystem:  electrical, cryogenics, magnets, … Possible interactions between subsystems  electrical failure scenario → cryo. failure scenario Transient modes:  magnetic forces, EMC, … 2 february 2009Chamonix

Risk analysis  Gathering data for a global LHC risk assessment…  Management risk assessment needed ?  What impact is accepted on machine ?  What impact is accepted on personnel ?  What impact is accepted on operability ? 2 february 2009Chamonix

Interim conclusion We still have more questions than answers… Work has started in gathering all info necessary to come to meaningful conclusions. This week is your chance to give us your input, express concerns and refine with us the boundary conditions… 2 february Chamonix 2009