TMP Development Module 7. What is a TMP? Set of coordinated transportation management strategies applied to manage work zone impacts of the project Scaleable.

Slides:



Advertisements
Similar presentations
Work Zone Impact Strategies Module 6. TMP Overview3 Identification of TMP Strategies Should be based on: type of work zone traffic conditions anticipated.
Advertisements

Project Description and Needs Lincoln Way Widening Addition of a center-turn lane and safety improvements to the grade and horizontal alignment. Needs.
Gerald L. Ullman, Ph.D., P.E. Texas Transportation Institute Designing and Maintaining a Pedestrian-Friendly Work Zone.
ODOT’s Public Involvement Process PI and the Project Development Process Minimum PI Requirements.
Overview What is the National ITS Architecture? User Services
Louisiana Safe Routes To School Program
FHWA Work Zone Program Federal Highway Administration Office of Safety Integration Washington, DC July 22, 2008.
Created by: Victor Lund, PEKen Johnson, PE, PTOE St. Louis CountyMnDOT.
TDOT’s WORK ZONE SAFETY AND MOBILITY MANUAL Use & Implementation of Transportation Management Plan AASHTO Subcommittee on Design Dyan C. Damron, P.E. –
Traffic Control Plan Development Course
November, 2008 Montana Department of Transportation Transportation Management Plans.
LANE CLOSURE CHARTS CHART DEVELOPMENT AND DELAY DAMAGES (District 3) OBJECTIVE To become familiar with the lane closure chart development process.
HERO UNIT Training Module Work Zone Traffic Control And Incident Management Operations.
Work Zone Safety It Starts With YOU!!. 2 BOOK 7 What is NEW??? IMSA TECHNICAL EXPO October, 2014 Dave Edwards.
Lecture(3) Instructor : Dr. Abed Al-Majed Nassar
Transportation Management Plan Overview. TMP Overview2 Is that the impression people have?
Safe, Accountable, Flexible, Efficient Transportation Equity Act: A Legacy for Users SAFETEA-LU Key Safety Provisions Federal Highway Administration.
Transportation Management Plan Overview Module 3.
MAINTENANCE & TRAFFIC OPERATION INCIDENT MANAGEMENT.
Final Rule on Temporary Traffic Control Devices 23 CFR 630 Subpart K Chung Eng, Office of Transportation Operations National WZ Safety Clearinghouse Webinar.
Work Zone Safety Awareness. What is a Work Zone?  Work Zone is a term applied specifically to highway and road construction sites involving federal government.
Old Policy – which no one ever seem to have heard of.
Commissioning of Fire Protection and Life Safety Systems Presented by: Charles Kilfoil Bechtel National Waste Treatment Plant Richland WA.
From Planning to Pouring: The Evolution of Safe Routes to School Julie Walcoff, Ohio DOT, Columbus, OH Alex Smith, Columbus Public Health, Columbus, OH.
Wisconsin Contractor-Engineer Conference January 22, 2009 Safety Apparel, FHWA Work Zone Safety Subpart K Rule & Permanent Concrete Barriers Bill Bremer,
1-1 Roles and Responsibilities. 1-2 Module Objectives  Recognize the roles of LEOs and others in work zones  List LEO responsibilities and expectations.
MODULE 2 ROLES AND PROCEDURES
TMP Evaluation and Performance Module 9. Assessing TMP Performance2 Module Outline Why Assess TMP Performance? Performance Assessment – Project and Program.
VIRGINIA’S IMPLEMENTATION of the FINAL RULE on WORK ZONE SAFETY and MOBILITY Virginia Department of Transportation’s Instructional and Informational Memorandum-LD-241.
Overview of the Work Zone Safety and Mobility Rule Module 1.
HIGHWAY/UTILITY PROGRAM OVERVIEW ROADWAY CONFERENCE APRIL 20, 2009.
1 Federal Highway Administration, USDOT Implementing the Rule on Work Zone Safety and Mobility.
Transportation Management Plan Overview. TMP Overview2 Is that the impression people have?
WORK ZONE SAFETY & MOBILITY Meeting the Federal Rule Jim Allen Safety Implementation Engineer ATSSA Illinois Chapter Meeting.
Rule on Work Zone Safety and Mobility SHA’s Road to Compliance Maryland State Highway Administration Office of Traffic and Safety Talking OperationsJawad.
C ONSIDERING L ARGE T RUCKS IN THE D EVELOPMENT OF T RAFFIC M ANAGEMENT P LANS Neil Boudreau, MassDOT State Traffic Engineer April 13, 2015.
Presentation Topics Oregon Transportation Investment Acts (OTIA) Goals of Statewide Traffic Mobility Program Focus of ODOT’s Mobility Approaches Results.
Office of Traffic, Safety and Technology Module 4 Work Zone Applications Traffic Control Plan Development Course.
1 Some Findings on Public Outreach for Work Zones.
Managing Travel for Planned Special Events: What, Why, & Benefits Walt Dunn, P.E. Dunn Engineering Associates, P.C. Talking Operations Seminar January.
Office of Traffic, Safety and Technology Module 5 Work Zone Plan Sets Module 5 Work Zone Plan Sets Traffic Control Plan Development Course.
Making Work Zones Work Better Chung Eng Work Zone Mobility & Safety Team Office of Transportation Operations Federal Highway Administration US Department.
Work Zone Rule Virtual Workshop – Rule State of the Practice Overview.
MATOC Trial Phase Dec 2008 to Jun 2009 Presentation to the Transportation Planning Board Richard W. Steeg, PE Chair MATOC Steering Committee VDOT Regional.
1 Federal Highway Administration, USDOT The Final Rule on Work Zone Safety and Mobility Updates to 23 CFR Section 630, Subpart J Presented by Tracy Scriba,
Planning for Travel and Transportation Management National Training Center Course # Unit Three Land Use Decisions.
The Fargo/Moorhead Area Interstate Operations Study Opportunities and Planned Activities Presentation for the Mn/DOT Travel Demand Modeling Coordinating.
New Development and Significant Development 12/21/20151 New Development & Significant Redevelopment.
1 Implementation of Transportation Management Plans (TMPs) Presented by Tracy Scriba Federal Highway Administration AASHTO Design Meeting July 15, 2008.
General Tab Project, Cost Schedule, and Work Limits Roadway Character
Safe, Accountable, Flexible, Efficient Transportation Equity Act: A Legacy for Users Advancing Safety through SAFETEA-LU Michael Halladay FHWA Office of.
Improving Communication and Coordination in Highway Work Zones Kimberly Peters Incident Management Program Director, INDOT Event Date.
Construction zones and traffic control Objective Review extent of problem Identify contractor responsibilites Identify control plan components.
Preparation Plan. Objectives Describe the role and importance of a preparation plan. Describe the key contents of a preparation plan. Identify and discuss.
Work Zone Safety Guidelines For Maintenance, Construction and Traffic Personnel.
Maricopa Association of Governments (MAG) February 5, 2003.
PRE-PLANNING FOR CONSTRUCTION PROJECTS. OVERVIEW ASSESSING OWNER CAPABILITIES ANALYSIS OF RESOURCES REGULATORY REQUIREMENTS SITE DEVELOPMENT REVIEWING.
Secondary & Cumulative Effects Analysis Training Program Module 1: How to Determine Which Resources Should be Considered in a SCEA How to identify what.
Maintenance and Temporary Traffic Control
2009 Manual on Uniform Traffic Control Devices
Traffic Control Plan Development Course
General Tab Project, Cost Schedule, and Work Limits Roadway Character
Module 6: Deep Dive Work Zone TSMO
Kathy Harvey, P.E. State Design Engineer Missouri DOT
General Tab Project, Cost Schedule, and Work Limits Roadway Character
HERO UNIT Training Module
Traffic Control Plan A plan directed to the safe and expeditious movement of traffic through construction and to the safety of the work force performing.
Module 6: Deep Dive Work Zone TSMO
WisTMP 2.0 Update Andy Heidtke, PE Statewide Work Zone Design Engineer
HSE Requirements for Pipeline Operations GROUP HSE GROUPE (CR-GR-HSE-414) EXECUTIVE SUMMARY This rule defines the minimum HSE requirements related to the.
Presentation transcript:

TMP Development Module 7

What is a TMP? Set of coordinated transportation management strategies applied to manage work zone impacts of the project Scaleable – projects with larger anticipated impacts may require more strategies Required in all FA projects – TMP=TCP in some projects TMP=TCP+TO+PI components in others

TMP Development Process

TMP Development, Implementation, and Assessment 11 Step Process 1. Compile Project Material 2. Determine TMP Needs 3. Identify Stakeholders 4. Develop TMP 5. Update/Revise TMP 6. Finalize Construction Phasing/Staging and TMP

TMP Development, Implementation, and Assessment 11 Step Process (continued) 7. Re-evaluate/Revise TMP 8. Implement TMP 9. TMP Monitoring 10. Update/Revise TMP Based on Monitoring 11. Post-Project TMP Evaluation

TMP Team Approach Better coordination throughout the process from development to implementation Involve all involved offices internally  TMP Coordinator  Planning  Design  Traffic engineering  Construction  Operations (maintenance)?

Step 1 - Compile Project Material Staff responsible for each stage of the project (planning, preliminary engineering, design, construction) begins by compiling available project materials such as: Project definition Construction phasing/staging alternates Preliminary work zone management strategies. Preliminary cost estimates for strategy implementation Information from other projects in the corridor to evaluate the combined or cumulative impact of the projects.

Step 2 - Determine TMP Needs Necessary Components of TMP  Impact assessment  Duration of project  Possible Strategies Determine if it is a significant project: Based upon the agency's policy and procedures, project's anticipated work zone impacts.

Step 2a - Basic TMP Basic TMPs –  Applied on construction or maintenance projects with minimal anticipated impacts  Projects typically only involve the development of a TCP – layout of devices, phases, etc.

Step 2b - Intermediate TMP Intermediate TMPs – Used for construction or maintenance projects that are anticipated to have more than minimal disruption, but have not been identified as significant projects. Include more detailed work zone impacts analysis and management strategy information than Basic TMPs, including some element of PI and/or TO strategies as well as TCP.

Step 2c - Major TMP - Significant Projects Major TMPs are intended for significant projects. Major impacts to road users, residents and businesses TMPs for significant projects shall consist of a TCP, and also address PI and TO components. In addition to the TMP components required by the Rule, TMPs may also contain cost estimates, coordination strategies between stakeholders, secondary mitigation strategy(s), analysis of potential impacts on detour routes, and analysis of the potential effects of the management strategies.

Step 3 – Identify Stakeholders Internal and external that can provide valuable input to the agency on what strategies to include in the TMP to help manage the work zone impacts of a project. TMP DOT Road Users Local Government Property Owners Emergency Responders Federal Agencies Contractor

Step 4 – Develop TMP The level of detail of the TMP during early planning is largely dependent upon the type of planning activity, the expected impacts of the project, and the availability of data. At a minimum, early planning should entail a qualitative exercise to list the potential impacts of a project, along with a list of potential management strategies, and the expected costs of those management strategies.

Step 5 – Update/Revise TMP The TMP is updated or revised as the project progresses through its various developmental stages as more project-specific information becomes available.

Step 6 – Finalize Construction Phasing/Staging and TMP PS&Es shall include either all the applicable elements of a TMP, or the provisions for a contractor to develop a TMP. TMP development should begin prior to project letting, even for design-build projects. Some elements could be accomplished early in process – alternate route work or beginning of PI plan Some may not be in PS&E – agency in house

Step 7 – Re-evaluate/Revise TMP If alternative construction phasing/staging plans or other management strategies have been suggested, technical specialists from the contractor or agency need to review the TMP to see if changes are needed.

Step 8 – Implement TMP The TMP is implemented. In some cases, components of the TMP may need to be implemented prior to construction (e.g., public relations campaign, improvements to detour routes, etc.).

Step 9 – TMP Monitoring Monitor operational performance of work zone during the construction phase  Are predicted impacts realistic?  Are the strategies in the TMP effective in managing the impacts?  Do any adjustments to TMP need to be initiated?

Step 10 – Update/Revise TMP Based on Monitoring If performance requirements are not met, the agency and/or contractor should revisit the TMP and consider alternate management strategies and/or phasing/staging approach(es) that meet the approval of the agency.

Step 11 – Post-Project TMP Evaluation TMP performance assessment can aid in addressing the following concerns: Which management strategies have proven to be either more or less effective in improving the safety and mobility of work zones? Are there combinations of strategies that seem to work well? Should TMP policies, processes, procedures, standards, and/or costs be adjusted based on what has been observed or measured? Are the best decisions in planning, designing, implementing, monitoring, and assessing work zones being made? Performance assessment may involve two tracks: 1) the overall TMP process 2) actual field performance of the work zone and TMP.

TMP PROCESS –CA Example Conceptual Planning and Design Request TMP Data Sheet What Kind of TMP is required? Establish TMP Team (Ops, Design, Traffic, Const, CHP) START MAJOR Prepare Data Sheet Arrange for Funding of TMP Strategies Detailed Plans & Specs (inc.TMP) Modify Strategies as Needed Start early TMP elements Begin Construction Implement TMP Minor Maintenance and Permits activities Blanket ** Modify TMP Strategies as Needed / Monitor traffic initially / Provide Lessons Learned

Ohio DOT’s TMP Development Process Start Project MOTAA MOT Policy Exception Requests Stage 1 Design Construct Project

Developing the TMP (Putting the components together) Traffic Control Plan  Layout of traffic control devices to guide road users through or around work zone.  Determined after analysis of strategies  Contain any restrictions on work hours  Include Work Zone Speed Limits – State policy ?

TYPICAL TRAFFIC CONTROL PLANS CONTENTS : LANES WIDTHS WORK AREA & DIMENSIONS CONSTRUCTION SEQUENCE SCHEDULE, STAGES & ACTIVITIES /STAGE ADJACENT HAZARDS TEMPORARY DRAINAGE TYPE OF AREA (CBD, RURAL, URBAN) GEOMETRICS LOCAL ORDINANCES SPECIAL PROVISIONS PAY ITEMS

TYPICAL TRAFFIC CONTROL PLANS CONTENTS : LOCATION/TYPES OF TC DEVICES SIGNS, BARRIERS, PAVEMENT MARKINGS, ARROW BOARDS, CMS, ETC… EMERGENCY ACCESS PEDS./BYCLIST ACCESS EQUIPMENT, WORKERS ACCESS CROSSOVERS/EMERGENCY OPENINGS EXISTING REGULATORY SPEED LIMIT/OTHER SIGNS TRAFFIC CONTROL NOTES LIGHTING/GLARE SCREEN GEOMETRICS LOCAL BUSINESS/RESIDENT ACCESS DETOURS, IF APPLICALIBE

PEDESTRIAN/BICYCLISTS Situations That Warrant Special Considerations: Sidewalks Traverse Work Zone Designated School Route Significant Pedestrian/Bicyclist Activity ADA compliance Existing Generators (Parks, Schools, Shops)

Additional TMP Components for Significant Project Transportation Operations Plan  Improvements to alternate route Traffic Signal retiming Intersection geometric improvements  Utilize existing infrastructure – detectors, cameras, TMC

Traffic Operations Plan  Incident management plan for work zone Pre-stationed tow operators during peak hours  Motorist Assist Patrols Utilize existing with added units Contract during project  Demand reduction strategies Carpools Increase transit ridership  ITS real time traffic information systems

Other Considerations Existing state policies  Work zone speed limits Reduced at all times? Reduced when workers present and exposed? Use of Law Enforcement?  Use of Positive Protection – PCB or other 23 CFR 630 Subpart K

MUTCD Sec 6C.01 “Reduced speed limits should be used only in the specific portion of the TTC zone where conditions or restrictive features are present…A TTC plan should be designed so that vehicles can reasonably safely travel through the TTC zone with a speed limit reduction of no more than 10 mph.”

Increase in Fatal Plus Injury Accident Rates From Before to During Construction Speed Limit Reduction (mph) Percentage Increase (%) Rural - traveled way & detours

Increase in Speed Variance from Upstream to Work Zone Speed Limit Reduction (mph) Percentage Increase (%)

Minimizing Variance Safest traffic operations result when speed variance is minimized Only police enforcement is effective in reducing speeds without increasing speed variance

Stationary Police Vehicle on Approach

Enforcement Enforcement Impact on Vehicle Speeds Enforcement Policies Problems Work Zone Training for Police Policies on Work Zone Speed Limits

Observed Problems  Difficult to ticket speeders in work zones  Officers have little guidance on when or where to deploy  Lack of ticketing  Officers are stationed in unsafe positions

Observed Problems (cont.)  State laws affect enforcement options  TTC plans are not designed for enforcement  Officers are in short supply

Do not allow this…

Reduction in Mean Speeds Between Upstream and Work Locations Speed Limit Reduction (mph) Reduction in Mean Speed (mph)

Comparison of Speed Variance Between Upstream and Work Locations Speed Limit Reduction (mph) Increase in Speed Variance (mph)

Incident Management Plan Ensure access to all areas for emergency vehicles  Hospitals nearby?  Trauma centers? Plan to provide access within work site  Identify alternate routes  Pre-sign for use during incidents? Pre-station tow operators during peak hours

Business Access Temporary entrances  Signing  Pavement Advance notification of phase changes  Keep owners informed Work Schedules  Christmas shopping season  Weekends

Residential Access Keep residents informed as project begins and progresses  Maintain access if possible  Neighborhood association meetings, newletters, mailings, etc.

Additional TMP Components Public Information  Strategies to inform public of work zone conditions Website Real time traffic information system Community outreach – residents and businesses Twitter TV – Radio – commuters  Occasionally contracted out to PR firm for major campaign

Billboards on Project Project logo Progress

NHI A THE STEVENSON RECONSTRUCTION Brochures for Media Kits and Public Distribute early – may influence alternate route choice

Example Checklist FHWA Guide

Example Checklist DDOT

Example Checklist DDOT Guide

TMP Overview53 Summary Estimate and budget for TMP development and implementation early in project development (update as appropriate throughout project) Consider and address WZ impacts from a broad transportation management perspective (rather than solely a traffic control perspective) Coordinate with key parties to jointly identify WZ impacts issues to account for and management strategies to address them Strive to use strategies that keep lanes open, especially during peak traffic times

TMP Overview54 Summary (cont.) Consider using extended closures or full closures versus numerous night closures Consider strategies that facilitate decision-making by the public to avoid the WZ (e.g., public awareness, advance signage in locations prior to key motorist decision points) Training is important for all personnel involved in TMPs Management support is needed for effective TMP efforts

Questions ?