Stakeholder Information Update Edmonton-Calgary 500 kV Transmission Development December 14, 2005 Introduction Neil Millar, vice-president, Transmission.

Slides:



Advertisements
Similar presentations
CE Electric UK – Potential developments in long-term charging arrangements and IDNO charging methodologies 1 April 9, 2008 Potential developments in long-term.
Advertisements

Sacramento Local Agency Formation Commission (LAFCo) ANALYSIS OF PROPOSED SMUD SPHERE OF INFLUENCE AND ANNEXATION Presented by Chris Tooker Friday, October.
Mountain States Transmission Intertie (MSTI) Open Season Update Meeting Mountain States Transmission Intertie (MSTI) Open Season Update Meeting Tuesday,
Electricity planning and approval in Alberta Laura Bowman staff lawyer Environmental Law Centre January 7, 2010 Bill 50.
ISO Rules 9.1 Transmission Facility Projects Industry Workgroup Meeting January 16, 2013.
TERRACE TO KITIMAT TRANSMISSION PROJECT UPDATE Feb/March 2015.
THE POWER OF POSSIBILITY Electric Transmission System Development in Alberta Neil J. Brausen, P. Eng., Director System Planning APEGGA Calgary Branch Luncheon.
MARCH 31, 2014 Maine 2014 Outage Coordination CONTAINS CRITICAL ENERGY INFRASTRUCTURE INFORMATION – DO NOT RELEASE.
Customer Meeting April 28, 2010 Torrington, WY. Agenda Introductions Accomplishments Update on Torrington Area PVVC Overview PVVC Schedule and Cost Estimates.
State Milestones Subsidized Insurance Workgroup High Level Timeline 2011 Jan 2011 Feb 2011 Mar 2011 Apr 2011 May 2011 Jun 2011 Jul 2011 Aug 2011 Sept 2011.
NOVEMBER 11, 2014 PUBLIC VERSION Maine 2014 Outage Coordination CONTAINS CRITICAL ENERGY INFRASTRUCTURE INFORMATION – DO NOT RELEASE.
AUGUST 19, 2014 PUBLIC VERSION Maine 2014 Outage Coordination CONTAINS CRITICAL ENERGY INFRASTRUCTURE INFORMATION – DO NOT RELEASE.
Stakeholder Information Update Edmonton-Calgary 500 kV Transmission Development September 29, 2005 Introduction Neil Millar, vice-president, Transmission.
©2011 Pacific Gas and Electric Company. All rights reserved. SmartMeter TM Steering Committee Update – April/May 2012.
Guidelines for RTF Measure Economics Estimation Methods (formerly Cost and Non-Energy Benefits Guidelines) Progress Update to the Regional Technical Forum.
Northern California to Pacific Northwest/Canada Transmission Line Steve Metague, PG&E February 29, 2008.
Wyoming Infrastructure Authority Developing Electric Infrastructure for the Future of the West Energy Gateway Update Presented by Darrell T. Gerrard Vice.
2006 Reliability Study Scope Name Date. DRAFT 2 Purpose of Study Assess the PEC and Duke transmission systems’ reliability Develop a single reliability.
1 NSTAR TRANSMISSION RELIABILITY PROJECT ENVIRONMENTAL BUSINESS COUNCIL UPDATE APRIL 21, 2005.
Capital Improvement Program. During the Annual Strategic Action Plan (SAP) evaluation, long-term needs and priorities are identified by City Council Capital.
Reliable Power Reliable Markets Reliable People Performance Targets for the Customer Interconnection Process January, 2008.
1 Transmission Line Projects in Maryland – an Overview Sandra S. Patty PPRP - Manager, Transmission Projects PPRAC Meeting Country Inn & Suites, Annapolis,
Sacramento Local Agency Formation Commission (LAFCo) UPDATE ON PROPOSED SMUD ANNEXATION Presented to Yolo LAFCo September 19, 2005.
Brio Rapid Transit System Update on Stations and Timetables July 10, 2012.
Planning and Community Development Department Housing Element City Council February 03, 2014.
Discussion of Market Participant Choice for Transmission Connections Stakeholder Session October 14, 2011.
Base Plan Development Overview 2007 Transmission Summit July 31, 2007 New Orleans, Louisiana.
A Strawman for Discussion by Dottie Stockstill & Greg Ramon Special ERCOT Board Meeting June 24, 2003.
Renewables Integration Development Project North West of the Island of Ireland Louis Fisher, EirGrid.
Three Rivers Levee Improvement Authority June 8, 2007 Presentation to the State Reclamation Board Proposed Feather River Setback Levee.
Icfi.com © 2006 ICF International. All rights reserved. Wyoming Collector and Transmission System Project – Status Report Presented to: Wyoming Infrastructure.
Serving the people of Cumbria Do not use fonts other than Arial for your presentations Commissioning, Procurement & Contract Management Staff Engagement.
METROPOLITAN TRANSPORTATION COMMISSION Key Steps to Delivering Project 1.Lead agency submits final project scope, budget and schedule to MTC 2.MTC.
ATC Planning Zone Meeting Teresa Mogensen Director, Transmission Planning & Service Scott Barnhart Manager, Transmission Planning.
Current Export Initiatives Jerry Mossing Exports Workshop February, 16,2006, Metropolitan Center, Calgary.
R E T I Coordinating Committee California’s Renewable Energy Transmission Initiative: Status Update California Public Utilities Commission California Energy.
Texas Department of Transportation Corpus Christi District Harbor Bridge Project U.S. 181 (Harbor Bridge)/SH 286 (Crosstown Expressway) Citizens Advisory.
Phase I Engineering and Environmental Studies Project Development Flowchart US Route 45; IL Route 132 to IL Route 173 and Millburn Bypass CSS
Exit Capacity Substitution and Revision Transmission Workstream meeting, 3 rd December 2009.
Millbrook Dam Environmental Assessment Study Dan Marinigh CAO/Secretary-Treasurer Otonabee Region Conservation Authority October 20, 2015 Otonabee Conservation.
1 Sunrise Powerlink Project Update Orange County Business Council March 10, 2009.
Reliable Power Reliable Markets Reliable People Hanna Region Transmission Development Ramaiah Divi, P.Eng Manager, Central System Planning.
Yellowhead Area Transmission System Development
The SaTH Foundation Trust Programme Deborah Shaw March 29th 2007.
OCTOBER 2, 2013 Maine 2013 Outage Coordination Redacted Copy.
©2011 Pacific Gas and Electric Company. All rights reserved. SmartMeter TM Steering Committee Update – December 2012.
The Kern Regional Transportation Plan A Vision and Guidebook for Kern County in 2025.
Middle Fork Project Relicensing Process Plan April 25, 2006.
Community Based Adult Services (CBAS) Program Stakeholder Update Toby Douglas, Director California Department of Health Care Services (DHCS) December 12,
Transition Plan Network Operations Model Change Requests 5/26/2010.
2006 Reliability Study James Manning Bryan Guy May 12, 2006.
Planning Commission Study Session: Preferred Plan July 23, 2015.
PAC Meeting July 2, Agenda  Introductions and thanks  Project to date  Next steps  Questions.
Innovation, Science and Economic Development Canada (ISED) 600 MHz Repurposing RABC 600 MHz Working Group Meeting Innovation, Science and Economic Development.
Localisation of Council Tax Support. Council Tax Support Purpose of the Report  Remind members of the background to the national abolition of Council.
Status of the Planning Working Group’s (PWG) Efforts
The Oakton Condominium Association September 12, 2017
Impact Fee Advisory Committee November 10, 2016
August LNBA Agenda Time Topic 1:00 – 1:15
Springbrook Estates Sewer Improvement Area Informational Meeting
Lafayette New Terminal Program Update
BUSINESS OWNER MEETING
2040 Long Range Transportation Plan Update
Lafayette New Terminal Program Update
Exit Capacity Substitution and Revision
Strategic Planning Timeline Overview
Second Independent Evaluation of UNAIDS
Western Orbital: M11 J11 Park and Ride Provision
XRN 4927 – MiR Drop 4 - Status Update
Presentation transcript:

Stakeholder Information Update Edmonton-Calgary 500 kV Transmission Development December 14, 2005 Introduction Neil Millar, vice-president, Transmission - AESO

Today’s Meeting - Purpose Provide stakeholders with a review of project status and milestones Provide end-of-project cost estimates Provide an update on South KEG conversion costs and engineering considerations Provide an update on Genesee-Langdon line siting and landowner consultation

Agenda Introduction and context (Neil Millar, AESO) Overview of project status (Fred Ritter, AESO) Cost estimate update (Stephen Kane, AltaLink) S-KEG engineering considerations (Fred Ritter, AESO) Landowner consultation update (Dennis Walters, AltaLink) Questions

Edmonton–Calgary Reinforcement Key Elements S-KEG lines conversion to 500 kV (Keephills-Genesee-Ellerslie) New 500 kV line (Genesee to Langdon) Benefits Necessary to reliably serve Alberta (Red Deer & south) Remove barriers to new generation Significant line loss savings

Progress To Date AESO filed Need Identification document in May 2004 with EUB EUB hearing in December 2004, closing in January 2005 EUB Approval of Need received in April 2005 Transformer amendment filed by AESO October 13, 2005 AltaLink and EPCOR proposal to provide service (PPS) documents for the South KEG conversion received by the AESO in November 2005

Stakeholder Information Update Edmonton-Calgary 500 kV Transmission Development December 14, 2005 Overall Project Status Fred Ritter, director, Engineering - AESO

South-KEG 500 kV Conversion EPCOR & AltaLink have provided proposals for service & estimates for their respective portions AESO is reviewing the proposals & engineering considerations AESO expects to direct AltaLink and EPCOR to file facilities applications in January 2006 Continue work with EPCOR Generation on conversion sequence

South KEG Conversion – Schedule AESO Need Approved by EUB April/05 AltaLink begins landowner consultation July/05 AESO files transformer amendment Oct/05 Functional specification complete Oct/05 +20% - 10% Estimate Nov/05 Proposal to provide service to AESO Nov/05 Facility application filed with EUB Jan/06 Permit and licenseissued by EUB July/06 Equipment & material procurement July/06 Construction start Sept/06 +10% -10% Estimate Nov/06 In-service date Oct/07

Genesee to Langdon 500 kV Line AltaLink line optimization work is well underway AESO has participated in AltaLink’s landowner open houses along with the EUB Continue developing the functional specification and facility application for mid-2006

Genesee to Langdon 500 kV Line – Schedule AESO Need approved April/05 AltaLink begins landowner consultation July/05 Functional specification complete Feb/06 +20% -10% estimate Apr/06 Proposal to provide service to AESO Apr/06 Facility application filed with EUB June/06 Permit and licensefrom EUB Dec/06 Equipment & material procurement Jan/07 +10% -10% estimate March/07 Construction start June/07 In-service date Sept/09

Questions?

Stakeholder Information Update Edmonton-Calgary 500 kV Transmission Development December 14, 2005 Cost Estimate Update Stephen Kane, director, 500kV Project Execution - AltaLink

Genesee to Langdon 500kV Line Original Needs Estimate $299M (2004 dollars; includes AltaLink & EPCOR costs) Adjustments Escalation (04 to 09 dollars) $ 42M E&S $ 12M (EUB approves rate for capital projects) AFUDC $ 20M (allowance for funds used during construction) Current as-spent dollars 2009 in-service date as per original needs estimate $373M

South KEG Conversion Original Needs Estimate $40M (2004 dollars; includes AltaLink & EPCOR costs) Adjustments Escalation (04 to 07 dollars) $3.0M E&S $1.5M (EUB approves rate for capital projects) AFUDC $0.5M (allowance for funds used during construction) Current as-spent dollars 2007 in-service date as per original needs estimate $45M

South KEG Conversion Current as-spent dollars 2007 in-service date$45M Transformer amendment$12M Escalation, E&S, AFUDC$1.5M Brushing & Clearing$1.0M Escalation, E&S, AFUDC $0.2M Contingency$2.9M Current as-spent dollars 2007 in-service date$62.6M

South KEG Conversion Other Engineering Considerations Communications upgrade $1.0M - $4.5M Substation development staging $1.0M - $5.0M Transformer specifications $0.5M - $3.0M Transmission line terminations $1.0M - $2.5M Contingency $0.1M - $0.5M Adjustments (Escalation, E&S, AFUDC) $0.3M - $1.5M Total Potential $3.9M - $17M (Range reflects potential scope)

Stakeholder Information Update Edmonton-Calgary 500 kV Transmission Development December 14, 2005 S-KEG Engineering Considerations Fred Ritter, director, Engineering - AESO

AESO Review of TFO SKEG Proposals Engineering: Review project service proposals and associated cost estimates Review options with EPCOR Transmission and AltaLink to manage cost Detailed engineering studies ongoing Work with EPCOR Generation to coordinate with planned generator turnarounds where possible to manage costs Power Engineers providing ongoing support Planning: Review S-KEG conversion steps to determine if lower cost alternatives are possible through different sequencing of the conversion stages

Direction to AltaLink and EPCOR The AESO plans to issue direction to AltaLink and EPCOR Transmission in January 2006 to file a facilities application conditional upon: the EUB’s approval of the AESO’s transformer amendment; and, a review of AltaLink and EPCOR project proposals and options to manage project costs.

South KEG Conversion Other Engineering Considerations Communications upgrade Substation development staging Transformer specifications Transmission line terminations

Stakeholder Information Update Edmonton-Calgary 500 kV Transmission Development December 14, 2005 Landowner Consultation Update Dennis Walters, director, Major Projects - AltaLink

Siting Update: Genesee - Langdon 500kV line Completed first round of landowner consultation, which started in July 2005 and ended with two weeks of Nov/Dec open houses Most common landowner issues for new line: EMF Compensation Visual Farming impacts Land value Corridor Evaluating input from 2,000 landowners, plus Environmental Impact Assessment and other work

Early 2006: Refine route as much as possible and begin second round of landowner consultation Mid-2006: Plan to file facilities application Expect EUB hearing for N-S 500kV line Project schedule based on EUB decision by the end of 2006 Siting Update: Genesee-Langdon 500kV line

Siting Update: S-KEG Conversion Completed landowner and agency consultation All landowner issues addressed Plan to file facilities application with EUB early 2006 Project schedule based on EUB decision by mid-2006

Questions?

Contacts- Project Information Andy Kneubuhler, manager, 500 kV Projects Fred Ritter, director, Engineering – Transmission > Project Updates> Edmonton to Calgary 500 kV Transmission Development