July 18 2002S. Patricelli ATLAS TMB1 RPCs new schedule & QC results zSchedule yGas Volume production schedule yGlobal RPC schedule zQC results yGas Volume.

Slides:



Advertisements
Similar presentations
Davide Piccolo INFN Napoli Muon Annul Review Cern 15 September 2003 Chamber Production QA/QC MUON ANNUAL REVIEW On RESISTIVE PLATE CHMABERS CERN, 15 September.
Advertisements

Muon EDR: Chamber design M2/3 R1/2 16/04/20031T.Schneider/LHCb Muon EDR 1.General description - AW read out -Cathode pad read out -HV supply 2.Details.
Update on the bakelite gluing Feb 2002: first warning from BaBar  13 gaps (over 48) accepted (27%) (i.e. max 2 non contiguous unglued spacers)…the remaining.
RPC Atlas – Stato del progetto Riunione Commissione I 13 Maggio 2003 By R. Santonico.
Development of high rate RPCs Lei Xia Argonne National Laboratory.
THERMO-MECHANICAL TESTS ON TRACKER LADDERS (Low temperature problem on plane 1) Status Report: D.Rapin Sept 26,2012 (help from Giovanni, Franck, Mingming,...)
BMLD refurbishing G. Iacobucci and G. Chiodini INFN Bologna and Lecce for the RPC group CERN, June 19, 2006 ATLAS Muon week.
Status of OPERA RPC production. A. Garfagnini Opera collaboration meeting Nagoya, 12 march 2002  RPC production at GT;  Schedule for OPERA in 2002; 
Status of the LHCb RPC detector Changes with respect to Note cm strips instead of 3 cm (cost optimization) All gaps same size (standardization)
1 May 6, 2009 C. Lu Continuously Monitoring the RPC Gas Mixture with a Gas Chromatograph C. Lu Princeton University.
Status of the Tracker DB System Tk week april 03 D. Contardo Developments Applications.
ATLAS RPC: Cosmic Ray Teststand at INFN Lecce G. Chiodini, M. Bianco, E. Brambilla, G. Cataldi, R. Coluccia, P. Creti, G. Fiore, R. Gerardi, E. Gorini,
Davide Piccolo - INFN NapoliSIENA maggio 2004 Production and Quality control of RPCs for the CMS muon barrel system Davide Piccolo – INFN Napoli.
UPDATE ON CMS RESISTIVE PLATE CHAMBERS CMS RPC Barrel Collaboration GR1, 5 Aprile 2004.
QA/QC working group Working group ATLAS NSW - QA/QC working group - J. GIRAUD (20/02/2014)1.
Introduction to Gas Chromatography Written by Bette Kreuz Produced by Ruth Dusenbery University of Michigan-Dearborn 2000.
2011 HV scan SF6 flow-meter accident 2011 Results comparison RPC HV efficiency scan Pigi Paolucci on behalf of RPC collaboration.
Production Readiness Review of Frascati MWPC Production Site December 4 th, 2003 – P. Campana.
June 8-th 2004W.Baldini1 Ferrara production center Ferrara production center Production Readiness Review OverviewOfOperations P R R.
Results from development of Glass RPCs for INO detector
GRID job tracking and monitoring Dmitry Rogozin Laboratory of Particle Physics, JINR 07/08/ /09/2006.
ISR Work Progress Report Muon Week April 10 th 2003 A. Benvenuti INFN Bologna.
October 28-th, 2005Straw tracker 1 Status of Straw Tracker for P236 P.L. Frabetti, V.Kekelidze, K.Kleinknecht, V.Peshekhonov, B.Peyaud, Yu.Potrebenikov,
RPC Cosmic Rays Test in Naples Paolo Iengo Atlas RPC Group Napoli ( M. Alviggi, V. Canale, M. Caprio, G. Carlino,R. de Asmundis, M. Della Pietra, D. della.
Status of the Brick Manipulation database development Introduction: goal and principles System analysis –The brick life –Manipulation procedures Proposed.
Status of CERN M1R2 production LHCb Muon meeting sept.061Thomas Schneider -Beginning of 2006 two visits to Erbicol because of several reasons: -Material.
Malte HildebrandtDC Status Report, Dear MEG Committee,PSI, April 14 th 2009 this is the first report concerning the drift chamber status as.
PROCStar III Performance Charactarization Instructor : Ina Rivkin Performed by: Idan Steinberg Evgeni Riaboy Semestrial Project Winter 2010.
Tariq J. Solaija, NCP Forward RPC EDR, Tariq Solaija Forward RPC EDR The Standard RPC for low  regions Tariq J. Solaija National Centre for.
RPC production at GT (status and plans). Status After the IFR meeting in Rome a new version of the Production Plan have been proposed to GT Main requirements.
Silicon Meeting July 10, 2003 Module and Stave Production Status James Fast Fermilab.
May 2001, Istanbul Workshop High Voltage Plates and Capacitor Status Jack Fowler.
Optimization of the Resistive Plate Chamber operation with a closed loop gas system at the Large Hadron Collider experiments M. Capeans, I. Glushkov, R.
Bakelite surface vs Gap production Evaluation of First samples sent back from Korea Tests and QC of panels presently in GT Evaluation of second set of.
M. Gilchriese - April 2001 Disk Sector Status. M. Gilchriese - April Technical Status Three prototypes to current dimensions(8-sector disks) except.
Atsuhiko Ochi Kobe University 6, November 2012 ATLAS MicroMEGAS meeting.
Chamber construction Construction Tools Production sites Assembly Sequence (“travelers”) Manpower P. Campana LNF – LHCb Muon EDR Cern April 16 th, 2003.
The RPC Closed loop Gas System Slides from Bianco and Guida.
Operating System Principles And Multitasking
16/04/20031PNPI / LHCb Muon EDR Wire Pad Chambers PNPI design for regions R4 in Stations M2,M3,M4  4 gas gaps of 5mm±70µm;  Active area: 1224x252.8 mm².
MM detector construction One or several modules per sector considerations.
G. Pugliese RPC requests for GIF++ G.Pugliese, N. Zaganidis and I. Pedraza on behalf of the RPC group 1.
The techniques involved in systems analysis Explanation of a feasibility study:Explanation of a feasibility study: –economic, –legal, –technical, –time.
Andrea Di Simone Andrea Di Simone – INFN Roma2 Andrea Di Simone CERN PH/ATC and INFN-CNAF On behalf of ATLAS RPC groups: Lecce, Napoli, Protvino, Roma2.
LNF activities on WPC Panels Construction of prototypes and layout Status of tooling Proto 0, open items, plan,...
Status of NA62 straw electronics Webs Covers Services Readout.
G. PassalevaRoma - July 28, 2004 Status of MWPC production site in Florence G. Passaleva.
CM27 – 8 th July 2010 LH2 System Progress and Future Plans M Hills T Bradshaw M Courthold I Mullacrane P Warburton.
OPERA Coll.Meet. October 2002Luca Stanco - Padova1 1.Status of Magnets and financial orders (including RPC) Mario Spinetti15’ 2.Status of RPC (including.
G. Carboni - Muon Meeting – Muon Meeting 12/ Agenda IntroductionGiovanni (30’) GEM and TDR AddendumWalter (20’) Update on M1 ratesAlessia.
Results from the CMS-RPC tests at CERN Gamma Irradiation Facility Roberto Guida CMS-RPC (Bari, Beijing, Napoli, Pavia, Sofia) Seoul, October 2005.
QA/QC in MM SM1 Mod 0 Production at INFN QA/QC MM SM1 Mod 0 - G. Maccarrone 19-Jan
C.Gustavino, june 4th 2004, Hamburg XPC Status report VETO status report Glass RPC R&D Outline:
1 G. Aielli for the RPC community. General information  BOE to be delivered in September  Detector design is over  Production facility reviewd and.
Pavel Nevski DDM Workshop BNL, September 27, 2006 JOB DEFINITION as a part of Production.
Marcello Abbrescia RPCs for CMS during Phase II RPC rate capability M. Abbrescia, The dynamic behaviour of Resistive Plate Chambers, NIM A 533 (2004) 7–10.
9/12/2003Ivan Hruska1 First box prototype –Box design in July ‘03 –Box produced during August ’03 Tested last week in few fingers Small changes necessary.
19/6/2002S. Patricelli Muon week1 Status of RPC production (1) zThe leading production for RPCs is the the gas volume production at GT. All other items.
European DHCAL development European DHCAL development CIEMAT,IPNL,LAL, LAPP,LLR, PROTVINO, SACLAY CIEMAT,IPNL,LAL, LAPP,LLR, PROTVINO, SACLAY Status :
Concept Design for LBNF Far detector (LAr single phase)
Network integration with PanDA Artem Petrosyan PanDA UTA,
Siena 2002 Siena, 24/10/2002 G. Passaleva New results from an extensive aging test on bakelite RPC G. Passaleva INFN Firenze.
14/02/2008 Michele Bianco 1 G.Chiodini & E.Gorini ATLAS RPC certification with cosmic rays Università del Salento Facoltà di Scienze MM.FF.NN.
Production ad Quality control of RPCs for the CMS muon barrel system
Software for Spectrometer T0 jumps correction
RPC Production at GT A Mass scale RPC Production
CMS RPC Endcap RE1 Status Report
Page Replacement.
LO4 - Be Able to Update Websites to Meet Business Needs
NSS Instrument Project Tollgate Coordinator
Presentation transcript:

July S. Patricelli ATLAS TMB1 RPCs new schedule & QC results zSchedule yGas Volume production schedule yGlobal RPC schedule zQC results yGas Volume production - gluing yGas Volume production - oiling yGas Volume production - currents yProduction database Outline

July S. Patricelli ATLAS TMB2 Gas Volumes production plan at GT (Standard Units)

July S. Patricelli ATLAS TMB3 Gas Volumes Production details (Standard Units)

July S. Patricelli ATLAS TMB4 Global schedule zThe Gas Volume production sequence still has some flexibility, but not much due to time necessary for material procurement. yBOS production before BOL - Easy yBOS production before BMS - Very difficult zThe Global schedule for RPC Units production has to take into account the production status of all other components.

July S. Patricelli ATLAS TMB5 Production status - All parts

July S. Patricelli ATLAS TMB6 Readout panel production zConcern at present is for the preparation of readout panels (i.e. mounting of F.E. boards on strip panels). zMain reason for the delay is last delivery of Front End boards from Microtel. This was the first large delivery of F.E. boards for BML-D Units now under production. zHowever: this is also the most time consuming task in the production chain of RPCs.

July S. Patricelli ATLAS TMB7 Global RPC schedule Special Units not included in this schedule. We must first reach “cruise speed” in the production of Standard Units.

July S. Patricelli ATLAS TMB8 Gas Volume QC - Gluing zThe original idea (PRR) for spacer gluing QC was to prepare an external sample and measure the maximum stressing force before breaking. This test was found to be not the optimal solution for gluing QC. zDuring its production at GT BaBar prepared a machine which allows to measure, on closed gaps, if any spacer is not glued (push test). yRPC is laid on a straight table and gas flow is allowed up to a fixed pressure (5 mb). yA row of spacers is “touched” by a series of 660 gr. loads and P is measured continuously. yIf one of the spacers is not able to stand that pressure a clear jump in pressure is seen.

July S. Patricelli ATLAS TMB9 Gas Volume QC - Gluing zFilling upzLocalizing the spacer inside the row. zLocalizing rows of spacers with problems.

July S. Patricelli ATLAS TMB10 Gas Volume QC - Gluing zWe started the push test QC on our gas volumes after the “gluing crisis” and the introduction of the “washing machine”. yEvery day, before starting production, GT prepares some samples to verify glue polymerization. yOf all gas volumes produced in a day one undergoes the push test. yIf one gas volume has more than one spacer not well glued, the full production of that day undergoes the push test. yGas Volumes with more than one spacers not well glued are discarded. zProduction from 28/5 to 13/68/3672 = 0,2 % spacers not well glued 1/62 gas volume discarded (5 spacers) zProduction from 14/6 up to nowawaiting test at GT zFuture productionpush test done weekly

July S. Patricelli ATLAS TMB11 Gas Volume QC - Oiling zThe facility now at GT allows the simultaneous oiling of at least 40 gas volumes. zWhen this operation is done: xCollect a sample of the (output) oil which has been used xFill up one gas volume to high pressure (max 80 mb). If gas volume not broken (as it happens almost in all cases) the chamber is mechanically opened for visual inspection. xCut one or more pieces (10 x 10 cm 2) of oiled backelite zItems 1 & 3 are sent to the Dept. of Chemistry of Torino University

July S. Patricelli ATLAS TMB12 Gas Volume QC - Oiling - IR analysis zThe oil is first polymerized in thin films on inert support (to check the polymerization time) and then IR analyzed to detect if any contaminant is present. zOnly absorption peaks due to linseed oil present

July S. Patricelli ATLAS TMB13 Gas Volume QC - Oiling - IR analysis zThe sample of oiled backelite is IR analyzed using a micro ATR (Attenuated Total Reflectance) technique to detect any impurity or sign of oil degradation. zOnly absorption peaks due to linseed and bakelite present Backelite

July S. Patricelli ATLAS TMB14 Gas Volume QC - Oiling - IR analysis zFor each set on analysis we receive a written report (.doc) which is inserted in the production database. zGas Volumes oiled up to may 16th have been certified by this test. zFor Gas Volumes produced after this date we are waiting for results.

July S. Patricelli ATLAS TMB15 Gas Volume QC - Currents zFor chambers produced with “new” (2002) bakelite we decided to add a new step in the QC control chain before Gas Volumes are assembled in Units.  Before oiling, chambers are flushed in pure Argon, the HV is raised till current reaches 30  A ( ~ 2.5 kV) and the chamber is monitored for three days. Chambers with anomalous current drift are discarded (0/290 up to now). zAfter oiling chambers are flushed with ATLAS gas mixture (without SF 6 ), HV is raised up to 9 kV 20 °C) while recording the V-I characteristic.

July S. Patricelli ATLAS TMB16 Gas Volume QC - Currents Not accepted (1/44) Under observation (3/43) T = 32 °C

July S. Patricelli ATLAS TMB17 Production Database (1) zStatus of RPC production is reported in the Production Database. All parts are identified by bar-code. zBakelite plates: yDetails on all bakelite plates produced (Lecce at PanPla) yData from QC-1 (preparation) form (General Tecnica) zGas Volumes: yData from QC-2 (assembly) form (General Tecnica) yPush test results (Napoli at General Tecnica) yCurrent test results (Roma2 at General Tecnica - work in progress) yData from QC-3 (oiling) form (General Tecnica) yIR analysis results (Torino University)

July S. Patricelli ATLAS TMB18 Production Database (2) zReadout panels: yResults of Burn-in and bench test of F.E. boards (separate DB in Roma2) yMounting of F.E. boards on strip panels (Roma2) zSupport panels: yProduction data of support panels (Protvino) zRPC Unit assembly: yDetails of all parts which are in a Unit (Lecce)

July S. Patricelli ATLAS TMB19 Production Database (3) zThe Production database is available on the web via a user interface at (link from the RPC ATLAS page). zWarning: Data are not all up to date. yStill need some sensibilization of the production sites to transfer data in due time. ySome problems with 2001 production data which we are trying to recover. zQC results are accessible with queries via the user interface. Some are already implemented. Others are now being developed.

July S. Patricelli ATLAS TMB20 User Interface (1) Query result to trace back all components in a Unit.

July S. Patricelli ATLAS TMB21 User Interface (2) Query result to verify Gas Volume production status.

July S. Patricelli ATLAS TMB22 Conclusion zGas Volume for ATLAS production schedule is still compatible with ATLAS schedule. zMain concern at the moment is the schedule for Readout Panel production. zTime for special chambers still to be “allocated” in the schedule. This will be done only after “cruise speed” for Standard production is reached. zQC in Gas Volume production with new technique is under control for gluing, oiling and currents. zProduction Database needs some update for 2001 production (mostly bakelite). zAll QC results as described are in the D.B. Need to implement more queries (web interface) to extract statistical information.