Earned Value Management (EVM) Reference Card EVM Terminology ACWPActual Cost of Work Performed (Actual cost incurred for work accomplished during a given.

Slides:



Advertisements
Similar presentations
Connoizor Enabling Performance for Businesses through Software Website: Contact:
Advertisements

E ARNED V ALUE M ANAGEMENT G OLD C ARD Projected Slip ? Management Reserve Cost Variance Schedule Variance ACWP Cum BCWP Cum BCWS Cum $ EAC Time Now Completion.
Presenter: Sohel Akhter, PMP, CCNA,ISMS
Budget Management. 57 Budget Management Budget Development Good scheduling skills and abilities Understanding of the project scope Well developed WBS.
1 Earned Value Management a tool for project Portfolio management Jim Strong DLMP PMO Director.
Replanning, Reprogramming, and Single Point Adjustments July NAVY CEVM
N O T E “CLICK” TO CONTINUE… If the slide show is not launched, click on View  Slide Show in the menu bar at the top of the Power Point window. When the.
An Overview of Earned Value Management (EVM) Using EVM to Track Progress.
1 Estimating Costs At Completion Review this tutorial and the Project Pyramid Exercise until you are fully comfortable with how to calculate an estimate.
National Aeronautics and Space Administration ANSI/EIA-748-B Earned Value Management Systems (EVMS) 32 Guidelines ANSI/EIA-748-B Earned Value.
CSSE Oct.2008 Monitoring and reporting project status Chapter 10, pages
Irwin/McGraw-Hill ©The McGraw-Hill Companies, 2000 Chapter 13 Progress and Performance Measurement and Evaluation.
Chapter 10: Monitoring and Controlling Change
Management Reserve (MR) Total Allocated Budget (TAB)
ANSI/EIA -748 EVMS 32 Guidelines National Aeronautics and Space Administration.
Where We Are Now. Where We Are Now Structure of a Project Monitoring Information System Creating a project monitoring system involves determining:
BASICS OF EARNED VALUE MANAGEMENT
Earned Value Management
Progress and Performance Measurement and Evaluation CHAPTER THIRTEEN Student Version Copyright © 2011 by The McGraw-Hill Companies, Inc. All rights reserved.
Chapter 10 Project Monitoring and Control
OPSM 639, C. Akkan SAVE your existing MS Project File at the end of PART3 as _PART4 _PART4 WITH BASELINE. Make sure you keep the original file without.
Project Management 6e..
CPM-400: xxx Lesson B: EV Data Analysis I Instructor Ellen Udell
Earned Value Analysis by John Cornman. Introduction “Earned Value Analysis” is an industry standard way to measure a project’s progress, forecast its.
Validating IPMRs, CPRs, and IMS Deliverables NAVY CEVM
Project Management Methodology Project monitoring and control.
Chapter 13: Progress and Performance Measurement and Evaluation
Roberta Tomasini Defense Acquisition University DSN Earned Value and the Acquisition Program.
Dave Bachman DAU / CDSC September 9, 2004
PowerPoint Presentation by Charlie Cook Copyright © 2006 The McGraw-Hill Companies. All rights reserved. THE MANAGERIAL PROCESS Clifford F. Gray Eric W.
Department of the Interior CPIC Forum Department of the Interior CPIC Forum Better Control of Cost and Schedule Variance through Earned Value Management.
Chapter 15 Cost Control.
Software Project Management (SPM)
EARNED VALUE MANAGEMENT (EVM)
Earned Value Management System (EVMS). Given: –total budget of $100,000 –12 month effort –produce 20 units Status: –spent to date: $64,000 –time elapsed:
10/19/ :26 AM 1 Project Cost Control. 10/19/ :26 AM 2  Controlling involves making sure that the results achieved are in line with the planned.
Earned Value management This presentation is just a short introduction to a few terms and concepts. I am sure there will be training sessions in the next.
Project Management Part 6 Project Control. Part 6 - Project Control2 Topic Outline: Project Control Project control steps Measuring and monitoring system.
EVM Home Page = = “One Book” DAU POC: (703) (DSN 655) Address: Revised.
Project Cost Management
Mohawk Vehicle - MEGA HERZ ELEC & VEN - MOH-2 F C-0050 J:\CS40\Data Analysis\- Standard Analysis Package/Sample Standard Analysis Package.
Brookhaven Science Associates U.S. Department of Energy Facility Managers Meeting DOE-OECM Certification of Earned Value Management Systems April 27-28,
Earned Value Management (EVM) Reference Card EVM Terminology ACWPActual Cost of Work Performed (Actual cost incurred for work accomplished during a given.
Project Management 6e..
O The Integrated Program Management Report (IPMR), Data Item Description DI-MGMT (latest version) at DIDs.shtml,
Introduction To Earned Value November 14, Definition Earned Value is a method for measuring project performance. It compares the amount of work.
EVM UPDATE JANUARY 31/FEBRUARY 2, EVM REQUIREMENTS NASA PROCEDURAL REQUIREMENTS (NPR) D - NASA SPACE FLIGHT PROGRAM AND PROJECT MANAGEMENT.
Earned Value Analysis Tracking Project Progress. Introduction | Components | Project Scenario | Values | Calculations | Forecasts | Summary l What Is.
Presented by Niyi Ladipo September 14,  Results of the Survey  What is Earned Value Management (EVM)?  EVM vs. Traditional Cost Management 
EVM – Do You Really Know What the Numbers Mean? Booz | Allen |Hamilton Seth Huckabee EVP, PMP, PMI-SP.
1 Understanding Earned Value in Under an Hour Breakout Session # A11 Name: Wayne Brantley, MS Ed, PMP, ITIL Senior Director of Professional Education.
EARNED VALUE  Earned Value Management Systems  Earned Value Analysis.
Earned Value Management Reading the Roadmap to Project Success (or, Are We There Yet?) Steve Margolis, PMP Perpetual Technologies, Inc. March 19, 2008.
E ARNED V ALUE M ANAGEMENT ‘G OLD C ARD ’ Projected Slip ? Management Reserve Cost Variance Schedule Variance ACWP Cum BCWP Cum BCWS Cum $ EAC Time Now.
Session C01. Successful Implementation of an Over Target Baseline/Schedule from a Government Perspective 1 Session #C01 Name:Joseph Annunziato and Daniel.
Information Technology Project Management, Seventh Edition Note: See the text itself for full citations.
EVM Home Page = Address: DAU POC: (703) (DSN 655) Revised December 2006 TERMINOLOGY.
Schedule Control (Earned Value)
October 11, EARNED VALUE AND PERFORMANCE MANAGEMENT.
Earned Value Management Reading the Roadmap to Project Success (or, Are We There Yet?) Steve Margolis, PMP Perpetual Technologies, Inc. April 13, 2010.
Performance Measurement Baseline Contract Price (Project Price)
Project Monitoring
ANSI/EIA-748-B Earned Value Management Systems (EVMS)
Performance Measurement Baseline Contract Price (Project Price)
Project Cost Management
September 2016 EVM 202—Lesson 4 Integrated Baseline Review Process (Part 4: Baseline Maintenance)
Progress and Performance Measurement and Evaluation
Implementing EV in IT A Three Step Approach John Chapman Touchstone Ltd
Earned Value Measures Planned Value (PV) Earned Value (EV)
فرآيند كنترل پروژه.
Presentation transcript:

Earned Value Management (EVM) Reference Card EVM Terminology ACWPActual Cost of Work Performed (Actual cost incurred for work accomplished during a given period) AUW Authorized Un-priced Work (Work contractually approved, but not yet negotiated) BACBudget At Completion (Total planned value for the project) BCWSBudgeted Cost for Work Scheduled (Planned Value - budget assigned to the planned scheduled work to be accomplished) BCWPBudgeted Cost for Work Performed (Earned Value - budget value for the physical work accomplished) CAControl Account (Management control point to plan and control scope, schedule, and budget) CBBContract Budget Baseline (Total negotiated cost plus AUW) EACEstimate At Completion (Expected total cost of the project when the scope of work will be completed) ETCEstimate To Complete (Expected cost needed to complete all remaining work) MRManagement Reserve (Budget withheld for unknowns / risk management) NCCNegotiated Contract Cost (Contract price minus profit or fees or project value for in-house work) OTBOver Target Baseline (Sum of CBB and recognized overrun) PBBProject Budget Baseline (Same as CBB for in-house projects) PMBPerformance Measurement Baseline (Time-phased budget plan) PPPlanning Package (Far term effort within a CA not yet defined into WPs) TABTotal Allocated Budget (Sum of all budgets for work on project/contract = NCC, CBB/PBB, or OTB) TCPITo Complete Performance Index (Efficiency needed from ‘status date’ to achieve an EAC or BAC) UBUndistributed Budget (Broadly defined effort not distributed into CAs) WPWork Package (Near term effort detailed planned within a CA) Revised July 2011 NASA EVM Website: NASA Policy & Requirements for the Application of EVM NASA EVM requirements are found in NPR , NASA Program and Project Management Processes and Requirements and NPR , NASA Information Technology and Institutional Infrastructure Program and Project Management Requirements. Policy is contained in NASA FAR Supplement (NFS) NASA EVM requirements are predicated on the principles and guidelines in ANSI/EIA-748, Industry Guidelines for Earned Value Management Systems. NPR requires the project EVM approach to be in place by Key Decision Point (KDP) C (the conclusion of Preliminary Design Review (PDR)) and implemented in Phase C (Final Design and Fabrication) through KDP E (Flight Readiness Review (FRR) or Launch Readiness Review (LRR)). Additionally, project performance reporting must begin within 60 days after the start of Phase C. To meet this timeline, it is highly recommended that projects begin implementation planning during Phase B (Preliminary Design and Technology Completion). NPR also requires that NASA programs and projects use EVM on projects and contracts that meet the criteria that follow. 1.For projects with a total anticipated final value of $20 million or more, EVM principles should be applied, as defined by ANSI/EIA-748, Earned Value Management Systems. If the project's primary NASA Center has a validated EVMS, the project uses that system rather than the EVM principles application approach. 2.For development contracts and subcontracts valued at or between $20M and $50M, the contractor is expected to have an EVMS that complies with the 32 guidelines in the ANSI/EIA-748 Standard. 3.For development contracts and subcontracts valued at $50M or more, the contractor is required to have an EVMS that has been formally validated by the Government. 4.EVM is not required on contracts for non-developmental engineering support services, steady state operations, basic and applied research, and routine services such as janitorial services or grounds maintenance services. In these cases, application of EVM is at the discretion of the program or project manager (PM). NASA projects that do not have a validated EVMS will use the seven management principles that are contained in ANSI/EIA-748 standard. UB WPs PPs CAs PMB MR CBB Fee/Profit (no Project analogy) Contract Price (Project Price) AUW OTB TAB PBB *NASA Contractor & In-house Project Hierarchy Favorable Causes: Poor initial planning or estimating Technical breakthrough Cost of labor & Material lower than plan Front end loading Method of earning BCWP Inaccurate costing methods Performance Indices: (Favorable is > 1.0, Unfavorable is < 1.0) Cost Performance Index (Efficiency): CPI = BCWP / ACWP Schedule Performance Index (Efficiency): SPI = BCWP / BCWS To Complete Performance Index (TCPI) TCPI EAC = Work Remaining / Cost Remaining = (BAC – BCWP Cum ) / (EAC – ACWP Cum ) TCPI BAC = Work Remaining / Budget Remaining = (BAC – BCWP Cum ) / (BAC – ACWP Cum ) Unfavorable Causes: Poor initial planning or estimating Technical problem Cost of labor or material higher than plan Inflation New labor contracts Work stoppage Estimate at Completion (EAC) = ACWP + ETC EAC = Actuals to Date + Work Remaining / Performance Factor EAC Composite = ACWP Cum + (BAC – BCWP Cum ) / (CPI Cum x SPI Cum ) EAC CPI = BAC / CPI Cum Status Percentage % Complete = BCWP Cum / BAC x 100 % Spent = ACWP Cum / BAC x 100 % Schedule = BCWS Cum / BAC x 100 CV SV Actual Costs (ACWP) Earned Value (BCWP) Planned Value (BCWS) $ EAC Time Now Performance Measurement Baseline (PMB) BAC Time Management Reserve (MR) TAB (CBB or PBB) Projected Slippage VAC ETC Variances: (Favorable is Positive, Unfavorable is Negative) Cost Variance (CV): CV = BCWP – ACWP CV% = CV / BCWP x 100 Schedule Variance (SV): SV = BCWP – BCWS SV% = SV / BCWS x 100 Variance at Completion (VAC): VAC = BAC – EAC NCC Plus Overrun Common EAC Calculations