MOM report 23/9 – 28/9 G.CECCHET. MOM report Hall PPS commissioning Target tests last night MOM laptop.

Slides:



Advertisements
Similar presentations
MOM Report October 9- Now Linda R. Coney UCR. October 15 th Running Target Target Beamline Magnets Beamline Magnets Detectors? Detectors? Could not turn.
Advertisements

K. Long, 18 April, 2015 Beam-line status — red sky at night?
MOM Report Ray Gamet MICE Operations Manager University of Liverpool MICO 18 th May 2009.
MICE Beam Loss vs Particle Rate Adam Dobbs, ISIS Meeting, 18 th December 2009.
SS and AFC Control Systems Brian Martlew 21 st Sept 2011.
MOM Summary 19/01/10 Water Now the ice has cleared I am able to get on the roof again. Could do with getting the conductivity readings fed back similarly.
MOM Summary 11/01/10 Due to the Inclement Weather it has perhaps been quieter than usual Water - Tank has been holding water fine. Some ice has been forming.
MICE Particle Rate and ISIS Beam Loss Adam Dobbs, Target – ISIS Meeting, 17 th September 2010.
MOM Report Paul Soler MICE Operations Manager University of Glasgow MICO April 27, 2009.
MOM Report Paul Soler MICE Operations Manager University of Glasgow MICO April 20, 2009.
MOM Report Michael S. Zisman MICE Operations Manager Center for Beam Physics Lawrence Berkeley National Laboratory MICO March 16, 2009.
Linda R. Coney – 24th April 2009 MOM Update Linda R. Coney 21 September, 2009.
Linda R. Coney – 24th September 2009 MOM Update End of Sept Run Linda R. Coney 05 October, 2009.
MICO 1 st February 2010 Terry Hart (MOM). MICO 1 st February June 2015 Decay Solenoid DS will not be ready for Machine Physics. Matt Hills spent.
Online Reconstruction Update Linda R. Coney UCR Mar 25, 2010.
MOM Report Ray Gamet MICE Operations Manager University of Liverpool MICO 11 th May 2009.
MICE FAC Alain Blondel 1 Summary of run meeting 8 August 2011 Present: Andy Nichols Tim Hayler Pierrick Hanlet Gail Hanson Linda Coney Victoria.
MOM’s report from G.CECCHET (abridged). MOM’s report First half of November we had normal operations with some data taking for Marco, Yordan, Maurizio.
Computing Panel Discussion Continued Marco Apollonio, Linda Coney, Mike Courthold, Malcolm Ellis, Jean-Sebastien Graulich, Pierrick Hanlet, Henry Nebrensky.
Online Reconstruction Update Linda R. Coney UCR Dec 17, 2009.
1 Commissioning Needs MOM (m. apollonio) RUN Schedule –Dry Run –DAQ / Detectors / Target Proton Absorber –polarity inversion SHIFTERS ! Future MoM.
MICE Commissioning Issues Michael S. Zisman Center for Beam Physics Accelerator & Fusion Research Division Lawrence Berkeley National Laboratory MICO Meeting—RAL.
MICO Meeting, 1 st March 2010 Terry Hart (MOM) - Decay Solenoid - Targets - DAQ - March User Runs Plans - Suggestions.
Luminosity Monitor Commissioning MICE Collaboration Meeting March 2010 Paul Soler, David Forrest Danielle MacLennan.
MOM - M.ApollonioMICO meeting - RAL - 17/3/20081 NEXT steps + proposed aims Today - START Cherenkov INSTALLATION (?) Tuesday 25 MARCH - MICO Meeting (?
1 MICE PM Report Installations to date Future installation work Preparations for Phase Two Target status MICE Video Conference, 22nd May, 2008.
MOM Report. Shield Wall – Gone Before During After 2.
Detector Systems Update MICO March 3, MICE Detector Systems  CKOV u CKOV humidity (HIH4000) and temperature (LM35) sensors in hand for installation.
Pierrick Hanlet MICO June 6, 2011 MICE Operations Manager Report.
Alain Blondel MICE VC 9 september 2010 Spokesmouse report o VC 22nd April o 12th-13th May posters for IPAC (Vittorio Palladino) o VC 20th May o IPAC May.
MOM Report Paul Soler MICE Operations Manager University of Glasgow MICO May 5, 2009.
MOM Report Paul Soler MICE Operations Manager University of Glasgow MICO April 4, 2011.
MOM Report Linda R. Coney MICE Operations Manager University of California, Riverside MICO April 6, 2009.
MICO 8 th February 2010 Terry Hart (MOM) - Decay Solenoid and Target - MICE Machine Physics runs - Problems and Issues.
MOM Report Paul Soler MICE Operations Manager University of Glasgow MICO April 19, 2010.
Detector Systems Update MICO March 10, MICE Detector Systems  CKOV u No update  TOF0/1 u Tests with laser injection system progressing. u Tests.
Spectrometer Solenoid Update Michael S. Zisman Center for Beam Physics Accelerator & Fusion Research Division Lawrence Berkeley National Laboratory MICO.
MOM Report Linda R. Coney MICE Operations Manager University of California, Riverside MICO March 30, 2009.
MOM Report Linda Coney MICE Operations Manager University of California, Riverside MICO Meeting May 24, 2010.
Linda R. Coney – 24th April 2009 MOM Update Linda R. Coney 7 September, 2009.
MICE Online Linda R. Coney UCR MICE CM30 Oxford July 2011.
CM26 March 2010Jean-Sebastien GraulichSlide 1 Online Summary o The heplnw17 case o DAQ o CAM o Online Reconstruction o Data Base o Data Storage Jean-Sebastien.
MICE CM Alain Blondel 1   MICE GOALS OF THE MEETING Welcome to MICE CM28.
MICE VC Aug '10J.S. GraulichSlide 1 MOM report o Achievements Since CM27 o Daily Operations o Run Plans o Summary Jean-Sebastien Graulich, Geneva.
Linda Coney MC VC May 19, 2011 MICE Operations Manager Report.
MOM Commissioning Requests [Ken mail ] Target: - Timing - Turn-key system for target operation Beam counters: - Remove BC1 - Readout BC2 Electronics: -
DAQ MICO Report Online Monitoring: –Status All histograms are now implemented Still not fully online –Only monitoring from data file (slightly offline,
1 May run: Beamline Configuration. Some preliminary thoughts. K.Tilley, 24/04/08.
MOM Report Victoria Blackmore VC /06/11 1/7.
1M. Ellis - MICE VC - 1st November 2007 Cosmic Ray Test Preparations  The cosmic ray test was initially planned to be held in R12, but this proved to.
Click to add Text L. CONEY1 MICE Shifter Training June 2015.
1 MICE Hall construction status Richard Apsimon MICE VC meeting 29th Nov 2007.
Linda R. Coney – 24th September 2009 MOM Update Linda R. Coney 24 September, 2009.
MOM Report Paul Hodgson Paul Soler Victoria Blackmore VC-139: 14/04/111/8.
Alain Blondel MICE VC 12 March 2009 Brief MICE news 1. Decay solenoid: operations will restart in early July. Criteria for acceptance have been specified.
1 MICE Radiation Shielding MICE Phone Conference, 28 January 2004 Yury Ivanyushenkov Engineering Department, RAL.
March 18, 2008 TJRMICE Beamline Status1 MICE Beamline Status (March 18, 2008) Tom Roberts Muons, Inc. Illinois Institute of Technology.
Running plan Step I.1 Basic radiation levels. I.1.1 ISIS running with beam elements on, target off, beam stop shut. Establish permanent MICE monitoring.
MICE MICO Alain Blondel 23 December MICE Commissioning needs 22 December 08.
STARS AND CONSTELLATIONS. One day Isabelle was looking through her telescope she wanted to see the other planets in the solar system but all she could.
Electronics Spares for StepIV Operations MICE CM39 C.Macwaters 25/6/14.
11 th February 2008Brian Martlew EPICS for MICE Status of the MICE slow control system Brian Martlew STFC, Daresbury Laboratory.
MOM Report Linda Coney MICE Operations Manager University of California, Riverside MICE Video Conference May 20, 2010.
1 Updated Run Plans. K.Tilley, MICO, 07/02/08 - pre-commissioning - Target, - beamline functionality - detectors, particle production - decay solenoid.
Beamline Update Adam Dobbs, MICE CM38 Feb Contents Recent and Upcoming Activities Target Conventional magnets Decay Solenoid Proton Absorber Summary.
MICE Online Group Linda R. Coney UCR MICE CM31 UMiss October 2011.
MICE VC Alain Blondel 1 MICE NEWS MICE VC Next Collaboration meeting will be at Cosener’s14-16 February meeting at Coseners House.
What do we want to achieve in this running period? Michael S. Zisman Deputy Spokesmouse Center for Beam Physics Lawrence Berkeley National Laboratory MICO.
MICE Step IV Commissioning: Overview (March-April 2015) Milorad Popovic MAP 2015 Spring Collaboration Meeting.
L. Coney UC Riverside MICE CM32 – Glasgow – June 2012
Presentation transcript:

MOM report 23/9 – 28/9 G.CECCHET

MOM report Hall PPS commissioning Target tests last night MOM laptop

MOM report Hall PPS commissioning The PPS system is near is near final commissioning. Craig is discussing with ISIS in order to do the final tests on the PPS crates in the MLCR. DSA already under PPS control of ISIS. Any access to DSA has to be discussed with ISIS. New OPN from D.Findley giving MICE full responsibility of the security of the Hall untill Nov. 6 th, 2011

MOM report Target tests last night Last night Paul, Adam, Andrew and Henry tested the target hard/soft aspects and all went fine (see eLog). Problems came out when we started some magnets to setup a beamline to test some detectors: D2, Q3 and Q6 couldn’t be started, only D1; Not possible to setup HV to TOF’s using remote control;

MOM report DAQ not receiving any trigger (see various reasons in eLog); Martin Hughes is away so we do not yet know the run plans for tomorrow (except targhet). Run plans will be updated tomorrow afternoon.

MOM report MOM laptop The MOM laptop suddenly failed to be connect to the RAL network creating me many problems. Now it seems to be back to normal thanks to the help of Craig and Antony. I’ll prepare a more detailed report on this with some suggestions. I’ll send it to Linda and the collaboration waiting for comments.