MOM Summary 11/01/10 Due to the Inclement Weather it has perhaps been quieter than usual Water - Tank has been holding water fine. Some ice has been forming.

Slides:



Advertisements
Similar presentations
K. Long, 18 April, 2015 Beam-line status — red sky at night?
Advertisements

MICE: Hall Infrastructure Chris Nelson CEng CM15 8 th June 2006.
MOM Report Ray Gamet MICE Operations Manager University of Liverpool MICO 18 th May 2009.
G.Barber Tracker Planning & Mechanical Preparation June Tracker Planning & Mechanical Preparation An outline of (known) outstanding work to be carried.
June 26, 2009TLH, NFMCC Friday Meeting1 MICE Updates MICE News Overview ISIS and MICE Schedules DAQ Review Spectrometer Update Aspirational Schedule Terry.
Step IV Infrastructure update STFC Tim Hayler Eddie Holtom Norbert Collomb Graham Stokes 14 th December 2011 MICO170 meeting 1Tim Hayler.
MOM Summary 19/01/10 Water Now the ice has cleared I am able to get on the roof again. Could do with getting the conductivity readings fed back similarly.
MOM Report Paul Soler MICE Operations Manager University of Glasgow MICO April 27, 2009.
MOM Report Paul Soler MICE Operations Manager University of Glasgow MICO April 20, 2009.
MICE: Hall Infrastructure Chris Nelson CEng CM16 8 th Oct 2006.
MOM Report Paul Soler MICE Operations Manager University of Glasgow MICE Video Conference April 22, 2010.
Linda R. Coney – 24th September 2009 MOM Update End of Sept Run Linda R. Coney 05 October, 2009.
MICO 1 st February 2010 Terry Hart (MOM). MICO 1 st February June 2015 Decay Solenoid DS will not be ready for Machine Physics. Matt Hills spent.
Acceptance Criteria for the Decay Solenoid Tom Bradshaw Mike Courthold Matthew Hills.
MOM Report Ray Gamet MICE Operations Manager University of Liverpool MICO 11 th May 2009.
MICO 22 nd February 2010 Terry Hart (MOM) - Decay Solenoid and Target - MICE Machine Physics runs - User Run Plans.
MOM’s report from G.CECCHET (abridged). MOM’s report First half of November we had normal operations with some data taking for Marco, Yordan, Maurizio.
MICO Meeting, 1 st March 2010 Terry Hart (MOM) - Decay Solenoid - Targets - DAQ - March User Runs Plans - Suggestions.
MOM Report Paul Soler MICE Operations Manager University of Glasgow MICO April 12, 2010.
MOM - M.ApollonioMICO meeting - RAL - 17/3/20081 NEXT steps + proposed aims Today - START Cherenkov INSTALLATION (?) Tuesday 25 MARCH - MICO Meeting (?
1 MICE PM Report Installations to date Future installation work Preparations for Phase Two Target status MICE Video Conference, 22nd May, 2008.
Pierrick Hanlet MICO June 6, 2011 MICE Operations Manager Report.
MOM Report Paul Soler MICE Operations Manager University of Glasgow MICO April 26, 2010.
MOM Report Paul Soler MICE Operations Manager University of Glasgow MICO May 5, 2009.
MOM Report Linda R. Coney MICE Operations Manager University of California, Riverside MICO April 6, 2009.
MICO 8 th February 2010 Terry Hart (MOM) - Decay Solenoid and Target - MICE Machine Physics runs - Problems and Issues.
MOM Report Paul Soler MICE Operations Manager University of Glasgow MICO April 19, 2010.
Commissioning needs: K.Long. Routine: LN2 bottle: –Needs to be sited in MICE Hall or outside vault so that routine checks of contents can be made.
MICO 15 th February 2010 Terry Hart (MOM) - Decay Solenoid and Target - MICE Machine Physics runs - User Run Plans.
Detector Systems Update MICO March 10, MICE Detector Systems  CKOV u No update  TOF0/1 u Tests with laser injection system progressing. u Tests.
Spectrometer Solenoid Update Michael S. Zisman Center for Beam Physics Accelerator & Fusion Research Division Lawrence Berkeley National Laboratory MICO.
Update Hardware for conductive cooling of the quench resistors has been fabricated at LBNL. Preparation for installation to start this week. Installation.
Detector Systems Update MICO Feb 25, MICE Detector Systems  CKOV u CKOV installation planned during March shutdown u Cable issues resolved. Geneva.
MOM Report Linda R. Coney MICE Operations Manager University of California, Riverside MICO March 30, 2009.
Linda R. Coney – 24th April 2009 MOM Update Linda R. Coney 7 September, 2009.
1 Summary of MICE beamline & hall installations This is a very rough summary of the progress since mid-December Richard Apsimon & Andy Nichols MICO meeting.
1 Hall & Beamline Installation Richard Apsimon, Andy Nichols, Willie Spensley MICE Collaboration Meeting, th Feb 2008.
1 MICE - INFRASTRUCTURE MICO meeting 7 th February 2008 Tim Hayler.
MICE: overview K. Long, 18 March, Contents ► Introduction ► Beam line ► Infrastructure ► MICE steps ► Phase II (comment) ► Conclusions.
UKNF/MICE PSAG, 3/5/11 Spectrometer solenoids: –Repair plan still ‘in approval’, already two months late –Workshop/mini review at LBNL 10 th /11 th May.
Infrastructure Update As at 11 th March 2009 Remaining four plates now fitted to North shield wall North & South walls and all galleries are considered.
MICE Magnetic Field Mitigation Review Potential impact on ISIS of MICE Stray Magnetic Fields 24 th September 2013 Martin Hughes.
MOM Report Galina Vankova RAL, MICE Video Conference.
MOM report – part I Roumen Tsenov as MOM ( )
Preparations in the MICE hall Video Conference 25 th June 09 Tim Hayler Andy Lintern Peter Lau Geoff Barber.
MOM Commissioning Requests [Ken mail ] Target: - Timing - Turn-key system for target operation Beam counters: - Remove BC1 - Readout BC2 Electronics: -
Schedule and Work We are moving into a very intensive 4 months with a lot of work to be carried out Electrical services to the devices – after the South.
Click to add Text L. CONEY1 MICE Shifter Training June 2015.
1 MICE Hall construction status Richard Apsimon MICE VC meeting 29th Nov 2007.
Linda R. Coney – 24th September 2009 MOM Update Linda R. Coney 24 September, 2009.
MICE FAC Alain Blondel 21 september   MICE The International Muon Ionization Cooling Experiment BRIEF STATUS OF MICE.
1 MICE Hall and Infrastructure - Progress since CM18 Chris Nelson MICE CM19 Oct 2007.
MOM Report Paul Hodgson Paul Soler Victoria Blackmore VC-139: 14/04/111/8.
MICE VC Alain Blondel 1 MICE NEWS MICE VC 161 Agenda Overall schedule Magnetic field mitigation review Status of things.
1 MICE PM Report Summary since CM21 Decay solenoid Infrastructure progress Step One Installation Worries MICE Video Conference, 19 th June, 2008.
1 MICE Beamline Installation, status & plans Contents: Upstream & Target, BPM Decay solenoid DSA, D2, Q4,5,6 cKOV support Q7,8,9 Open issues & concerns.
MICE VC MOM Report, 25 th February 2010 Terry Hart (MOM) - Decay Solenoid - Targets - DAQ - Machine Physics and User Runs - Suggestions.
March 18, 2008 TJRMICE Beamline Status1 MICE Beamline Status (March 18, 2008) Tom Roberts Muons, Inc. Illinois Institute of Technology.
PRY Base - Contents l PRY Support/Base/Platform in the MICE Hall l Requirements l Environment l Design l Structural Integrity l Preparation l Installation.
Target tests 1 st – 2 nd Nov. Chris Booth Sheffield 7 th December 2006.
MICE Project Report Alan Bross (for Paul Drumm). Project Issues ● Key dates: – ISIS Synchrotron start-up scheduled for 1st August ● Shielded area around.
Running plan Step I.1 Basic radiation levels. I.1.1 ISIS running with beam elements on, target off, beam stop shut. Establish permanent MICE monitoring.
G.Barber Mice Tracker Integration Harbin Jan Mice Tracker Integration Installation requirements & Procedure.
MICE MICO Alain Blondel 23 December MICE Commissioning needs 22 December 08.
MOM Report Linda Coney MICE Operations Manager University of California, Riverside MICE Video Conference May 20, 2010.
1 Project Infrastructure for steps I-III Tim Hayler, STFC – RAL MICE Collaboration Meeting, RAL, nd October 2008.
OsC mtg 15/10/2014 MICE Step IV Alan Grant. Content Step IV – Construction Status – Finances – Schedule – Risks – Summary 2.
1 MICE PM Report Phase One installations to date Phase One remaining items Progress with Phase Two Worries Don’t have time for a detailed status report,
What do we want to achieve in this running period? Michael S. Zisman Deputy Spokesmouse Center for Beam Physics Lawrence Berkeley National Laboratory MICO.
MICE PM Report Progress with the Infrastructure A few problems
Presentation transcript:

MOM Summary 11/01/10 Due to the Inclement Weather it has perhaps been quieter than usual Water - Tank has been holding water fine. Some ice has been forming in the tank. - Stopped going on the roof after the 7 th as conditions are too treacherous. -Display of water depth just outside MLCR seems fine. Could do with getting the conductivity readings fed back similarly. I believe A.Nichols has approached J. Governs wrt this. -Magnet Chiller controller outside of MLCR is crashing on a daily basis. Needs resetting every morning. Probable cause – Has been misbehaving since a component was removed. – Willie is also chasing this with John Governs. This box is currently only used for monitoring purposes.

MOM Summary 11/01/10 MICE HALL Decay Solenoid A larger Transfer Line collar is to be fitted on DS later today by WS and MH. This is to enable several adapters to be removed and will hopefully help improve the vacuum. Cryo Compressers A batch of fittings for the cryo compressors has arrived on the RAL site on Xmas Eve but have been mis-delivered. These are currently being chased by A.Nichols Other Work Willies team are currently drilling holes in the steelwork. Preparation work for the tracker solenoids. Linde Plant Servicing to run from 18 th to 22 nd Hall Survey completed this weekend. TOF1 slightly out. Willie sent results out.

MOM Summary 11/01/10 Daresbury - Guys are due to come Tue/Wed this week. -Installing Luminosity Monitors in target Synch - Replace component in target PSU - Install new interlock for target frame (will not be functional yet though) - Ensure that the target tip TC HW is correctly installed.

MOM Summary 11/01/10 Luminosity Monitors -Willie seems to have all of this in hand! -RAMS have all been sent off to Jane Vickers -P. Soler’s boys are due down today to bring the actual monitors. Paul is coming down himself on Tue or Wed -The stands for the monitors are in the MICE Hall and painted. Awaiting plate and lead blocks from G.Barber Wed – Pulling Cable from MLCR to synch. – Andy Nobbs / I.M. Job should be complete by the end of the week. DAQ - Spoke to JSG. He plans to come 26 th to 31 st of Jan to fix CAMAC. I have requested documentation so that a non-daq expert can plug leads back in.

MOM Summary 11/01/10 Running -No running planned for January because of shutdown -Running anticipated early in February Machine Physics (MP) 2 nd Feb? TBC -User Run Starts 16 th Feb – Confirmed -There will be a ISIS planning meeting later this month so that MICE can request beam time during MP. I will send out a request for what we would like to study. -UPDATE 14:00 -Alain has been discussing what we might like to do. I will draw up a list and circulate shortly