LCLS Beam Parameters, Status and Run Schedule Rick Iverson for the LCLS team 1 R. Iverson ESTB Workshop SLAC, March 2011.

Slides:



Advertisements
Similar presentations
January 6. January 7 January 8 January 9 January 10.
Advertisements

Jose Chan FAC- Undulator System Installation & Assembly 10/30/07 1 Undulator System Installation & Assembly Schedule Jose.
Workshop Issues Linac Coherent Light Source Stanford Synchrotron Radiation Laboratory Stanford Linear Accelerator Center Diagnostics.
X. X September Mo Tu We Th Fr Sa Su
Chubaka Producciones Presenta :.
ESTB Test Beam Procedures User Support Operations Schedules Carsten Hast March 17 th 2011.
ESTB Test Beam Upgrades Hadrons Shorter bunch length Carsten Hast March 17 th 2011.
FACET: A National User Facility Carsten Hast SLAC National Accelerator Laboratory.
Welcome! Mauro Pivi SLAC, ESTB Workshop March 2011, SLAC.
Technical Coordinator’s Report (KL for PD) Solenoid problems & Schedule Actions on –KL/CN: plan for work to December shutdown –KL/CN: plan for work in.
Richard M. Boyce FAC Review – Accelerator Installation October 29-31, Installation – Accelerator Systems Installation Planning.
June 19, 2008 Heinz-Dieter Nuhn, SLAC / LCLS Overview 1 Overview Heinz-Dieter Nuhn, SLAC / LCLS June 19, 2008 Introduction Workshop.
FAC review, 10/27 D. Schultz 1 e-Beams System Update Injector System Installation has started. Linac System Preparing for ’06 installation. Controls System.
2012 JANUARY Sun Mon Tue Wed Thu Fri Sat
Richard M. Boyce FAC April 16, LCLS Installation & Planning Integration process – IMT 2007 Installation Planning BTH.
All Experimenters’ Meeting January 09, Accelerator Operation Summary Calendar Week # 51 NuMI Weekly Integrated Intensity 8.81E18 protons BNB Weekly.
FAC, 4/16/07 D. Schultz 1 e-Beams Systems Update People ARR Linac Installation Undulator Production MMF Operations David Schultz.
Richard M. Boyce FAC October 29-31, Installation Planning Integration process – IMT update Installation Planning &
P Pathophysiology Calendar. SundayMondayTuesdayWednesdayThursdayFridaySaturday January 2012.
1 E. Carrone 1 FEE PPS Status FAC FEE PPS Status Enzo Carrone June 8, 2009.
Mike Scharfenstein FAC Review - November 11, 2008 SLAC National Accelerator Laboratory 1 Environment Safety & Health Status.
E. Bong, SLACLCLS FAC Meeting - April 29, 2004 Linac Overview E. Bong LCLS FAC Meeting April 29, 2004 LCLS.
9/22/04J. Welch, LCLS Commissioning Worskhop, SLAC LCLS Commissioning Schedule and Startup Plan LCLS Commissioning Schedule and Startup Plan.
LCLS Undulator Systems TDR Charge Linac Coherent Light Source Stanford Linear Accelerator Center Technical Review, March 3, 2004.
E166 Collaboration J.C. Sheppard SLAC, October, 2003 E166 Background Test Beamtime Request J. C. Sheppard.
Whole School Attendance Whole School Attendance 94.64% Overall School Absence 5.36%
ELECTRIC KILNS – JANUARY 2015 SundayMondayTuesdayWednesdayThursdayFridaySaturday Small 123 Large Small Large Small Large Small.
FAC, 10/12/06 D. Schultz 1 Readiness for 2007 Startup Linac Injector Controls ARR David Schultz.
John Seeman LCLS December 2, Conduct of LCLS Accelerator Operations John Seeman Assistant Director LCLS Directorate.
All Experimenters’ Meeting February 09, Accelerator Operation Summary Calendar Week # 06 NuMI Weekly Integrated Intensity 6.69 E18 protons Beam.
David Schultz Accelerator Readiness Dec. 2, ‘08 SLAC National Accelerator Laboratory 1 Undulator Complex Status LCLS Introduction.
September 2008 SundayMondayTuesdayWednesdayThursdayFridaySaturday
R. Corsini, CLIC Project Meeting October 24, 2012 CTF3 Experimental program for end 2012 R. Corsini for the CTF3 Team 1.
DATE POWER 2 INCOME JANUARY 100member X 25.00P2, FEBRUARY 200member X 25.00P5, MARCH 400member X 25.00P10, APRIL 800member.
February 21-21, 2008JINR Scientific Council 103-d session IREN project status.
The End Station Test Beam (ESTB) at SLAC Carsten Hast For the everlasting never giving up SLAC Test Beam Gang R. Erickson, T. Fieguth, C. Hast, J. Jaros,
SLAC End Station A Test Beam ESTB Carsten Hast SLAC National Accelerator Laboratory ALCPG11 Eugene, Oregon March 22 nd, 2011.
ESTB End Station Test Beam Design, Performance, Infrastructure, Status Mauro Pivi, SLAC National Accelerator Laboratory on behalf of ESTB/ESA team ARD.
DR 3.2 km Lattice Requirements Webex meeting 10 January 2011.
John N. Galayda LCLS Accelerator Readiness December 2, LCLS Overview December 2, 2008 Project Construction Status.
FACET User Support Carsten Hast Accelerator Research Division Test Facilities Department
2011 Calendar Important Dates/Events/Homework. SunSatFriThursWedTuesMon January
SunSatFriThursWedTuesMon January
SABER, “maybe” a new facility in the South Arc (South Arc Beam Experimental Region) End Station A (ESA) in 2007 ILC Test Beams in 2008 Test Beams beyond.
All Experimenters’ Meeting January 26, Accelerator Operation Summary Calendar Week # 03 NuMI Weekly Integrated Intensity 2.74 E18 protons Beam.
End Station A Test Beam (ESTB) Carsten Hast and Mauro Pivi August 23 th 2012 Proposals, Procedures, Schedule.
End Station A Test Beam Facility ESTB Carsten Hast SiD Workshop SLAC, January 16-18, 2013,
All Experimenters’ Meeting December 8, 2014 Photo by Greg Vogel.
X LCLS SCU NbTi Prototype Schedule Version: February 12, 2015 Update 23JUN2015 X X System complete and ready for test X System complete & tested w/Hall.
Math Review 4 th Grade. Dates There are 52 weeks in one year. There are 365 days in one year. January, March, May, July, August, October, and December.
PIP Update Oct 29 th Agenda Summary Update – Current Activities – Updates – Additional Meetings/Notes.
July 2007 SundayMondayTuesdayWednesdayThursdayFridaySaturday
29/10/09 Positron Workshop 1 Working Assumptions for Low Energy Operations Jim Clarke ASTeC & Cockcroft Institute Daresbury Laboratory.
LCLS-II Project Overview David Schultz LCLS-II Deputy Project Director March 19, 2012.
August Wildcat Express 8-11, Inservice Inservice Inservice Inservice ,
Conditions at a potential location of a beam dump experiment at LCLS-II Clive Field, SLAC: 4/29/16.
End Station A Test Beam ESTB Design, Performance, Infrastructure, Status Mauro Pivi, SLAC on behalf of the ESTB team: C. Hast, T. Beukers T. Fieguth, R.
SLAC ESTB End Station A Test Beam Other Test Beams
McDonald’s Kalender 2009.
McDonald’s Kalender 2009.
13-block rotation schedule
My ‘Proposal’ is to turn one of these photos…
McDonald’s Kalender 2009.
FY 2019 Close Schedule Bi-Weekly Payroll governs close schedule
McDonald’s calendar 2007.
McDonald’s calendar 2007.
Production Month Sun Hours K Monthly Kwh Tou Peak Value After Kwh
2015 January February March April May June July August September
UNITS OF TIME QUESTIONS.
Presentation transcript:

LCLS Beam Parameters, Status and Run Schedule Rick Iverson for the LCLS team 1 R. Iverson ESTB Workshop SLAC, March 2011

2

LCLS on the web: 3 R. Iverson ESTB Workshop SLAC, March 2011

4

LCLS Short Term Schedule short-term-schedule.pdf 5 R. Iverson ESTB Workshop SLAC, March 2011

Additional availability: BYKIK “On” Upstream of the LCLS undulator, BYKIK kicker is used to park the beam out of the beam line. When BYKIK turns “ON”, the A-line kickers will also fire “ON” to re-direct the LCLS beam in ESTB A-line  ESTB If LCLS experiments don’t need full 120 Hz rate, the remaining beam is parked out by BYKIK.

Number of pulses per hour parked on BYKIK dump in December, About ~5% additional availability to ESTB/ESA. Additional availability: BYKIK “On”

LCLS Schedule This Down Time (now to mid May) MCC electrical work and PPS certification End of May LCLS starts up and runs until Christmas (last week in October off) October 25-Nov 1: Install HXRSS chicane in undulator hall Linac off from Christmas to end of January LCLS running resumes February 2012 R. Iverson ESTB Workshop SLAC, March