HL-LHC Planned Activities - Accelerator

Slides:



Advertisements
Similar presentations
The HiLumi LHC Design Study (a sub-system of HL-LHC) is co-funded by the European Commission within the Framework Programme 7 Capacities Specific Programme,
Advertisements

Sc Magnet test facility Consolidation Project presentation M. Bajko for the TEMB on behalf of the MSC TF section team 31. Aug
ColUSM #51 30 th January, 2015 D. Duarte Ramos, C. Mucher, L. Gentini, T. Sahner, H. Prin, R. Wawrowski, Q. Deliege, V. Baglin, F. Savary.
11 October 2006Basic Layout of LER G. de Rijk1 Basic Layout of LER  The basic idea  VLHC type magnets  LER in the LHC tunnel  Layout  LER experiment.
F. Savary on behalf of the WP11 team Input from V. Baglin, D. Ramos.
Crab Cavities in IR1 and IR5 Some considerations on tunnel integration What will be the situation in the tunnel after the LHC IR Phase-1 Upgrade. What.
1 Presented at ColUSM by D. Ramos on behalf of the Cold Collimator Feasibility Study Working Group Longitudinal.
WP 13 : Beam Diagnostics Conceptual Specifications Rhodri Jones (BE/BI)
The HiLumi LHC Design Study (a sub-system of HL-LHC) is co-funded by the European Commission within the Framework Programme 7 Capacities Specific Programme,
CRYOGENICS AND POWERING
MQXF Cold-mass Assembly and Cryostating H. Prin, D. Duarte Ramos, P. Ferracin, P. Fessia 4 th Joint HiLumi LHC-LARP Annual Meeting November 17-21, 2014.
The HiLumi LHC Design Study (a sub-system of HL-LHC) is co-funded by the European Commission within the Framework Programme 7 Capacities Specific Programme,
FP 420 Connection Cryostat Design and Integration Keith Potter, Jaak Lippmaa, Guido Ryckwaert, Benoit Florin, Thierry Renaglia, Thierry Colombet, Shrikant.
The HiLumi LHC Design Study is included in the High Luminosity LHC project and is partly funded by the European Commission within the Framework Programme.
1 Second LHC Splice Review Copper Stabilizer Continuity Measurement possible QC tool for consolidated splices H. Thiesen 28 November 2011 K. Brodzinski,
Cryogenics in SPS & LHC (2 K / 4.5 K) LHC-CC11, 14 November 2011 L. Tavian, CERN, TE-CRG With the contribution of N. Delruelle, G. Ferlin & B. Vullierme.
The HiLumi LHC Design Study is included in the High Luminosity LHC project and is partly funded by the European Commission within the Framework Programme.
The HiLumi LHC Design Study is included in the High Luminosity LHC project and is partly funded by the European Commission within the Framework Programme.
The HiLumi LHC Design Study is included in the High Luminosity LHC project and is partly funded by the European Commission within the Framework Programme.
The HiLumi LHC Design Study is included in the High Luminosity LHC project and is partly funded by the European Commission within the Framework Programme.
The HiLumi LHC Design Study (a sub-system of HL-LHC) is co-funded by the European Commission within the Framework Programme 7 Capacities Specific Programme,
Readiness of test stations for design validation Marta Bajko on behalf of the TE-MSC TF team CERN, 11 th December 2014 QXF design review, CERN.
12th HL-LHC Parameter and Layout Committee meeting.
The HiLumi LHC Design Study is included in the High Luminosity LHC project and is partly funded by the European Commission within the Framework Programme.
JRA on Development of High Temperature SC Link Motivation Work Packages Partners & resources Amalia Ballarino Esgard open meeting CERN,
Plan for test station Marta Bajko For the Technical Review of FReSCa2 June 2015 Saclay Paris.
Superconducting Technologies for the Next Generation of Accelerators CERN, Globe of Science and Innovation 4-5 December Superconducting Links for the Hi-Lumi.
The integration of 420 m detectors into the LHC
HL-LHC 11 T Dipole for DS Collimation 8 th to10 th December, 2014 D. Duarte Ramos, C. Mucher, L. Gentini, T. Sahner, H. Prin, R. Wawrowski, F. Savary,
The HiLumi LHC Design Study is included in the High Luminosity LHC project and is partly funded by the European Commission within the Framework Programme.
TE-CRG Activities D. Delikaris, TE-CRG.
CW Cryomodules for Project X Yuriy Orlov, Tom Nicol, and Tom Peterson Cryomodules for Project X, 14 June 2013Page 1.
ColUSM #63 18 th September, 2015 D. Ramos, C. Mucher, L. Gentini, H. Prin, Q. Deliege, A. Bastard, J. Hrivnak.
Logo area HL LHC IT STRING M. Bajko CERN TE-TM and QXF Review.
TEST FACILITY STATUS FOR TESTING CERN Marta Bajko WP10. EUCARD 2 Task 4 - HTS Magnet Tests, June 2015.
Training LHC Powering – Blanca Perea Solano From Individual System Tests to Powering to Nominal Blanca Perea on behalf of Hardware Commissioning Coordination.
Integration of forward physics detectors into the LSS of the LHC D. Macina (TS/LEA) Technical Support 2004 Workshop.
28 th January LHC Performance Workshop Session 8: (E)YETS and Long Shutdown 2 Strategy and Preparation. HL-LHC.
NIKHEF Annual Meeting, December 18, The LHC Project Status report to the NIKHEF annual meeting Jos Engelen Based on last week’s reports to CERN.
The HiLumi LHC Design Study is included in the High Luminosity LHC project and is partly funded by the European Commission within the Framework Programme.
Cryogenics storage and distribution
Cold mass design, assembly plans and QA/QC at CERN
Framework Schedule from EYETS 2016 to LS2
HL-LHC IT STRING and Series test of SC link
SLHC –PP WP6 LHC IR Upgrade - Phase I.
Roadmap for triplet cryostats
HL-LHC Aperture Update
M. Alcaide Leon, Paolo Fessia
Long Shutdown for the LHC: Vacuum Beam Pipes
Comparison between 1) HL-LHC BASELINE: Q5 at point 6 at 1
M. Alcaide Leon, Paolo Fessia
Cryogenics for sc links, a short update
Powering the LHC Magnets
Hollow e- lens, Cryogenic aspects
Accelerator and Experiment Interface Session: LS2, LS3
Machine lay-out September 2015
The 11T cryo-assembly: summary of design and integration aspects
UK RFD Pre-Series cryomodule
Superconducting Links and Cold Powering components for HL-LHC
DEBRIS IMPACT IN THE TAS-TRIPLET-D1 REGION
TEST PLANS for HL LHC IT STRING
Optic design and performance evaluation for SPPC collimation systems
LHC installation status
HL-LHCV1.4 (BI) R. De Maria WP13 meeting 3/9/2018.
Summary post TCC#54_02Aug’18
Review of hardware commissioning
Review Bloc 4 and SM18 facilities and upgrade
HL-LHC New MS optimisation WP9, Preliminary cost estimates
HL-LHCV1.4 (BI) R. De Maria WP13 meeting 3/9/2018.
J. Fleiter, S. C. Hopkins, A. Ballarino
Presentation transcript:

HL-LHC Planned Activities - Accelerator I. Bejar Alonso – HL-LHC Technical coordinator On behalf of HL-LHC WPs Leaders

HL-LHC baseline (P. Fessia Presentation)

Warm compressor and other surface eq. Interaction Region and MS Equipment on the Beam Tunnel equipment Vert. J Surface Eq. Dis. Cryoplant IP 1,5 CB Warm compressor and other surface eq. Interaction Region and MS IP 1,5 P I C BIS Cryo line IR+MS Alignment QPS2 Magnet system MQXFA MQXFB, MBXF, MBRD, MQYY, Q5 1.9, Q6 1.9 MCBXFB, MCBXFA, MQSXF, MCTXF, MCTSXF, MCDXF, MCDSXF, MCOXF, MCOSXF, MCSXF,MCSSXF, MCBRD, MCBYY EE DF(X-M) + SC Link DSH (X-M) TAXS, TAXN DFH(X-M) + Power converters Collimation (TCTPM, TCL, TCLM, TCTP) Rad-hard electronics for BLM and BPM Beam vacuum Beam diagnostic BPMSQW, BMPSQ, BPMSQT, BMLC RF system Loads, circulators, RF power, LLRF, HVPS, central LLRR Crab Cavity cryomodules CC diagnostic and protection SC link/ Powering arc IP 1,5 DS Collimation pp (TBC RUN II) IP 1,5 H.F. dipoles Cryo-bypass+TCLD DFA+ SC Link DSHA DFHA + Power converters DS Collimation for ion IP 2 H.F. dipoles Cryo-bypass+TCLD In orange Works during LS2 SC link/powering IP 7 Hor. SC Link DSH + DFA Power converters DS Collimation pp (TBC RUN II) IP 7 H.F. dipoles Cryo-bypass+TCLD

In orange Works during LS2 Equipment on the Beam Tunnel equipment Vert. J Surface equip. Dis. Collimation upgrade P I C BIS Secondary TCSPM IP 3 7 Primary TCP TCPP IP 3 7 TCSG, TCLA, TCAP IP 3 7 TCSP IP 6 Injection protection IP 2 8 TDI (TBC) TCLIA, TCLIB (TBC) TCDD TCDDM (TBC) TCLIM (TBC) MKI (TBC) Beam diagnostic IP 4 Fast wire scanners BWSF New light extraction line BSRT Beam gas vertex detector BGV Cryoplant IP 4 Warm compressor and other surface eq. Cryo line for RF CB Q5 at point 6 IP 6 Dump (TBC) TCDS (TBC) MKB, TDE (TBC) In orange Works during LS2 High rad warm magnets (TBC) IP 7 Mini-TAN IP 8

HL-LHC options

Crab Cavity for crab kissing scheme Other RF harmonic system Equipment on the Beam Tunnel equipment Vert. J Surface equipment Dis. WIC FMCM BBLR IP 1,5 Crab Cavity for crab kissing scheme IP 1,5 Other RF harmonic system IP 4 Sub harmonic Higher order harmonic ADT upgrade IP 4 Hollow e-lenses IP 4 Crystal collimation TECG IP 7 In orange Works during LS2 TAS IP 8

HL-LHC ARCHITECTURE & INSTALLATION DURING LS2

What about LS2? Marzia’s presentation The LS2 project include the activities across the LHC, Injectors and LHC experiments: Resources levelling across the accelerators  one of the main challenge of LS2 !!! The activities will be declared in Plan, with a similar approval process as LS1. Practical issues: Temporary storage areas and “bases de chantier” will be installed at the earliest 6 months before, and dismounted at the latest 6 months after LS2; Buffer zone availability: most probably the existing areas are not sufficient;

HL activities @ P2, P4 and TZ76 Proposal of First Draft skeleton Marzia’s presentation 2018 2019 July '18 Aug. '18 Sept. '18 Oct. '18 Nov. '18 Dec. '18 Jan. '19 Feb. '19 March '19 April '19 May '19 June '19 July '19 Aug. '19 Sept. '19 Oct. '19 Nov. '19 Dec. '19 WARM UP and TESTS Lift replacement CRYO Maintenance Magnets replacement Other activities… HL activities @ P2, P4 and TZ76 Cool Down @ P7 HL activities @ LSS7 COOL DOWN, TESTS and HWC Depending on the cool down and warm up sequence Windows available for activities  Between 9 and 13 Months

WPs with potencial installation activity during LS2 SPS test during Run 2

In orange Works during LS2 Magnets (WP3) Magnets (WP3) LQXFA (Q1) MQXFA LQXFC (Q2A) MCBXFB MQXFB LQXFD (Q2B) LQXFB (Q3) LCXF (CP) MCBXFA MQSXF MCTXF MCTSXF MCDXF MCDSXF MCOXF MCOSXF MCSXF MCSSXF LBXF (D1) MBXF LBRD (D2) MBRD MCBRD LQYY (Q4) MCBYY MQYY LQYCJ (Q5) MCBY MQY LQNDF (Q6) MCBC MQML Cryo-assemblies Cold masses level still to be defined Magnets Replacement of Q5 in IP6 In orange Works during LS2

Different options for the Q5 Present arrangement LHCQQS_S0255 LHCQQS_S0123 LHCQQS_S0254 LHCQQS_S0004 MQY MCBY Proposal for HL-LHC Based on the arrangement of Q7 in the experimental insertions. Using existing components design with available spare parts in the stock (TE-MSC-LMF). Longitudinal dimension increased by 3650mm compared to the present situation. MQY MQY MCBY Cold masses assemblies could be assembled for an installation in LS2

+ Q5 Integration issues To be discussed during the 14/10 HL-LHC PLC To avoid the QRL service module displacement: combining a jumper connection Q6L3 like to the modified shape To be discussed during the 14/10 HL-LHC PLC +

Halo cleaning (Betatron & Momentum) Collimation (WP5) Collimation (WP5) IR cleaning Incoming TCTPM Outgoing TCL TCLM DS collimation TCLD P3 TCLDx P2 P7 P1&P5 Halo cleaning (Betatron & Momentum) Crystal collimation Hollow E-Lens TCSPM Present collimators TCP, TCPP TCSG TCLA TCAP TCSP TCTP TCTPM (Target Collimator Tertiary Pick-up metallic) TCSPM (Target Secondary Collimator Pick up metallic Installation of prototypes Currently existing in LHC machine (to be eventually modified)

Cold Powering (WP6) Superconducting link P7 Cold Powering (WP6) Tunnel Interconnection Cryostats [DF] Arc [DFA] DFAA (L1) DFAB (R1) DFAI (L5) DFAJ (R5) DFAM (L7) DFAN (R7) Matching sections [DFM] DFMA DFMB DFMI DFMJ DFMM DFMN Inner triplets [DFX] DFXA DFXB DFXI DFXJ Current Leads HTS [DFLH] Surface Interconnection Cryostats [DFH] [DFHA] DFHAA DFHAB DFHAI DFHAJ DFHAM DFHAN [DFHM] DFHMA DFHMB DFHMI DFHMJ [DFHX] DFHXA DFHXB DFHXI DFHXJ Superconducting links HTS [DSH] [DSHA] DSHAA DSHAB DSHAI DSHAJ DSHAM DSHAN [DSHM] DSHMA DSHMB DSHMI DSHMJ [DSHX] DSHXA DSHXB DSHXI DSHXJ Superconducting links [DSL] [DSLM] DSLMM DSLMN Power converters

Overview of Point 7 DFBA actual position DFBA actual position SC links IP7 SC links DFB HL-LHC positions

Routing under study With 2 new long ducts from UJ76 to the TZ76 gallery

Experiments-Collider Interface (WP8) Target Absorbers for Insertion Region Secondary (TAXS) ATLAS CMS LHCb Radiation shielding (ATLAS and CMS) Target Absorbers for Insertion Region Neutrals (TAXN)

P8 LEFT (8L). INTEGRATION NEUTRAL ABSORBER. C4L8 D2 TCTPV NEUTRAL ABSORBER (10x12x60 cm3) 113700mm/ IP8 TCTPH BRAN

P8 LEFT (8L). INTEGRATION NEUTRAL ABSORBER. C4L8

Cryogenics (WP9) Cryogenics in P4 Cryogenics (WP9) Storage Warm (QSV) QSVA (80 m3) QSVB (250 m3) Cryogenic (QSD) QSDQ? Refrigeration Warm compressors stations QSCA QSCB QSCC QSCD QSCE QSCF QSCG Refrigeration units QSRA QURA QSRB QURC QURD QURE QURF QSRG QURCG Dryers (QSA) Distribution Warm piping Surface QSP Shafts QPP Ring Helium (QRPR) Warm recovery (QRPW) Interconnection boxes QUIA QUIB QUIC QUIF Transfer lines QPLB QPLG Underground QULA QULCA/B QULF QRL Experimental areas and LSS QXL LHC existing Specific to HL-LHC Modified for HL-LHC (already existing)

Cryogenics P4 Under study alternative scenarios that take in consideration different upgrade phases Decision to be taken in Autumn 2015

11 T Dipole Magnets (WP11) 11 T Dipole Magnets (WP11) 2 m Model Double-aperture Magnet (MBHDP) Single-aperture Magnet (MBHSP) 11-T Dipole (DS) Cryo-assembly (LBH) Cold mass (LMBH) Magnet (MBH) Other (tbc) Cryo-assembly prototype (LBH_P) (LMBHP) (MBH_P) Connection cryostat (LExxx)

Integration in the LHC Lattice Connection cryostat 15660 mm 11 T dipole cold mass Interconnect Collimator MB replaced by 3 cryo-assemblies, installed and aligned independently 11 T dipoles assembled with an angle of 2.55 mrad relative to each other and shifted by 0.8 mm towards the center of the LHC to minimize loss of mechanical aperture Cryostat for the 11 T dipole following standard LHC design Short connection cryostat: creates space for collimator and warm beam vacuum sector; continuity of powering and cryogenics along the LHC arc Collimator: 0.8-m-long active part – tungsten – 1.34 m with transitions and expansion joints RF-shielded gate valves allow for independent operation of cold and room temperature beam vacuum sectors Example of integration on the left side of an interaction point (IP7 in this case), two main dipoles are replaced by four 11-T Dipoles, and 2 collimators

Vacuum (WP12) Support to all WPs Vacuum (WP12) Vacuum (V) Beam screen Non-shielded (VSC) P2 (VSCG) P8 Shielded Beam Screen (VSM) P1 (VSMA) P5 Vacuum chambers (VCj) Vacuum layout (LV) LSS 1 LSS 5 LSS 4 Insulation vacuum (LVI) By pass vacuum layout (LV) Vacuum layout experiments (LVXj) ATLAS CMS LHCb ALICE Support to all WPs j: 1, 2, 5, 8

Beam Diagnostics & Instrumentation (WP13) Beam Loss Monitors [BLM] Cryogenic [BLMC] RadHard electronics [BLE] Fast Wire scanners [BWSF] Beam Position Monitors [BPM] Cryogenic Cryogenic stripline [BPMSQ] Tungsten shielded cryogenic stripline [BPMSQT] Warm Q1 stripline [BPMSWQ] Electronics [BPE] Luminosity Monitors [BRANQ] Wideband pick-ups [BPW] Synchrotron light monitors [BSR] Light Extraction [BSRTM] Interlock Abort Monitor [BSRA] Streak cameras [BSRS] Halo diagnostics [BSRH] Beam Gas Vertex Detector [BGV] Chamber [BGVC] Detector [BGVD] Long Range Beam Beam Compensator Collimator wire prototype [TCTPW?] Final [BBLR] Installation of prototypes

Beam Transfer & Kickers (WP14) Injection TDIS TCLIA TCLIB TCDD TCLIM MKI Magnets Controls upgrade LHC beam Dumping System MKB-TDE TCDS

WP14: For both IP2 and IP8 IP6: No installation foreseen in LS2. Will all be LS3. IP TDI to be replace by TDIS, most likely from 1  3 tanks TCLIA and TCLIB possibly replaced One proto-type MKI to be installed during run 2 and/or LS2 (only one LS) TCDD to be replaced by tighter mask

PLACE TO BE DEFINED (1.8mx2m) Surface Cryogenics P4 PX46 SX4 NEW TECHNICAL GALLERY PLACE TO BE DEFINED (1.8mx2m) Halfen supports EXISTING TECHNICAL GALLERY Minor modifications SUH4

Other infrastructures/works Minor works for Cold Powering P7 Possibility to advance civil engineering (excavation and buildings) in P1 and P5 and use of surface buildings for storage Installation work compatible with maintenance and consolidation work Importance of SM18 upgrade

Conclusions Identify and prepare work that can be done in LS2 on the time frame allocated for which the technology/solution is mature and can not bring any risk to the run 3 start date Integrate as early as possible our work planning with other LS2 Works Work together with the consolidation team to optimize resources

Cryo-assembly LHCQQS_S0255 LHCQQS_S0123 LHCQQS_S0254 LHCQQS_S0004 Based on the Q7 vacuum vessel with the adapted service module and covers. Components availability under study with TE-MSC-CMI.

Cold to warm transition Two-phase He heat exchanger Sector valve Locally enlarged cold mass Bus bar flexible elements for thermal contraction compensation Bus bar lines are moved away from beam to create space for the collimator Usage of standard LHC interconnect components: reliability, tooling, procedures Envelope for collimator vacuum vessel Vacuum vessel connection cryostat

SM18 upgrade. We relay on it Request from HL LHC Limitations of the present installations Cryostat geometry: Typical Magnet parameters for QXF type magnets Maximum stored energy : 10 MJ Nominal Current : 17 kA Short Sample current > 20 kA Magnet inductance : 8,27 mH/m Magnet outer diameter: 0.63 m Magnet length : 2 – 16 m max. Nominal Ramp Rate: 11 – 20 A/s Maximum Ramp Rate: 400 A/s HL LHC string with 100 m of Sc link cooled with feed box and powered by DFB (6x 3 kA 9x 120 A 1 x 11 kA 2 x 25 kA) 45m including D1 550 mm diameter D = 800 mm L= 1.5 m D = 600 mm L= 4 m Power converter and EE: I max = 20 kA Fresca 2 dipole 20 kA Fresca dipole 2 with HTs FReSCa HL LHC QXF in horizontal ( 25 kA) 10 or 20 tests Series HL LHC QXF in horizontal ( 25 kA) 10 or 20 tests till 2021 QXF long HL LHC QXF in vertical 25 kA QXF short HL LHC 11T in horizontal 11T Dipole HL LHC 11T in vertical HFM SMC,RMC EUCARD2 + 5T Sc link 20 m 20 kA 20 m 600 A 60 m 600 A x 24 60 m, 1 x 20 kA 3 x 20 kA,9 x 120 A, 6 x 300 A LHC cold masses( MQ, Correctors) in vertical cryostat LHC LHC cryo magnets (MB, SSS, S4, USA magnets, ondulators, connection cryostats…) in horizontal position Projects timing 2014 2015 2016 2017 2018 2020