CSSE 372 20.Oct.2008 Monitoring and reporting project status Chapter 10, pages 317-342.

Slides:



Advertisements
Similar presentations
COST CONTROL - EARNED VALUE 1.0. EARNED VALUE - INTRODUCTION
Advertisements

Connoizor Enabling Performance for Businesses through Software Website: Contact:
Presenter: Sohel Akhter, PMP, CCNA,ISMS
©2003 Rolls-Royce plc The information in this document is the property of Rolls-Royce plc and may not be copied or communicated to a third party, or used.
Budget Management. 57 Budget Management Budget Development Good scheduling skills and abilities Understanding of the project scope Well developed WBS.
 Costs are planned, measured, analyzed and controlled in terms of project activities.  Expenditure for any activity is incurred evenly over the duration.
1 What Is It ? Why Do I Need It ? How Do I Do It? Earned Value Analysis.
Monitoring and Control Earned Value Management (EVM)
Microsoft Project 2002 Sessions 5-6. Entering Tasks During this first session we will enter a set of tasks that comprise building a shed – data sheet.
Chapter 10: Monitoring and Controlling Change
Monitoring and Controlling
Project Monitoring and Control. Introduction Goal: ensuring that the project is on time and on budget and/or highlight any deviation from the plan Areas.
Phase III: Execution Phase IV: Monitoring and Control Earned Value Analysis Burns: Chapter 8: pages Burns: Chapter 12: the entire chapter Schwalbe:
Earned Value Management
OPMA 5364 Project Management Part 6 Project Control
Chapter 10 Project Monitoring and Control
Project Management 6e..
EARNED VALUE MANAGEMENT SYSTEM A Project Performance Tool
Earned Value Analysis by John Cornman. Introduction “Earned Value Analysis” is an industry standard way to measure a project’s progress, forecast its.
This work is licensed under a Creative Commons Attribution 3.0 Unported LicenseCreative Commons Attribution 3.0 Unported License (CC-BY). Project Management.
Project Monitoring and Control. Monitoring – collecting, recording, and reporting information concerning project performance that project manger and others.
Project Management Methodology Project monitoring and control.
1 ev14a Interactive Session 4 u Tuesday, July 17 7pm to 10pm u Build a sqa plan for the dental office software u Assume a 3-person, development team, a.
1. Earned Value Analysis (EVA) Earned value is a measure of progress enables us to assess the “percent of completeness” of a project using quantitative.
Earned Value JOEL VIRAY TOPICS What is Earned Value Management? –Why do I need it? –How do I do it? Earned Value Reporting Earned.
Monitoring and Information Systems
Software Project Management Lecture # 7. What are we studying today? Chapter 24 - Project Scheduling  Effort distribution  Defining task set for the.
EARNED VALUE MANAGEMENT (EVM)
Earned Value Management System (EVMS). Given: –total budget of $100,000 –12 month effort –produce 20 units Status: –spent to date: $64,000 –time elapsed:
10/19/ :26 AM 1 Project Cost Control. 10/19/ :26 AM 2  Controlling involves making sure that the results achieved are in line with the planned.
Earned Value SOS section Sp8Jan24ev3. Earned Value Analysis One approach to measuring progress in a software project is to calculate how much.
Chapter 9 Project Development. What to manager Client experience  Clients are very important  Happy or not is largely dependent on their expectations.
Project Management Part 6 Project Control. Part 6 - Project Control2 Topic Outline: Project Control Project control steps Measuring and monitoring system.
1 Project Management – Unit 4 – Part 1 Cost Model ACWP: Actual cost of work performed: Actual costs in performing the work so far. BCWP: Budgeted cost.
Stage III: Project Execution and Control Earned Value Analysis B: Chapter 8: pages B: Chapter 12: the entire chapter.
Project Cost Con trol. 1.To identify those work types having excessive costs and to give an indication of how serious those overruns are. 2.To forecast.
Advanced Project Plan Tracking Lesson 15. Skills Matrix SkillsMatrix Skill Record actual start, finish, and duration values of tasks Enter actual start.
UU Master Class Earned Value 17 July Earned Value Contents What is Earned Value / Earned Value Analysis Why and where is it used A brief history.
Introduction To Earned Value November 14, Definition Earned Value is a method for measuring project performance. It compares the amount of work.
Earned Value Analysis Tracking Project Progress. Introduction | Components | Project Scenario | Values | Calculations | Forecasts | Summary l What Is.
Where Module 04 : Knowing Where the Project Is 1.
1 Earned value analysis Planned value (PV) or Budgeted cost of work scheduled (BCWS) – original estimate of the effort/cost to complete a task (compare.
PMP Study Guide Chapter 11: Controlling Work Results.
EVM – Do You Really Know What the Numbers Mean? Booz | Allen |Hamilton Seth Huckabee EVP, PMP, PMI-SP.
1 Understanding Earned Value in Under an Hour Breakout Session # A11 Name: Wayne Brantley, MS Ed, PMP, ITIL Senior Director of Professional Education.
Information Technology Project Management, Seventh Edition Note: See the text itself for full citations.
Schedule Control (Earned Value)
Project Cost Con trol. 1.To identify those work types having excessive costs and to give an indication of how serious those overruns are. 2.To forecast.
What Is It ? Why Do I Need It ? How Do I Do It? Earned Value Analysis.
Agenda ‒ Cost Management ‒ Cost Budgeting ‒ Cost Control Learning Goals 1.Cost Control 2.Earned Value Management.
Project Management 1 Project Control. Project Management 2 Topics Project Control Status Reporting Earned Value Analysis.
Earned Value Management
Measuring Progress HNC Project Management. Measuring Schedule Performance Break project tasks up into small work units. Work units that are too large.
Earned Value Analysis by Miles M. Hamby, PhD Copyright©2014 Miles M
Project Monitoring
“PMP® Exam Prep” Earned Value Management
TOPIC-8B- PROJECT COST CONTROL
PROJECT MANAGEMENT AND CONTROL
CHAPTER:7 Project Cost Management
Earned Value Management
Earned Value Management
Progress and Performance Measurement and Evaluation
Earned Value - What is it
An Introduction to Earned Value Performance Measurement
Monitoring and Reporting Project Progress
Earned Value Measures Planned Value (PV) Earned Value (EV)
ENGINEERING MANAGEMENT (GE 404)
فرآيند كنترل پروژه.
5. Project PLAN & cost estimation
Managing Project Work, Scope, Schedules, and Cost
Presentation transcript:

CSSE Oct.2008 Monitoring and reporting project status Chapter 10, pages

Outline Control vs. risk Other kinds of reporting EV

Why do we need to monitor progress? 70% of projects are: Over budget Behind schedule 52% of all projects finish at 189% of their initial budget Average of 16% of SW projects are on-time and budget Source: The Standish Group

How and What to Update? Determine a set period of time and day of week Report actual work accomplished during this period Report start and finish dates Report days of duration accomplished and remaining Report resource effort Report percent complete

Types of progress reporting Current period reports Cumulative reports Exception reports Stoplight reports Variance reports Numerical Graphical

Milestone trend charts

Stoplight reports

EVA Earned Value Analysis (EVA) is: an industry standard way to: measure a project’s progress, forecast its completion date and final cost, and provide schedule and budget variances along the way.

Baseline vs. actual cost curve

Let’s talk terms BCWS - Budgeted Cost of Work Scheduled ACWP - Actual Cost of Work Performed BCWP - Budgeted Cost of Work Performed

Variance (EV – PV) Positive Indicates ahead of schedule or less cost than planned May not always be good Negative Indicates behind schedule or more cost than planned May not always be bad

Full story

Performance indices Schedule Performance Index SPI = BCWP/ BCWS Cost Performance Index CPI = BCWP/ ACWP

Let’s do an example… PROJECT STATUS: Make 1000 widgets over 50 days (20 per day) INPUT: Total Expected Output = 1000 INPUT: Budgeted Unit Cost = $.50 Total Project Budget is 1000 x $.50 = $500.

EV Input BCWS: How much did we expect to pay for the work that was scheduled? Total Project Days = 10 Unit Production Per Day = 20 widgets/day Budgeted Unit Cost = $.50/widget BCWS = 10 days x 20 widgets/day x $.50/widget budget = $100

EV Input BCWP: How much did we expect to pay for the work that was actually done? Actual Current Output = 150 Budgeted Unit Cost = $.50/widget BCWP = 150 widgets x $.50/widget budgeted = $75

EV Input ACWP: What was the actual cost of the work that was completed? Actual Current Output = 150 Actual Unit Cost = $.60/widget ACWP = 150 widgets x $.60/widget actual = $90

EV Analysis SV: Schedule Variance = BCWP – BCWS The Question: Are we ahead or behind production schedule? SV = BCWP – BCWS = $75 - $100 = -$25

EV Analysis SPI: Schedule Performance Index = BCWP/BCWS The Question: How far ahead or behind schedule are we? SPI = BCWP/BCWS = 75/100 = 0.75 (LT 1, so behind schedule)

EV Analysis CV: Cost Variance is measured as follows: If BCWP > ACWP, the project is UNDER budget! If BCWP < ACWP, the project is OVER budget! The Question: Are we on or off budget? CV = BCWP - ACWP = $75 - $90 = -$15 (negative means over budget)

EV Analysis CPI: Cost Performance Index The Question: How far on or off budget are we? CPI = BCWP / ACWP = 75/90 = (less than 1 means over budget)

Project forecast EAC: Estimate at Completion Method 1: BCWP at a point + Estimates to completion. Method 2: The ratio of BAC / CPI. Method 3: (Wilkens) [(BAC - BCWP)/CPI] + ACWP The Question: At the rate going, how much will all of this cost? This is a SIMPLIFIED estimate of EAC EAC = BAC / CPI = $500 / = $600

Questions?