Status at DORIS Hall New fixed cable channel on the floor for cables from outside to electronics hut Firedetection and network connections rerouted to.

Slides:



Advertisements
Similar presentations
April 6th 2009Olympus Meeting at DESY, F.Brinker1 Detector power supply Detector cooling Polarity switches Kicker pulser Preparation of the experimental.
Advertisements

PEPPo Weekly Status Meeting February 16, 2011 & 6MSD Planning Meeting February 23, 2011 Part 1 – Technical summary of layout Part 2 – Month-by-Month Installation.
Meeting on status and plans of the LP subsystems for the LP beamtest at DESY 02/25/2008 Franck SENÉE1 LP-TPC: Micromegas Panel and Cosmic Muon Trigger.
How to Perform Preventive Maintenance of the Personal Computer Properly Shut Down of the Computer Properly Shut Down of the Computer Unplug all Connection.
HEL pre-design Diego Perini Superconducting solenoid Operation temperature: 4.2 K, current:about 250A, magnetic field: 5 Tesla Cooled by liquid.
Inti Lehmann University of Glasgow 27 June 2011 Status of the TOFs.
September 15th 2009Olympus technical review at DESY, F.Brinker1 DORIS storage ring Olympus in the IP-region Beam optic, changes on the lattice Beam dimensions,
Status at DORIS Hall Argus was removed by end of march Argus Parts (except 4 heavy pieces) shipped to Hall 1 Rails of electronics hut have to be extended.
Luminosity Monitor MWPCs, commissioning. A.Kiselev OLYMPUS Collaboration Meeting DESY, Hamburg,
OLYMPUS Collaboration Meeting Cooling Water David Rodríguez Piñeiro Mainz University OLYMPUS Collaboration Meeting DESY
Status at DORIS Hall Bolted connections of Al- frame made conductive for grounding reasons. Power cable connections rerouted at the top connections. Magentic.
F.Brinker, DESY, July 17 st 2008 Injection to Doris and Petra Fitting the detector in the IP-region Radiation issues Beam optic, Target cell Polarisation.
Intermediate Frame for Olympus Interface from Blast Frame to Argus rails Track gauge of Blast is 4645 mm while track of Argus is 3200 mm. We want to keep.
Status at DORIS Hall June 28th start of mounting the Al- frames, progressig very fast, finished by July 9th All 8 coils pressure tested with 15 bar = O.K.
1 MICE Magnets Contents: Background Refurbishment Testing Installation & survey Current status Upstream beamline Open issues & concerns MICE Beamline Review,
MICE Collaboration Meeting Harbin, China 13 – 17 January 2009 Integration Issues By Wing Lau, Oxford University.
RD51 Common Test Beam: Status RD51 collaboration week Kolymbari, June 2009 Yorgos Tsipolitis NTUA.
EATM12-08 Contribution NA62 Francois Butin, Lau Gatignon / EN-MEF 4 September 2012.
LBT Q Engineering Review PSPI: PEPSI installation preparation, includes all of the pier modifications.
ISR Work Progress Report Muon Week April 10 th 2003 A. Benvenuti INFN Bologna.
1 Hall & Beamline Installation Richard Apsimon, Andy Nichols, Willie Spensley MICE Collaboration Meeting, th Feb 2008.
NUMI NuMI Review of the Infrastructure – W, G & V 20 July 2001 WBS Page 1 1 Infrastructure Review - W.B.S Water Systems Water Systems –Upstream.
+ Circuits. + Why can’t you use lightning to power electrical devices? Lightning releases large amount of electricity. Devices need CURRENT to flow.
05/30/08J. Dunne -- SANE Collaboration Meeting 1 Beamline Status Upstream beamline –Chicane –SEM –Rasters –Girder Downstream beamline –Helium bag –Extension.
S1G Experiment Schedule Plan H. Hayano. Assembly work after cavity arrived Assumption: cavity with VT, with pickup antena, with Ar or N2 filled,
Beam Profile Monitor Status Immediate Objective Materials needed Projections Conclusion Anthony Tatum University of North Carolina Wilmington.
Magnetic Shielding Roy Preece. Issues Cooling channel initially designed without return yolks. Current North and South shielding walls designed to encapsulate.
1 HO Upgrade: QC and Production Preparation in India Shashi Dugad India-CMS Meeting, BARC 30 July 2010.
July LEReC Review July 2014 Low Energy RHIC electron Cooling Al Pendzick LEReC Civil Construction.
Accelerator and NuMI Upgrades Shutdown Update Cons Gattuso July 02, 2012 July 2, 2012 Cons Gattuso1.
Target Status Target installed in ISIS “Demonstrator” target in R78 Chris Booth Sheffield 7 th February 2008.
1 MICE Hall construction status Richard Apsimon MICE VC meeting 29th Nov 2007.
Spectrometer Solenoid Fabrication & Testing Update Steve Virostek Lawrence Berkeley National Lab MICE CM25 at RAL November 6, 2009.
Straw Working Group Status assembly at CERN Plans 10/2/14Straw WG.
1 MICE Hall and Infrastructure - Progress since CM18 Chris Nelson MICE CM19 Oct 2007.
ECAL – EE Design Status Presentation 19/7/06 D.J.A. Cockerill - RAL 1 EE Design Status D Cockerill CERN 19 July 2006.
S1G Experiment Schedule Plan; H. Hayano ILC10 GDE meeting.
LHCb Experimental Area Meeting V. Bobillier1 Earth network in UX85 experimental cavern.
Transversity Readiness and Timeline Xiaodong Jiang, March 17th, This document specifies the overall readiness for Hall A experiments E06-010/E
The Building 180 Cryogenic infrastructure water cooling system Status Update Stefano Moccia, EN-CV Coordination meeting 14/10/15.
Target tests 1 st – 2 nd Nov. Chris Booth Sheffield 7 th December 2006.
SBS Magnet and Infrastructure Status Robin Wines July 2015.
Target Commissioning Target installed in ISIS “Demonstrator” target in R78 Initial commissioning plans Chris Booth Sheffield 11 th February 2008.
1 Mice Collaboration Meeting CM33 Glasgow University 25 th – 29 th June 2012 STFC Daresbury Laboratory Electrical Infrastructure Report Authors : Ian Mullacrane.
IBL CO 2 cooling planning 03 July 2013 Jan Godlewski, Bart Verlaat, Lukasz Zwalinski 1
1 BROOKHAVEN SCIENCE ASSOCIATES Accelerator Systems Installation F. Willeke, ASD Director 6 th ASAC October 22-23, 2009.
9/12/2003Ivan Hruska1 First box prototype –Box design in July ‘03 –Box produced during August ’03 Tested last week in few fingers Small changes necessary.
Booster Shutdown Work - Week 4 Dump and Shielding installation completed Q805/Q806 re-installed, Septum in place Need to align quads and septum before.
News from DESY. Joachim Mnich Plenary ECFA CERN, November 2011.
DON LYNCH NOVEMBER 6, AGENDA November 4, BABAR Magnet Update Global Design Concept – Update Outer HCal Structural Analysis (2 nd pass) sPHENIX.
LARP LHC PHASE II COLL RC1 TESTS - S. Lundgren 30 Jan 2007 No 1 /13 LARP Phase II Secondary Collimator RC1 Collimator Development and Test Program Status.
T2 Status Report IP5 Installation Future plans. IP5 installation The mechanical structure has shown problems on installation and should be changed slightly.
Chris BoothUniversity of Sheffield 1 Target Status & Progress 1 st February 2006 Disappointingly slow progress over last 2 months. However, progress is.
Layout and conventional facility N.Terunuma KEK. Conventional facility 1 Layout of beam line should be fixed until end of June We have to start.
09/21/07Shutdown’07 Week 7 F.G. Garcia1 MTA beam line installation Weekly Report September 21, 2007 Period covered: September 14 th September 21 th (Week.
MICE Target – Status & Plans Chris Booth Sheffield 28 th February 2006.
1. Road to the EDR 2 Requirements Safety system Transfer line concept Plant concept design Requirements Evaporator concept and performance Transfer line.
LHCb CO 2 cooling meeting Burkhard Schmidt – May 20,
Proton PMG September 3 rd 2015 Cons Gattuso AD Shutdown Manager.
Operations meeting on FY07 Shutdown Date: June 27, W.B. Christie Outline Brief Overview of Shutdown Plan Details/discussion of next few weeks Comments.
Sébastien MICHALMarch Sébastien MICHALMarch 2009 EES 1 GROOVE EES 1 laid on table to be milled EES 1 laid on table to be milled –Move horizontally.
K.Gadow - DESY 1 The HCAL barrel absorber structure Design Status
ELENA installation progress F. Butin / ELENA collaboration.
David BAILLEUX On behalf of the Caltech group Issues for the Laser Monitoring System M&O - US CMS ECAL IB meeting 19 March Chilled water supply.
H.-G. Moser, April 25, 2016 Gemba Summary 1 Plan: Shipment (sea transport in summer) 6-8 weeks => arrival August/September Commissioning: After October.
Fan Coil Controller FC/S 1.1
SR1 extension follow up 27-Mar-17 Marco Ciapetti.
S1G Experiment Schedule Plan
Organics Waste Processing Facility Construction Progress Update July 8, 2011
Polarized 3He target installation
Presentation transcript:

Status at DORIS Hall New fixed cable channel on the floor for cables from outside to electronics hut Firedetection and network connections rerouted to the electronics hut Power to container under design (8 * 16 Amps. in the hut) Rails of electronics hut are extended to allow free access to entire pit All pieces of OLYMPUS frame moved to Hall 4 On Monday 28th start of mounting the frames Work is progressing well Jan Hauschildt, MEA1, June 29th, 2010

Status at DORIS Hall Pipes for gassupply recovered from ZEUS experiment and under preparation Material for water cooling on hand. Internal working order released Cables for power of coils laid from transformer via power supplies and polarity switches to the pit. Jan Hauschildt, MEA1, June 29th, 2010

Status at DORIS Hall, Hall 1 Work on shielding design started Work on lead curtain design in DORIS Tunnel started Coils still in Hall 1, going to move them to DORIS Hall, change water connections to DESY standards Still missing : Multiton rollers for the frames and watercooling manifolds Next shipment from Bates due to arrive mid July Jan Hauschildt, MEA1, June 29th, 2010