GLAST LAT ProjectMonthly Status Meeting Jan 26, 2006 1 Project Status January 26, 2006 Gamma-ray Large Area Space Telescope Lowell A. Klaisner Project.

Slides:



Advertisements
Similar presentations
 Costs are planned, measured, analyzed and controlled in terms of project activities.  Expenditure for any activity is incurred evenly over the duration.
Advertisements

GLAST LAT ProjectMonthly Review, Aug-1, DAQ & FSWV1 1 GLAST Large Area Telescope: Electronics, Data Acquisition & Flight Software W.B.S
GLAST LAT ProjectNovember 3, 2005 I&T Phase 0 IRR/TRR 1 GLAST Large Area Telescope: Integration and Test Phase 0 IRR/TRR November 3-4, 2005 Introduction.
CSSE Oct.2008 Monitoring and reporting project status Chapter 10, pages
GLAST LAT Instrument GLAST Monthly Mission Review August 6, 2007 K. Fouts, SLAC 1 Monthly Mission Review Project Status Overview August 6, 2007 Ken Fouts.
1 GLAST Large Area Telescope Monthly Mission Review LAT Flight Software Status June 6, 2007 Jana Thayer Stanford Linear Accelerator Center Gamma-ray Large.
© 2007 General Dynamics. All rights reserved. Integrated Space Systems 1196 EB-R GLAST Pre-Ship Review (PSR) LAT Payload I&T Review CONTRACT NO.
GLAST LAT ProjectLAT Face to Face, July 17-18, GLAST Large Area Telescope: Lowell A. Klaisner Stanford Linear Accelerator Center
Microsoft Project 2002 Sessions 5-6. Entering Tasks During this first session we will enter a set of tasks that comprise building a shed – data sheet.
GLAST LAT ProjectMonthly Status Meeting, June 30, Cost/Schedule Reports for 4.1 LAT Presentation Presentation May 2005 Month End Gamma-ray Large.
GLAST LAT Project LAT System Engineering 1 Test Definition Planning Pat Hascall SLAC System Engineering Gamma-ray Large Area Space Telescope.
GLAST LAT ProjectNovember 04, 2005 Phase 0 TRR 1 GLAST Large Area Telescope: Integration and Test -Electrical Test- Phase 0 TRR Key Requirements Documents.
1 GLAST Large Area Telescope Monthly Mission Review LAT Flight Software Status October 29, 2007 Jana Thayer Stanford Linear Accelerator Center Gamma-ray.
GLAST Large Area Telescope Instrument Flight Software F2F Meeting March 17, 2005 Jeff Fisher FSW Manager Stanford Linear Accelerator Center Gamma-ray Large.
GLAST LAT ProjectEngineering Meeting, December 3, GLAST Large Area Telescope: Engineering Meeting December 10, 2002 Lowell A. Klaisner Stanford.
GLAST LAT Project May 25, 2006: Pre-Environmental Test Review Presentation 6 of 12 LAT Test Results 1 GLAST Large Area Telescope Pre-Environmental Test.
GLAST LAT Instrument GLAST Monthly Mission Review July 12, 2007 N. Johnson, NRL 1 Monthly Mission Review Project Status Overview July 12, 2007 Neil Johnson.
GLAST LAT Project Technical/Cost/Schedule Review 03/31/ Integration and Test 1 GLAST Large Area Telescope: I & T Input to Monthly Technical/Cost/Schedule.
GLAST LAT Project Technical/Cost/Schedule Review 09/01/ Integration and Test 1 GLAST Large Area Telescope: I & T Input to Monthly Technical/Cost/Schedule.
GLAST LAT ProjectNovember 3, 2005 I&T Phase 0 IRR/TRR 1 GLAST Large Area Telescope: Integration and Test Phase 0 IRR/TRR November 3-4, 2005 Introduction.
Chapter 10: Monitoring and Controlling Change
GLAST LAT Project Technical/Cost/Schedule Review 03/30/ Integration and Test 1 GLAST Large Area Telescope: I & T Input to Monthly Technical/Cost/Schedule.
GLAST LAT ProjectJune Cost/Schedule Status Meeting 07/23/ Integration and Test 1 GLAST Large Area Telescope: I & T Input to June Cost/Schedule.
GLAST LAT Instrument GLAST Monthly Mission Review July 12, 2007 N. Johnson, NRL 1 Monthly Mission Review TVAC at NRL? Status July 12, 2007 Neil Johnson.
GLAST LAT ProjectDOE/NASA Status Review, March 30 & 31, 2004 Integration and Test 1 Integration, Facilities, Configuration, and Test (IFCT) Flow Procedure.
ISOC Peer Review - March 2, 2004 Section GLAST Large Area Telescope ISOC Peer Review Test Bed Terry Schalk GLAST Flight Software
GLAST LAT ProjectLAT Planning Meeting July 17 th and 18 th Integration and Test 1 GLAST Large Area Telescope: I & T Input to LAT Planning Meeting.
GLAST LAT Project Oct 5, GLAST Large Area Telescope Systems Engineering Test Status, NCRs and Verification Status Pat Hascall Systems Engineering.
GLAST LAT ProjectNovember 18, 2004 I&T Two Tower IRR 1 GLAST Large Area Telescope: Integration and Test One and Two Tower Integration Readiness Review.
1 ev14a Interactive Session 4 u Tuesday, July 17 7pm to 10pm u Build a sqa plan for the dental office software u Assume a 3-person, development team, a.
GLAST Large Area Telescope LAT Flight Software System Checkout TRR Current Status Sergio Maldonado FSW Test Team Lead Stanford Linear Accelerator Center.
GLAST LAT ProjectMonthly Status Review - ISOC, 1 September GLAST Large Area Telescope WBS 4.1.B Instrument Science Operations Center Monthly Status.
1. Earned Value Analysis (EVA) Earned value is a measure of progress enables us to assess the “percent of completeness” of a project using quantitative.
GLAST Large Area Telescope:
GLAST LAT ProjectJune 30, 2004 Monthly Review Rev. C 1 GLAST Large Area Telescope: Lowell A. Klaisner Stanford Linear Accelerator Center Project Manager.
EARNED VALUE MANAGEMENT (EVM)
10/19/ :26 AM 1 Project Cost Control. 10/19/ :26 AM 2  Controlling involves making sure that the results achieved are in line with the planned.
Earned Value SOS section Sp8Jan24ev3. Earned Value Analysis One approach to measuring progress in a software project is to calculate how much.
Chapter 9 Project Development. What to manager Client experience  Clients are very important  Happy or not is largely dependent on their expectations.
GLAST LAT ProjectCDR/CD3 Review May 12-16, 2003 Document: LAT-PR-01967Section XX 1 GLAST Large Area Telescope: LAT System Engineering WBS Dick Horn.
GLAST LAT ProjectFace to Face Managers Meeting 04/14/ Integration and Test 1 GLAST Large Area Telescope: I & T Input to Face to Face Managers.
GLAST LAT Project – Cost and Schedule ReviewJanuary 27, 2004 AntiCoincidence Detector 1 GLAST Large Area Telescope: Cost/Schedule Review January 27, 2005.
GLAST LAT Project Technical/Cost/Schedule Review 06/30/ Integration and Test 1 GLAST Large Area Telescope: I & T Input to Monthly Technical/Cost/Schedule.
GLAST LAT ProjectApril 2005 Project Status Overview May 24, April, 2005 Lowell Klaisner LAT Project Manager Rev. - LAT Project Status Overview Gamma-ray.
GLAST LAT Project Technical/Cost/Schedule Review 04/26/ Integration and Test 1 GLAST Large Area Telescope: I & T Input to Monthly Technical/Cost/Schedule.
GLAST LAT ProjectMonthly Review, May 24, DAQ & FSWV1 1 GLAST Large Area Telescope: Electronics, Data Acquisition & Flight Software W.B.S
GLAST LAT ProjectLAT Muons at NRL 28 Feb 2006 J. Eric Grove Naval Research Lab Washington DC LAT Muon Data Taking During Environmental Test at NRL J. Eric.
GLAST LAT Project LAT System Engineering 1 GLAST Large Area Telescope: LAT System Engineering Pat Hascall SLAC System Engineering Manager
GLAST LAT ProjectMonthly Review, June 30, DAQ & FSWV2 1 GLAST Large Area Telescope: Electronics, Data Acquisition & Flight Software W.B.S
GLAST LAT ProjectMonthly Status Review – Nov 3, 2005 GLAST Large Area Telescope: Performance & Safety Assurance Joseph Cullinan SLAC Performance & Safety.
Introduction To Earned Value November 14, Definition Earned Value is a method for measuring project performance. It compares the amount of work.
GLAST LAT ProjectDOE/NASA Baseline-Preliminary Design Review, January 8, 2002 Document: #1 GLAST Large Area Telescope: I&T Overview Elliott D. Bloom Stanford.
1 Earned value analysis Planned value (PV) or Budgeted cost of work scheduled (BCWS) – original estimate of the effort/cost to complete a task (compare.
Schedule Control (Earned Value)
GLAST LAT ProjectSeptember 15, 2006: Pre-Shipment Review Project Overview 1 Presentation 1 of 12 GLAST Large Area Telescope: LAT Pre-Shipment Review W.
Project Monitoring
GLAST Large Area Telescope:
GLAST Large Area Telescope
An Introduction to Earned Value Performance Measurement
GLAST Large Area Telescope Instrument Science Operations Center
EPU load – same as SIU load except…
Earned Value Measures Planned Value (PV) Earned Value (EV)
فرآيند كنترل پروژه.
LAT Test Results GLAST Large Area Telescope LAT Pre-Shipment Review
GLAST Large Area Telescope:
GLAST Large Area Telescope: I&T Test Readiness Review
March ’05 Face to Face Meeting Introduction
GLAST Large Area Telescope
Overview Cost to Complete
GLAST Large Area Telescope: I&T Test Readiness Review
Presentation transcript:

GLAST LAT ProjectMonthly Status Meeting Jan 26, Project Status January 26, 2006 Gamma-ray Large Area Space Telescope Lowell A. Klaisner Project Manager

GLAST LAT ProjectMonthly Status Meeting Jan 26, Project Status (1of2) Completed Phase 0 testing –Scheduled 140 hours of testing actually took 414 hours Longest single NCR resolution was tower 8 asserting busy unexpectedly – now resolved There were bugs in scripts and databases –Learned a lot about the instrument, scripts, and calibration strategies –Complete on last month’s schedule by working 24/7 Currently, commissioning and verifying the EGSE and associated software –Power Rack –Control Rack (VSC) –Mobile Computing Rack Then commission the SIUs and EPUs We are ready to begin Phase 1 as soon as this is completed –FSW, LICOS, scripts are available for the initial Phase 1 testing –Concurrent development will be needed to complete Phase 1

GLAST LAT ProjectMonthly Status Meeting Jan 26, Project Status (2of2) Open issues –EPU Programming –LICOS Script development –Spare RAD 750 failure Flight Software –6.1 loaded on SIUs – Initial operation –6.2 January 27 – Science runs, muon data –6.3 February 10 – Run for the record sans GBM and GRB –7.0 adds GBM and GRB interfaces Priorities 1.Operation on 1 SIU with FSW, LICOS, and test EGSE 2.Operation with full complement of SIUs and EPUs 3.Run for the record 4.Clean up and ship to NRL

GLAST LAT ProjectMonthly Status Meeting Jan 26, System Test Flow FSW Release FSW Checkout FQT – Testbed Install last 4 TWRs, 16 TWR CPT Install ACD, GASU, PDU LATTE 4 LAT CPT, SVAC Install flt SIU / EPUs, FSW Install LICOS System Commissioning MOOT / MOOD Config Mgmt 10/25 10/17 11/29 2/9/06 Perf & Ops Test Plan 2/23/06 Install Cross-LAT Plate/LPT LAT System Test 3/12/06 Light-tight tests Pre Ship Review/ Shipment 3/15/06 VSC Full Functionality Phase 1 Phase 2 Phase 0 3/20/06 FSW Updates/ FQT – Testbed SIIS Verification 3/15/06 3/9/06 1/20

GLAST LAT ProjectMonthly Status Meeting Jan 26, Phase 0 testing

GLAST LAT ProjectMonthly Status Meeting Jan 26, Data Acquisition System SIUSIU GASU GASU PDUPDU [EPU] [EPU] [EPU]

GLAST LAT ProjectMonthly Status Meeting Jan 26, Towers with ACD

GLAST LAT ProjectMonthly Status Meeting Jan 26, Level 1-2 Milestone List DOE ESSAB review for CD-4 is scheduled for February 2, 2006

GLAST LAT ProjectMonthly Status Meeting Jan 26, Level 3 Milestone Count

GLAST LAT ProjectMonthly Status Meeting Jan 26, FTE Report (DOE/NASA-funded only)

GLAST LAT ProjectMonthly Status Meeting Jan 26, Cost Report

GLAST LAT ProjectMonthly Status Meeting Jan 26, Performance Analysis LEGEND BAC: Budget At CompleteSV $: Schedule Variance = BCWP - BCWS% BCWS: Percent Scheduled = BCWS/BAC BCWS: Budgetd Cost of Work Scheduled (to date)CV $: Cost Variance = BCWP - ACWP% BCWP: Percent Complete = BCWP/BAC BCWP: Budgeted Cost of Work Performed (to date)SPI: Schedule Performance Index = BCWP/BCWS% ACWP: Percent Spent = ACWP/BAC ACWP: Actual Cost of Work Performed (to date)CPI: Cost Performance Index = BCWP/ACWP Cpi_Fcst: CPI (to date) EAC Forecast = BAC / CPI CpiSpi_Fcst: Combination CPI and SPI EAC Forecast = ACWP + (BAC - BCWP) / (CPI *SPI) Worse than.85Between.95 and 1.10 Between.85 and.95Better than 1.10 SPI and CPI Change Thresholds

GLAST LAT ProjectMonthly Status Meeting Jan 26, Variance Analysis Feb05 Current Month

GLAST LAT ProjectMonthly Status Meeting Jan 26, Liens List

GLAST LAT ProjectMonthly Status Meeting Jan 26, Backup Material

GLAST LAT ProjectMonthly Status Meeting Jan 26, CPR Level 3

GLAST LAT ProjectMonthly Status Meeting Jan 26, Level 3 Milestones Completed in December 2005

GLAST LAT ProjectMonthly Status Meeting Jan 26, Level 3 Milestones Completed in January 2005 None Completed

GLAST LAT ProjectMonthly Status Meeting Jan 26, Budget, Cost, Funding, Performance