FAC, 10/12/06 D. Schultz 1 e-Beams Systems Update Linac Injector Undulator Production MMF commissioning ARR David Schultz.

Slides:



Advertisements
Similar presentations
Kathleen Ratcliffe BC2/Linac Installation April 16, BC2 / Linac Installation Coordination Kathleen.
Advertisements

Rodd Pope, SLAC Undulator System April 16-17, 2007 FAC Meeting 1 Undulator System Assembly, Installation, and Integration.
Richard M. Boyce FAC Review – Accelerator Installation October 29-31, Installation – Accelerator Systems Installation Planning.
FAC review, 10/27 D. Schultz 1 e-Beams System Update Injector System Installation has started. Linac System Preparing for ’06 installation. Controls System.
FAC, 4/20/06 D. Schultz 1 e-Beams System Update Linac System Preparing for downtime installation. Injector System Installation has started. Undulator System.
Marion M. White Undulator System 07 April 2005 LCLSLCLSLCLSLCLS Undulator System Tests Marion M. White ANL-ASD-LCLS.
Paul Emma LCLS FAC April 16, Initial Experience with Injector Commissioning P. Emma, et al. Facilities Advisory Committee.
FAC 4/20/06 D. Schultz 1 The SAD and ARR for Commissioning The Status of the SAD Being written as a part of the SLAC Linac SAD The Status of the ARR Design.
Apr. 16, 2007 Undulator Breakout Dean R. Walters 1 Vacuum System Undulator Vacuum System Dean R. Walters Soon-Hong Lee, James Bailey, James.
John N. Galayda LCLS FAC 20 April Linac Coherent Light Source Overview and Charge Facility Advisory Committee John.
Jose Chan FAC - BC2/Linac Installation Status & 4/16/07 1 BC2/Linac Installation Status & Schedule Jose Chan.
Geoff Pile FAC Review - Undulator 17 June 2008 LCLS Undulator System Status and Schedule Geoff Pile.
David H. Dowell Injector RF Design November 3, LCLS Injector RF Gun: Design, Fabrication & Tuning Plans D. H. Dowell,
Eric Bong LCLS FAC Injector-Linac October 27, 2005 Injector Design / Diagnostics / Gun & Linac RF Design E. Bong LCLS FAC.
Mark Reichanadter LCLS FAC April 20-21, 2006 Meeting of the LCLS Facilities Advisory Committee LCLS Project Management M.
FAC, 4/16/07 D. Schultz 1 e-Beams Systems Update People ARR Linac Installation Undulator Production MMF Operations David Schultz.
John N. Galayda LCLS FAC October Linac Coherent Light Source Overview and Charge Facility Advisory Committee.
D. Schultz FAC 6/17/08 1 e-Beams Systems Update People Progress the last review LTU and Dump Installation Status Undulator.
Stephen Milton Undulator System 20 April, 2006 LCLS Undulator System Update S. Milton, ANL FAC, April 20 th, 2006.
Hamid Shoaee LCLS FAC Controls June 17, LCLS Control System Personnel Linac & BC2 Controls progress LTU, Dump Controls.
Bob Lill LCLS FAC June 16-18, 2008 RF BPM Status and Production Test Results.
Bill White Laser Installation and April 20, Laser Installation and Commissioning April 20, 2006 Procedures.
Eric Bong LCLS FAC Injector-Linac System October 27, 2005 Injector –Linac System Overview E. Bong LCLS FAC October 27, 2005.
David H. Dowell Injector April 29-30, 2004 LCLS Injector Overview D. H. Dowell, SLAC FAC Review April 29-30, 2004 Injector.
D Walters Undulator System June 17, Undulator System Components Status Dean Walters.
Hamid Shoaee LCLS FAC Review – October Control System Overview Hamid Shoaee Controls System Manager Injector control system commissioning & Support.
Geoff Pile LCLS Und. System FAC 29 th, 30 th & 31 st October 2007 LCLS Undulator System Update FAC Review October 29 th (30 th.
Geoff Pile LCLS Und. System Fabrication FAC 29 th, 30 th & 31 st October 2007 LCLS Undulator System Fabrication Schedule FAC.
C.E. Rago Inj/Lin Design & 4_20_06 1 Injector / Linac Design & Fabrication C.E. Rago FAC Review 04_20_06.
David H. Dowell Injector Physics/Diagnostics/Gun&L0 RF April 29-30, 2004 Injector Physics / Diagnostics / Gun & L0 Linac.
Hamid Shoaee Accelerator Readiness Dec. 2, ‘08 SLAC National Accelerator Laboratory Controls Department LCLS Maintenance.
FAC, 10/12/06 D. Schultz 1 Readiness for 2007 Startup Linac Injector Controls ARR David Schultz.
ILCTA_NML Progress at Fermilab Jerry Leibfritz September 10, 2007.
Injector Accelerator Readiness Review, 10/31/06 Henrik Loos 1 Beam Losses During LCLS Injector Phase-1 Operation Scope of phase 1 operation Operating modes.
1 BROOKHAVEN SCIENCE ASSOCIATES Preparations for Linac Commissioning Ray Fliller, Associate Physicist 8 th ASAC meeting for NSLS-II Project May 10-11,
Stephen Schuh Vacuum Controls SCR and 16 November 2005 Vacuum Controls System Concept Review and Preliminary Design Review.
HINS 6-Cavity Test 3 Month Plan Jan 12, Current Schedule 2-3 day shutdown scheduled to start Jan 18 (Wednesday) to upgrade BPM system and reinstall.
1 BROOKHAVEN SCIENCE ASSOCIATES ASD Procurements Gregory Fries Liaison/Manufacturing Engineer NSLS-II ASAC October 22-23, 2009.
D Walters Undulator Systems – BFW April 30, 2008 Production Status of the Quad Spool J Morgan – Engineer Bellows Module Soon-Hong.
ASTA Accelerator Directorate Review Project Plan and ES&H Carsten Hast May 20, 2014.
Hamid Shoaee Control LCLS ARR Oct 31, LCLS Accelerator Readiness Review Control System for Injector Commissioning.
Patrick’s Updates - 8/30/11 (one slide for each of the following) 1.XTCAV Project 2.ASTA Gun Test Facility Instrumentation & Controls 3.Fast wire scanner.
Proton PMG September 3 rd 2015 Cons Gattuso AD Shutdown Manager.
ILCTA_NML Progress at Fermilab Jerry Leibfritz August 16, 2007.
Drive-Laser Commissioning Status and Plans
Injector Performance Requirements Conventional Facilities Update
LCLS Injector: Introduction D. H
Injector –Linac Status & Schedule E. Bong LCLS FAC October 12, 2006
e-Beams Systems Update
Linac/BC1 Commissioning P
Electron Beam Systems ETC and Methodology
Injector / Linac Installation Current Status
Undulator System Components Status Dean Walters
INJECTOR (WBS 1.2.1) Jym Clendenin, SLAC April 23, 2002
LCLS Undulator System Status and Schedule
Maximum Credible Beam Event Paul Emma et al
LCLS Undulator System Production Management
LCLS Personnel Protection System and Beam Containment System
E-Beams Systems Manager
LCLS Undulator System Status and Schedule
LCLS Injector System Overview D. H
Control System Overview Hamid Shoaee LCLS Control System Manager
Electron Beam Systems ETC and Methodology
Injector/Linac Design Status C. E
LCLS e- Beams System Overview
Vacuum Controls Stephen Schuh Tom Porter 25 October 2006
e-Beams Systems Update
LINAC System Engineering / Design Status C.E. Rago
LCLS e- Beams Systems Manager
Control System Overview Hamid Shoaee LCLS Control System Manager
Presentation transcript:

FAC, 10/12/06 D. Schultz 1 e-Beams Systems Update Linac Injector Undulator Production MMF commissioning ARR David Schultz

FAC, 10/12/06 D. Schultz 2 LCLS Diagnostics and Controls Physicist Joe Frisch Joining Paul Emma on the LCLS Physics and Commissioning Team Brings extensive experience with diagnostics, RFBPMs, bunch length monitors, timing systems, laser systems, …

FAC, 10/12/06 D. Schultz Installation BC1 BLM LX L1 Ins/SAB Wall Laser stopper Sector 20 Sector 21

FAC, 10/12/06 D. Schultz 4 Linac Status Downtime installation work is underway Removal of accelerator structures is done. Next few weeks - installing Wall region components (this week) L1 and LX accelerator regions (this week) BC1 supports (next week) Insertion region installation 11/6 (week 12) Table due 10/16 BLM region installation 11/6 (week 12)

FAC, 10/12/06 D. Schultz 5 Linac Accelerator Section Removal Before After Making room for the Insertion, L-1 and L-X regions

FAC, 10/12/06 D. Schultz 6 The X-band accelerator section Klystron, modulator being power tested prior to installation.

FAC, 10/12/06 D. Schultz 7 Inj/Linac quad magnets ready for installation

FAC, 10/12/06 D. Schultz 8 Diagnostic devices ready to install. Wire scanners and profile monitors

FAC, 10/12/06 D. Schultz 9 Linac Downtime Issues BPM feed-through welding, many leak. Leak at ceramic, need UHV QC before welding Late components: BC1 Instrument package BLM 11 (BLM 12 will be in) Toroids (in several locations) Vacuum chambers in insertion region. Spool pieces are being fabricated to be installed temporarily. Time will be needed to install these components as they become available.

FAC, 10/12/06 D. Schultz 10 LCLS Insertion region Critical vacuum chambers which may be late. Linac integrity needed for ESA program in Jan. Linac beam LCLS Injection

FAC, 10/12/06 D. Schultz 11 Injector Installation Status Injector installation has taken second priority to Linac installation. Injector vault: Floor and cable plant installed Injector beamline: Accelerator structures, L0a ready, L0b to final bake RF waveguide needs to go through bake Gun is in hot test, RF on 10/5 2 nd gun is in brazing then final cold-test, final braze. Support stands are in the vault ready except for the GTL table

FAC, 10/12/06 D. Schultz 12 The LCLS Drive Laser Drive Laser installed, operating LSS installed in laser room Now working on temporal shaping, Streak camera Cross correlator

FAC, 10/12/06 D. Schultz 13 The Injector Vault Cable plant, vault ready for beamline components.

FAC, 10/12/06 D. Schultz 14 L0A on the MMF CMM

FAC, 10/12/06 D. Schultz 15 The LCLS photocathode electron gun

FAC, 10/12/06 D. Schultz 16 Injector Installation Issues Water system needs to be installed, installation reqs. out, BPM feed-through welding, toroids Late: The GTL stand released to purchasing. Estimate it will be here 11/16 for installation 11/20. Laser table installation begins 11/27 The Gun will be ready by then, needed later. GTL is late, now moving to machining. (next slide) Working to advance the schedule. What is competing? What can be sent out? Critical path.

FAC, 10/12/06 D. Schultz 17 Gun-to-Linac area Gun Laser table Spectrometer L0a GTL uv

FAC, 10/12/06 D. Schultz 18 Controls Magnet power supplies, vacuum controls, installed in racks and tested. Racks now being installed. Ethernet backbone to the Computer Center installed and connected. Wire scanners controls tested. Linac cable plant phase 2 installation is underway. Coordinating hardware installation schedule now with Controls checkout.

FAC, 10/12/06 D. Schultz 19 Magnets power racks assembled, tested, prior to installation

FAC, 10/12/06 D. Schultz 20 Vacuum system racks assembled, tested, prior to installation

FAC, 10/12/06 D. Schultz 21 Controls - PPS Personnel Protection System is in the review process with the SLAC RSC. PLC design conditionally approved! The Committee wants to see the certification procedure. Beam loss and shielding design approved. Beam Containment System, LCLS FDR 10/6, RSC review 10/12.

FAC, 10/12/06 D. Schultz 22 Undulator Systems Design Quadrupole Order placed, vendor designs, 1 st article 2/07 Fixed Support/Mover Final Design Review - September 13/14 Go ahead given for production. Beam Finder Wire Final Design Review - September 20, 2006 Go ahead given for production of BFW, except wire card. RF Beam Position Monitor Final Design Review - October 4 Testing program has been interrupted by RF gun failure. Vacuum Chamber Final Design Review - September 27/28 42" chamber welded, machined, to be coated. 2 other prototypes in hand for QC, permeability measurements. Plan D design effort initiated at SLAC.

FAC, 10/12/06 D. Schultz 23 Undulator vacuum chamber 4-Weld Prototype Issues: flatness, permeability, vacuum, Al coating, surface finish Vacuum Chamber Design Review - September 27/28

FAC, 10/12/06 D. Schultz 24 MMF Status Measurement benches installed and commissioned. CMM installed and in use. Quad measurement station operational. Eight finished undulators are here at SLAC. Six to eight more to be shipped to SLAC by October 20 th Issues: Air cond. mixing valve (new) failed. Now repaired. New breaker panel wiring needed to be worked on. Compressed air system does not meet spec. Looking for a work-around. Need to move to production fine-tuning.

FAC, 10/12/06 D. Schultz 25 Six undulator magnets in crates awaiting tuning at the MMF. Six to eight more to arrive at SLAC by October 20 th. Undulator magnets at the MMF

FAC, 10/12/06 D. Schultz 26 Injector Accelerator Readiness Review Safety Assessment Document Draft LCLS SAD for Injector Commissioning under internal review. Operating procedures are being written with AD Ops. Commissioning LCLS Commissioning Workshop October 9-11 Includes a Commissioning Readiness Review. Accelerator Readiness Review (ARR) LCLS ARR for Injector Commissioning scheduled for October 31st. Committee members, speakers on board.

FAC, 10/12/06 D. Schultz 27 The downtime schedule is very tight. We got off to a good start. Not all parts are in hand. Injector installation will delay commissioning. Controls checkout (last) is at risk. The Undulator vacuum chamber is still in the design/prototype stage. On the critical path. Adding engineering resources from SLAC. The MMF is late and needs attention. Issues