MINER A Director’s CD-3b Review 11 June 2007 Kevin McFarland University of Rochester 1MINERvA WBS 1,2,4: Scintillator and Fiber Fiber Milestones: WLS Fiber.

Slides:



Advertisements
Similar presentations
Car Hoist.
Advertisements

US CMS DOE/NSF Review: May 8-10, US CMS Cost & Schedule Mark Reichanadter US CMS Project Engineer DOE/NSF Review 8 May 2001.
TRD Collaboration Meeting GSI Clemens Adler TRD Chamber production issues General Issues, Planning and Hd Status.
MINER A NuMI MINER A Director’s Review 10 January 2005 H. Budd Univ. of Rochester Optical Cables and Scintillator Extrusions 10 January MINERvA.
WLS Fiber Pigtails Howard Budd University of Rochester Dec T2K Collaboration Meeting.
02/10/2004 Minimum Bias Trigger Scintillator Counters (MBTS) for early ATLAS running M.Nessi ATLAS week, Freiburg.
Scintillating Fiber and Ribbon Production Update Alan Bross MICE Tracker Phone Meeting September 8, 2006.
Polishing the Ferrules Howard Budd Sep Polishing Epoxy on the Ferrule We glued fibers in the 10 ferrules that Dave Warner gave us One problem.
1 Prototyping Megaton-Scale  Detectors Jason Trevor DOE Review July 25, 2007 Developing a New Lower-Cost Scintillator Design.
CPR2 Optical Cables Joey Huston Michigan State University …taking optical signals from edge of CPR/crack detectors to PMT boxes mounted on back of wedges.
BPM Upgrade Presented by: Nadine Kurita Contributors: S. Smith, S. Ecklund, J. Sebek, D. Martin, R. Hettel, R. Johnson, N. Reeck, M. Kosovsky, D. Arnett.
1 Start at Estimating Cable Labor Howard Budd University of Rochester Rochester Meeting Nov
Clear Fiber and Wave Guide Fab. Makoto YOSHIDA (Osaka Univ.) July MICE FT
EMCAL: project update - Italy - LNF - Frascati Fixture production Module assembly (proto) WLS fibers processing Lead procurement (proto) CT- Catania APD.
Fiber Attenuation Length Test for MINERvA Jaewon Park University of Rochester Jupiter/MINERvA Meeting, Sep 10, 2005.
Cosmic Ray Analysis 1M.Ellis - CM23 - Harbin - 15th January 2009  Not enough time to go into detail, so just a quick summary of the status since CM22:
1 Preliminary Cable Labor Estimate Howard Budd University of Rochester Rochester Meeting Dec
Diamonds & R&D on Pigtails Howard Budd Sep
Polishing the Ferrules Howard Budd Aug Visit We visited the place where the polisher is made We got 2 collets which the ferrules fit well in.
Polishing the Ferrules Howard Budd Sep Polishing Epoxy on the Ferrule We glued fibers in the 10 ferrules that Dave Warner gave us One problem.
Lab5 Production Status: Optics and RBX integration Pawel de Barbaro U. of Rochester.
Status of CLAS12 PCAL project
Project Planning Day 2 An Old Adage: Fail to Plan... and You Plan to Fail!
Service Bulletin 161 SUBJECT: Upgrade to current production level UNITS:D27105 DATE CODE RANGE: All units up to date code to be checked ISSUED.
Update on the Time-of-Flight and Position Resolution Measurements in the Proposed Detectors and Cost Estimates – August 2014 WILLIAM TIREMAN NORTHERN MICHIGAN.
1 Product Reliability Chris Nabavi BSc SMIEEE © 2006 PCE Systems Ltd.
CMS Tracker Week, CERN, July July 2003Tracker Week - Module ProductionSalvatore Costa - Catania Executive summary from Bonding WG Meeting.
The MINER A Operations Report All Experimenters Meeting Howard Budd, University of Rochester July 8, 2013.
Waveguide for Station 5 M. Yoshida (Osaka Univ.).
Flat Saw Training. Flat Saw Sizes –Low Horsepower Blade diameters range from 8” (200mm) to 18” (450mm) Power ranges from 4 to 25 horsepower.
The MINER A Operations Report All Experimenters Meeting Howard Budd, University of Rochester Aug 5, 2013.
1 MICE Tracking Detectors Malcolm Ellis NFMCC Meeting 12 th March 2006.
Tracker QA Paul Kyberd Quality Assurance A status report: A procedure for ensuring the quality of the finished tracker has been designed following our.
Tariq J. Solaija, NCP Forward RPC EDR, Tariq Solaija Forward RPC EDR The Standard RPC for low  regions Tariq J. Solaija National Centre for.
G.Barber KEK Test Beam Update, Berkeley 9 Feb KEK Test Beam – Tracker Progress Contents:- Station Space Frame Light Guide Map Station Connectors.
Systematic Study of Strip/Block Scintillators: Progress Report E.P. Jacosalem, S. Iba, N. Nakajima, H. Ono, A.L. Sanchez, A.M. Bacala & H. Miyata ILCCAL.
Tracker Summary Alan Bross MICE CM October 10, 2007.
MINERvA Mini-Review Debbie Harris Jeff Nelson Kevin McFarland Jeff’s slides version 1.
ECAL LED monitoring system upgrade Pavel Shatalov ITEP, Moscow, Russia Yuri Guz IHEP Protvino, Russia.
U. Of Rochester DOE Review, July 15-16, 2002: P. de Barbaro, CMS1 CMS Project at UR Pawel de Barbaro University of Rochester DoE Review July 15-16, 2002.
GIST 19: GGSPS status Status of GGSPS development and operations Andy Smith GGSPS software project manager.
Status of cosmic-ray test of the SciFi prototype and SciFi software in G4MICE M. Yoshida (Osaka Univ.)
Structure Update Installation & Building Update Revisions Outlined Costs Revisited (since given to Gina) Jeff Nelson Fermilab.
Improvements and changes for BOB SNIDEMILLER, SENIOR DIRECTOR OF TRANSPORATION TRANSPORTATION UPDATE.
Update on the Triple GEM Detectors for Muon Tomography K. Gnanvo, M. Hohlmann, L. Grasso, A. Quintero Florida Institute of Technology, Melbourne, FL.
VVS Prototype Construction at Fermilab Erik Ramberg 26 February,2002 Design issues for VVS Details of VVS prototype design Schedule and Budget Testing.
Response to TAC8 and Annual Review Recommendations John Haines Head of Target Division April 2, 2014.
Hybrid panel heated plate study Currently the curing of the ASIC glue for the hybrid panels are done at room temperature. This is a study to determine.
The MINER A Operations Report All Experimenters Meeting Howard Budd, University of Rochester June 24, 2013.
MINER A Operations Report All Experimenters’ Meeting Steve Hahn, FNAL July 1, 2013.
G.Barber/Peter Cooke: Mechanical Design Update Imperial 22 July Mechanical Update for Tracker workshop Contents:- New Station Layout Light Guide.
G. Carboni - Muon Meeting – Muon Meeting 12/ Agenda IntroductionGiovanni (30’) GEM and TDR AddendumWalter (20’) Update on M1 ratesAlessia.
ASTA Accelerator Directorate Review Project Plan and ES&H Carsten Hast May 20, 2014.
Project Setup and Execution For PMPlan Enterprise Presented by AlNik Solutions Copyright ©
PHENIX Vertex Detector with Conventional Strip Sensors Abhay Deshpande Stony Brook University.
9/12/2003Ivan Hruska1 First box prototype –Box design in July ‘03 –Box produced during August ’03 Tested last week in few fingers Small changes necessary.
CMS Upgrade Workshop, FNAL, Oct 28-30, O.Prokofiev Update ME4/2 Chambers and Tooling A construction of new ME4/2 prototype at CERN Factory tooling,
Trigger efficicency on double tracks Trigger efficiency on isolated tracks Final results of the Trigger Test on the 25ns beam Bx NUMBER Fraction of Triggers.
Preparations to Install the HBD for Run 6 Craig Woody BNL PHENIX Weekly Meeting January 26, 2006.
MINER A at the Triple Point: Three Phases at once Deborah Harris AEM August 31, 2009.
The MINER A Operations Report All Experimenters Meeting Howard Budd, University of Rochester Oct 14, 2013.
MUSE NSF Review March 24, MUSE Project Management Ronald Ransome Rutgers The State University of New Jersey For the MUSE Collaboration.
1 Fermi National Accelerator Laboratory EXTRUDED SCINTILLATOR STATUS Anna Pla-Dalmau April 9, 2010.
HADES collaboration meeting XXX, Lisbon, 7-10 October, 2015,
Jim Fast Pacific Northwest National Laboratory
University of Wisconsin
Scintillating Fiber/Clear Fiber QA and Ribbon Production
Design of the He and HB ODU
IFR detector mechanics
Guidelines for Fiber Optic Design and Installation
Presentation transcript:

MINER A Director’s CD-3b Review 11 June 2007 Kevin McFarland University of Rochester 1MINERvA WBS 1,2,4: Scintillator and Fiber Fiber Milestones: WLS Fiber for Tracking Proto. Quick summary –All Tracking prototype WLS fiber arrived in 2 shipments 60% shipment & 40% shipment 2 shipments due to availability of funds –60% shipment shipped in July –The 40% shipment is about ½ finished at the shutdown 40% shipment ready to ship about 1 month after shutdown finishes –Shutdown finishes Oct 12, but PPD will try to get crew back earlier very large loss of schedule contingency –Not expected to impact WBS 3 and downstream schedules –Have two functioning QC tests both show little variation n.b., these two techniques don’t define reflectivity in the same way, but both are sensitive to mirror variations

MINER A Director’s CD-3b Review 11 June 2007 Kevin McFarland University of Rochester 2MINERvA WBS 1,2,4: Scintillator and Fiber WLS Production We expect to start WLS production mirroring in mid January 2008

MINER A Director’s CD-3b Review 11 June 2007 Kevin McFarland University of Rochester 3MINERvA WBS 1,2,4: Scintillator and Fiber Upgrades since Dir Rev We have added 2 new technicians –One went from part time to full time in July –One starting ½ time in Aug & Sep (shared with CMS ) and full time in Oct –Both of these technicians are being trained for ODU production We have doubled the number of gluing stations from 60 to 120 We have more than doubled our table space for production We have identified the table space for boot production

MINER A Director’s CD-3b Review 11 June 2007 Kevin McFarland University of Rochester 4MINERvA WBS 1,2,4: Scintillator and Fiber Fiber Milestones: ODU for Tracking Proto. Quick summary –ODUs approximately 60% complete –some Q/C issues identified and addressed –ODU quantities required were updated by downstream factories

MINER A Director’s CD-3b Review 11 June 2007 Kevin McFarland University of Rochester 5MINERvA WBS 1,2,4: Scintillator and Fiber ODUs For tracking prototype we are supposed to ship 543 ODUs 335 ODUs have been shipped –Pass optical QC & fit test Another 120 ODUs have passed the optical QC –We are modifying the fit test and are waiting for test hardware from Lab 7 Another 200 are in various stages of production Optical QC test –Optical QC requires each fiber in a ODU must have its value > 90% of the transmission mean for that channel –5.7% failed the optical QC –In addition… Another 2.0% of ODUs failed because we purposely pushed the diamond to its limit before relapping/replacing to test its lifetime 7.5% failed to clip into box because of epoxy on back end of ferrule. –We noticed this problem after producing 300 ODUs –In the last 100 ODUs the problem did not occur –In the future we think < 1% of the ODUs will fail this test. The failure rate is slightly higher than before as we bring on these new people

MINER A Director’s CD-3b Review 11 June 2007 Kevin McFarland University of Rochester 6MINERvA WBS 1,2,4: Scintillator and Fiber Tracking Prototype ODUs Estimate of failures for future production –5% optical + 1% epoxy failure, if no other problems

MINER A Director’s CD-3b Review 11 June 2007 Kevin McFarland University of Rochester 7MINERvA WBS 1,2,4: Scintillator and Fiber Fiber Milestones: Cable Production In a slide… –Work on cable mold significantly delayed conscious choice because of large float –Cable production problems identified change in ferrule length implies needed mold modifications problems with pouring process and ES&H impact of the material (polyurethane with Al(OH) 3 fire retardant) material flow into and wear on mold ejection parts –Remediation new procedure removes need for ejector in the process of completing new hardware estimated startup in 4-6 weeks

MINER A Director’s CD-3b Review 11 June 2007 Kevin McFarland University of Rochester 8MINERvA WBS 1,2,4: Scintillator and Fiber Optical Cable R&D New Mold –Use sliding clamp to press connector against mold to prevent mold material from flowing to front of connector The Alumilite polyurethane did not flow into around the connector to the polished fibers as it was doing with the old mold –No extraction pins which got gummed up in previous mold Use straps put in the boot Mold cheaper by more than a factor of 2 –We have successfully made boots with new mold and our original molding material, Alumilite polyurethane –Problem with mold, connectors fit too tight in the mold right now material will have to be removed in the mold about 1 week of work.

MINER A Director’s CD-3b Review 11 June 2007 Kevin McFarland University of Rochester 9MINERvA WBS 1,2,4: Scintillator and Fiber Mold Material But the Alumilite is not ideal –It is fluid than we want –Will require a chemical hood, restricts how we do production We have identified 2 epoxies which look very promising to replace the Alumilite, but we have not finished the R&D –Both epoxies packaged for 2 component mixing guns –Both have about the right viscosity Heigl MP5405bk – 1 st choice –Hardens in 15 minutes, no chemical hood needed –Successfully & easily put boots on 5 cables with original mold –Problem, Its black material transmits red light Heigl will work with us to fix this problem.

MINER A Director’s CD-3b Review 11 June 2007 Kevin McFarland University of Rochester 10MINERvA WBS 1,2,4: Scintillator and Fiber Mold Material Resinlab EP1046fg –Can pull boot out after 1.5 hours, not ideal, but good enough to finish project –Epoxy is fine, other than the setting time None of these 3 products are fire retardant –ES&H suggestion is to paint with fire retardant paint –Sent initial set of Heigl painted sample to for fire test Had problems at sharp corners, but successful otherwise –Made new samples to fire test which fixed problems with sharp corners Made samples of all 3 materials They have been given to Jim Priest

MINER A Director’s CD-3b Review 11 June 2007 Kevin McFarland University of Rochester 11MINERvA WBS 1,2,4: Scintillator and Fiber Cable Production We expect to start tracking prototype cable production on Nov Full Cable production starts on May

MINER A Director’s CD-3b Review 11 June 2007 Kevin McFarland University of Rochester 12MINERvA WBS 1,2,4: Scintillator and Fiber Clear Fiber QC We measured the attenuation length for the ODU fiber Measured attenuation length of ODU fiber –5 m pieces –Cut back test –Use 1 m WLS jumper Get a 50 cm longer number as opposed to a 50 cm clear jumper CMS and some early MINERvA tests we used 50 cm clear jumper

MINER A Director’s CD-3b Review 11 June 2007 Kevin McFarland University of Rochester 13MINERvA WBS 1,2,4: Scintillator and Fiber Clear Cable QC Get  cm Equivalent to 770 cm in measuring it in the way that CMS did and we got about 800 cm for the attenuation length in CMS for 0.94 mm S-35 fibers –So CMS and MINERvA clear fibers are fairly close in attenuation length

MINER A Director’s CD-3b Review 11 June 2007 Kevin McFarland University of Rochester 14MINERvA WBS 1,2,4: Scintillator and Fiber ESH/QA Changes ESH/QA: WBS 1: –Removed weekly cosmic ray light yield check with extruded strips always tracked more precise source tests which are performed daily WBS 2: –QC procedure uses razor blades for cutting fiber at 45° recent concern raised by PPD ES&H. no directive yet, but in communication WBS 4: –QC improvements already discussed –We are working with ES&H on the new mold material both for personal safety and fire safety Heigl epoxy does not require a chemical hood

MINER A Director’s CD-3b Review 11 June 2007 Kevin McFarland University of Rochester 15MINERvA WBS 1,2,4: Scintillator and Fiber Identified Risks at CD-3a: WBS 4 (Fiber Cables) Final tests of light-tight mold essentially failed to hold up in a production situation –Solution is seen in either redesigning the mold or getting a new mold material and we did both –R&D should be finished in September 2007 Fiber costs carry significant contingency to reflect past changes in pricing from Kuraray (less of a problem with clear fiber than WLS)