© 2007 General Dynamics. All rights reserved. Integrated Space Systems 1196 EB-R75756-000 GLAST Pre-Ship Review (PSR) LAT Payload I&T Review CONTRACT NO.

Slides:



Advertisements
Similar presentations
GLAST LAT ProjectNovember 3, 2005 I&T Phase 0 IRR/TRR 1 GLAST Large Area Telescope: Integration and Test Phase 0 IRR/TRR November 3-4, 2005 Introduction.
Advertisements

GLAST LAT Instrument GLAST Monthly Mission Review May 2, 2007 K.A. Fouts, SLAC 1 Monthly Mission Review Project Status Overview May 2, 2007 Ken Fouts SLAC.
GLAST LAT Instrument GLAST Monthly Mission Review August 6, 2007 K. Fouts, SLAC 1 Monthly Mission Review Project Status Overview August 6, 2007 Ken Fouts.
GLAST LAT ProjectMonthly Status Meeting Jan 26, Project Status January 26, 2006 Gamma-ray Large Area Space Telescope Lowell A. Klaisner Project.
GLAST LAT ProjectLAT Engineering Meeting, April 1, 2003 GLAST Large Area Telescope: Performance & Safety Assurance Darren S. Marsh Stanford Linear Accelerator.
GLAST LAT ProjectNovember 04, 2005 Phase 0 TRR 1 GLAST Large Area Telescope: Integration and Test -Electrical Test- Phase 0 TRR Key Requirements Documents.
GLAST LAT Instrument GLAST Monthly Mission Review October 29, 2007 K. Fouts, SLAC 1 Monthly Mission Review Project Status Overview October 29, 2007 Ken.
GLAST LAT Project June 6, 2007 NCRs and Waivers 1 GLAST Large Area Telescope Systems Engineering Test Status, NCRs and Verification Status Pat Hascall.
1 GLAST LAT ProjectMechanical Systems Mechanical Systems Mechanical / Thermal Hardware November 2004 Status Marc Campell, Subsystem Manager.
GLAST LAT ProjectGSFC Monthly, 15 Dec 2003 LAT System Engineering 1 GLAST Large Area Telescope: LAT System Engineering Pat Hascall SLAC System Engineering.
GLAST LAT Project Aug 1, 2007 NCRs and Waivers 1 GLAST Large Area Telescope Systems Engineering Test Status, NCRs and Verification Status Pat Hascall Systems.
GLAST LAT ProjectApril 27, 2006: LAT Pre-Ship Review 1 Presentation 8 of 12 Integration and Test GLAST Large Area Telescope: Pre-Shipment Review Integration.
GLAST LAT Instrument GLAST Monthly Mission Review October 5, 2007 K. Fouts, SLAC 1 Monthly Mission Review Project Status Overview October 5, 2007 Ken Fouts.
GLAST LAT Project Oct 5, GLAST Large Area Telescope Systems Engineering Test Status, NCRs and Verification Status Pat Hascall Systems Engineering.
GLAST LAT Project May 25, 2006: Pre-Environmental Test Review Presentation 6 of 12 LAT Test Results 1 GLAST Large Area Telescope Pre-Environmental Test.
GLAST LAT Instrument GLAST Monthly Mission Review July 12, 2007 N. Johnson, NRL 1 Monthly Mission Review Project Status Overview July 12, 2007 Neil Johnson.
GLAST LAT ProjectLAT Mgr’s Meeting LAT Planning Meeting Mechanical/Thermal Systems March 17, 2005 Marc Campell.
GLAST LAT Project September 15, 2006: Pre-Shipment Review Presentation 3 of 12 SE Overview 1 GLAST Large Area Telescope LAT Pre-Shipment Review Systems.
GLAST LAT ProjectNovember 3, 2005 I&T Phase 0 IRR/TRR 1 GLAST Large Area Telescope: Integration and Test Phase 0 IRR/TRR November 3-4, 2005 Introduction.
GLAST LAT Project Technical/Cost/Schedule Review 03/30/ Integration and Test 1 GLAST Large Area Telescope: I & T Input to Monthly Technical/Cost/Schedule.
GLAST LAT ProjectMay 25, 2006: Pre-Environmental Test Review LAT Test Verification Process Presentation 4 of 12 GLAST Large Area Telescope Gamma-ray Large.
GLAST LAT ProjectJune Cost/Schedule Status Meeting 07/23/ Integration and Test 1 GLAST Large Area Telescope: I & T Input to June Cost/Schedule.
ISOC/SVACInstrument Analysis Meeting, Quatorze Juillet, 2006 Anders W. Borgland 1 Announcements Anders W. Borgland Science Verification, Analysis and Calibrations.
GLAST LAT ProjectSeptember 15, 2006: Pre-Shipment Review LAT Requirement Verification Presentation 5 of 12 GLAST Large Area Telescope Gamma-ray Large Area.
GLAST LAT ProjectLAT Planning Meeting July 17 th and 18 th Integration and Test 1 GLAST Large Area Telescope: I & T Input to LAT Planning Meeting.
GLAST LAT Project Oct 5, GLAST Large Area Telescope Systems Engineering Test Status, NCRs and Verification Status Pat Hascall Systems Engineering.
GLAST LAT Project May 2, 2007 NCRs and Waivers 1 GLAST Large Area Telescope Systems Engineering Test Status, NCRs and Verification Status Pat Hascall Systems.
GLAST Calorimeter SLAC LAT Meeting 17Jul 2003 Naval Research Lab Washington DC wnjohnson 1 SLAC Meeting Calorimeter Subsystem 17 July 2003 W. N. Johnson.
GLAST Large Area Telescope:
GLAST LAT ProjectI&T&C Pre PDR Presentation– Oct. 2, I&T&C Organization Chart I&T&C Manager Elliott Bloom WBS I&T Engineer B. Grist WBS
GLAST LAT ProjectCDR/CD3 Review May 12-16, 2003 Document: LAT-PR-01967Section XX 1 GLAST Large Area Telescope: LAT System Engineering WBS Dick Horn.
LAT Design Integration and Analysis1 GLAST LAT Project1 Sep 2005 LAT Monthly Status Review 1 Sep 2005 Design Integration and Analysis LAT Monthly Status.
GLAST LAT ProjectApril 27, 2006: LAT Pre-Ship Review Presentation 12 of 12 Quality Assurance 1 GLAST Large Area Telescope: LAT Pre-Ship Review Performance.
LAT Environmental Test PDR1 GLAST LAT Project3-4 May 2005 LAT Environmental Test Planning and Design Review 3-4 May 2005 Overview LAT Environmental Test.
GLAST LAT ProjectSeptember 15, 2006: Pre-Shipment Review 1 Integration and Test Presentation 11 of 12 GLAST Large Area Telescope: LAT Pre-Shipment Review.
GLAST LAT ProjectLAT Muons at NRL 28 Feb 2006 J. Eric Grove Naval Research Lab Washington DC LAT Muon Data Taking During Environmental Test at NRL J. Eric.
Solar Probe Plus A NASA Mission to Touch the Sun March 2015 Instrument Suite Name Presenter's Name.
GLAST LAT Project LAT System Engineering 1 GLAST Large Area Telescope: LAT System Engineering Pat Hascall SLAC System Engineering Manager
GLAST Large Area Telescope LAT Flight Software System Checkout TRR Test Suites (Backup) Stanford Linear Accelerator Center Gamma-ray Large Area Space Telescope.
GLAST LAT ProjectCAL Peer Design Review, Mar 17-18, 2003 W. N. Johnson Naval Research Lab Washington DC GLAST Large Area Telescope Calorimeter Subsystem.
1 GLAST LAT ProjectMechanical Systems Mechanical Systems September 2003 GSFC Status Marc Campell, Subsystem Manager.
GLAST LAT ProjectCDR/CD-3 Review May 12-16, 2003 Document: LAT-PR Section 5 IOC Subsystem 1 GLAST Large Area Telescope: IOC Subsystems WBS: 4.1.B.
LAT Design Integration and Analysis1 GLAST LAT Project24 May 2005 LAT Monthly Status Review 24 May 2005 Design Integration and Analysis LAT Monthly Status.
4-1 MAVEN IPER May 22-23, 2012 Particles and Fields Package Pre-Environmental Review May , Verification Dave Curtis, PFP Package Manager.
GLAST LAT ProjectFace to Face, 14 April 2004 LAT System Engineering 1 GLAST Large Area Telescope: EGSE and Interface Verification Pat Hascall SLAC System.
1 GLAST LAT ProjectMechanical Systems Mechanical Systems November 2003 GSFC Status Marc Campell, Subsystem Manager.
FM4/FM5 IPSRSYS - 1 UCB, May 5, 2006 THEMIS INSTRUMENT SUITE FM4/FM5 PRE-SHIP REVIEW SYSTEM OVERVIEW Ellen Taylor University of California - Berkeley.
GLAST LAT ProjectDOE/NASA Peer Critical Design Review, March 19-20, 2003 D. Nelson 1 GLAST Large Area Telescope: Electronics, Data Acquisition & Instrument.
1 SWEA pre-CDR Peer Review Particles and Fields Package (PFP) SWEA pre-CDR Peer Review Integration with PFP, Qualification, ATLO 2011 March 28 Dave Curtis.
GLAST LAT Project13 June 2005 LAT System EngineeringLAT Test Planning Meeting GLAST LAT GLAST LAT System Engineering Gamma-ray Large Area Space Telescope.
GLAST LAT ProjectSeptember 15, 2006: Pre-Shipment Review Project Overview 1 Presentation 1 of 12 GLAST Large Area Telescope: LAT Pre-Shipment Review W.
GLAST LAT Project May 25, 2006: Pre-Environmental Test Review Presentation 11 of 12 Thermal Vacuum Test 1 GLAST Large Area Telescope LAT Pre-Shipment Review.
EMI/EMC GLAST Large Area Telescope LAT Pre-Shipment Review
I&T&C Organization Chart
GLAST Large Area Telescope:
Baseline Environmental Test Flow at NRL
GLAST LAT System Engineering
GLAST Large Area Telescope
GLAST LAT System Engineering
Thermal Vacuum Test: Plans and Procedures
LAT Test Results GLAST Large Area Telescope LAT Pre-Shipment Review
Integration and Test Organization Chart
GLAST Large Area Telescope:
Mechanical/Thermal Systems
GLAST Large Area Telescope:
GLAST Large Area Telescope
Introduction and Overview
GLAST Large Area Telescope
Integration & Test Instrument Operations Coordination
Design Integration and Analysis
Presentation transcript:

© 2007 General Dynamics. All rights reserved. Integrated Space Systems 1196 EB-R GLAST Pre-Ship Review (PSR) LAT Payload I&T Review CONTRACT NO. NAS , D.O. NO. 11, CDRL NO. 24 Ken Fouts 1-2 November 2007

© 2007 General Dynamics. All rights reserved. Integrated Space Systems 1196 EB-R LAT Presentation Overview  LAT Status  Project Milestones  LAT Configuration Summary  LAT Test Summary  LAT QAR Status  LAT RFA/Waiver Status  LAT Verification and Requirements Summary  LAT Instrument Performance  LAT FSW Summary  Conclusion

© 2007 General Dynamics. All rights reserved. Integrated Space Systems 1196 EB-R LAT Project Milestones

© 2007 General Dynamics. All rights reserved. Integrated Space Systems 1196 EB-R Current Configuration  As built configuration  LAT-DS-1624 LAT Top Assembly  Radiators flight installed  LAT MLI closeout (ECD prior to TVAC)

© 2007 General Dynamics. All rights reserved. Integrated Space Systems 1196 EB-R LAT Summary Status  LAT is integrated with the spacecraft and has successfully completed EMI/EMC, Sine Vibe, Acoustic tests  Verified by the successful completion of 3 CPT’s  No major failures or environmental susceptibilities have been identified  No significant performance changes throughout the program  LAT requirement verification sell off is in progress  411 of 458 Total Requirements Verified  Additional requirements will be closed by:  Completion of TVAC test

© 2007 General Dynamics. All rights reserved. Integrated Space Systems 1196 EB-R LAT Unit Run Time As of Oct 26, 2007 the LAT passed 700 operating hours since the timer fix was installed FSW B1.0.1 has 281 operating hours  Note that the EPUs are 2 for 3 redundant and most test time is in configurations 1 and 2. Since EPU-P1 is on in both of those configurations it has double the run time of the other EPUs LAT Unit Operating Time (Hrs) SIU-PSIU-R GASU- P GASU- R EPU- P0 EPU- P1EPU-R CAL/TKR /TEMACD ACD HV1 ACD HV2PDU-PPDU-R

© 2007 General Dynamics. All rights reserved. Integrated Space Systems 1196 EB-R Status of LAT Related QARs QARDate Opened Affected Hardware Problem DescriptionCategoryLAT NCR Resolution /17/06MechReplace modified ACD to LAT blanketsHardware Discrepancy 942Close at launch base /17/06DAQACD FREE board 5 not responsive after power up CND946Monitor /17/06DAQLATC verify occasionally reports errors in CRC, SPT, ARC CND855Monitor /11/07DAQGrid radiator interface thermistors were swapped in Observatory telemetry database Software Change N/AClose before ship to NRL /04/07DAQOne heat pipe temp sensor showed occasional erroneous readings Hardware Discrepancy N/AUse as is /19/07MechAreas of contamination observed on ACD blanket Hardware Discrepancy N/AArea cleaned pre-Dynamics test. Reinspect post-TVAC /20/07MechSmall indentation on +Y radiator surface after contact with solar array Hardware Discrepancy N/AUse as is /10/07MechFound two broken ground wires (X-LAT blanket and LAT shorting plug) Hardware Discrepancy N/ARepair/rework

© 2007 General Dynamics. All rights reserved. Integrated Space Systems 1196 EB-R RFA/Waiver Status  RFAs from previous LAT reviews  PDR RFAs all closed  dPDR RFAs all closed  CDR RFAs all closed  PER RFAs all closed  PSR RFAs all closed  Observatory PER RFA’s all closed  Waiver status change since PER  3 New LAT Waivers CCR #TitleDescriptionStatus RS103 CAL Susceptibility Observed excess calorimeter triggers and occupancy near 280MHz..Approved RS103 Temp Sensor Susceptibility Observed a susceptibility in a subset of LAT RTD's during the MHz sweepApproved Use of 50V Capacitors in under 10V applications without screening Ceramic 50V capacitors used in <10V applications were not screened prior to use per MIL-C-123 Group B, Subgroup 2.Approved

© 2007 General Dynamics. All rights reserved. Integrated Space Systems 1196 EB-R LAT Risk Summary  No new LAT risks identified  All LAT risk items remain low

© 2007 General Dynamics. All rights reserved. Integrated Space Systems 1196 EB-R LAT Level Verification Status  All 458 VPs are Final  410 of 411 VPs planned for execution have been approved by GSFC  1 SRD VP (Background Rejection) in work by GSFC  Status  VCRM version 27 released  All deferred GRB reqts will be sold post FSW B1.0 installation

© 2007 General Dynamics. All rights reserved. Integrated Space Systems 1196 EB-R LAT Instrument Performance Summary  LAT detector status  LAT instruments fully functional on the Spacecraft  Performance measured at GD-AIS prior to integration  LAT Baseline performance confirmed  Post-integration performance measured at GD-AIS  Baseline functional performance confirmed  Awaiting pre-TV calibration  Post EMI/EMC performance verified at GD-AIS  Baseline functional performance confirmed by CPT  Post Dynamics test performance verified at GD-AIS  Baseline functional performance confirmed by CPT  Integrated LAT is ready for TVAC test

© 2007 General Dynamics. All rights reserved. Integrated Space Systems 1196 EB-R LAT FSW Summary  FSW B1-0-1 meets all 183/183 requirements  > 200 hours of run time with this build  Spontaneous reboots resolved  > 700 reboot-free hours since FSW fix installed  Reboot problem had minimal impact on LAT and Observatory testing  No LAT FSW liens

© 2007 General Dynamics. All rights reserved. Integrated Space Systems 1196 EB-R Conclusion  LAT testing after integration with the spacecraft successfully completed  LAT performance after EMI/EMC and Dynamics test verified by test.  No liens open which preclude shipment to NRL  LAT is ready for Observatory TVAC test