2003 Roads Report Warm Springs Agency. Project Completion Model Graphic display to show the various phases of project development for the roads program.

Slides:



Advertisements
Similar presentations
Fairfax County Board of Supervisors Transportation Sub-Committee Briefing Federal Highway Administration Eastern Federal Lands Highway Division Robert.
Advertisements

Legal Descriptions and Site Plan Requirements
Winter Storm ” Snowfall 20 Days of Freezing Rain.
At 4620 square miles, Lane County, Oregon is nearly as large as the State of Connecticut and is home to some 336,000 residents. Short Mountain Landfill,
Cost Estimation System Tool
Lander Streets and Utilities 2015 Public Meeting No. 2 McDougall & Cliff Project Area.
Capital Improvement Plan May 8 th, 2013 Presented by City Administration: Public Works Department Finance Department.
Dillon and Christina Project Area Lander Streets and Utilities 2015 Public Meeting No. 2.
APEX Engineering Ian Braun Andrew Halley Jorge Hernandez Mohamad Haikal Bin Maamor PROPOSED HUALAPAI MUSEUM SITE DESIGN 1.
Route 50 Widening Design/Build Project. 2  Virginia Department of Transportation  Shirley Contracting Company  Dewberry  Fairfax and Loudoun Counties.
Plot Plans & Legal Descriptions. Site or Plot Plans  A plot or site is an area of land generally one lot or construction site in size  The term plot.
East Bay RTK Network Duncan Marshall East Bay Regional Park District This presentation will probably involve audience discussion, which will.
County of Fairfax, Virginia Sully District Council Meeting November 19, 2014.
Capilano Road Improvement Project WELCOME TO THE OPEN HOUSE.
Pequest Trout Hatchery & Natural Resource Education Center Located on Route 46 in scenic Warren County New Jersey.
Friends of the Fox River November 9, 2014 Longmeadow Parkway Fox River Bridge Corridor.
Hardin County Engineering Department September 12, 2006.
US Highway 17 (Center Street) Sidewalk Feasibility Study Town of Pierson, Florida.
S.R. 256 Road Reconstruction Project From City of Austin to S.R. 203 Thursday, February 6, 2014 Austin Elementary School 6:00 p.m.
Wiehle Ave. Traffic Concerns Created by Judy and Doug Pew.
Delaware State Driver’s Education Study Guide. Drivers have trouble seeing motorcycles in traffic. Why?
BASICS OF SURVEYING Ivy Tech Community College. Surveying Definition DEFINITION The art and science of making such measurements as are necessary to determine.
U.S. 31 at CR 400 South Roundabout Information Meeting December 18, 2013 Clifty Creek Elementary Columbus, Indiana.
CASE STUDY PLSS 3 MILE RULE SUBDIVISION OF SECTIONS (INDIAN LANDS) Warm Springs Indian Reservation.
 Embankment Construction – LOTs  What is the maximum length of a LOT? Mainline pavement lanes, turn lanes, ramps, parking lots, concrete box.
How GIS and Land Surveying at Created by: Riley Lindsay Created by: Riley Lindsay can help local government?
VTA Light Rail System and Safety Enhancements MTC Railroad Crossing Seminar May, 21, 2008.
Chapter 14 Legal Descriptions and Site Plan Requirements.
Engineering and Technical Plans Description, process and standards Dh 2005.
WVDOT GTI SECTION Status Update for Districts. AGENDA Introduction. Introduction. Status Update. Status Update. How to Spatially Enable Database. How.
WVDOT GTI SECTION Status Update for Miss Utility.
Highway Design Class CTC 440. Introductions Students Me.
Presents Project Crimson March 1, 2006 Sarah Grace Cade Harrelson Cochrane Jamison Libby Probst Justin Williams.
NCGS: Positioning NC today and for the future! North Carolina Geodetic Survey Maintenance of a CORS/RTN infrastructure.
The Corporation of the Town of Amherstburg Public Works Department 2013 CAPITAL BUDGET Presented to: The Heavy Construction Association March 20, 2013.
What does PWD do for our City?. Administrative Services Engineering Operations.
Chapter 12 Legal Descriptions and Site Plan Requirements.
Working Successfully With Property Managers: An Interactive Engagement
SR 1 BLUFFTON Public Hearing September 25, INDOT Mission: INDOT will plan, build, maintain and operate a superior transportation system enhancing.
Chapter 15 Site Plan Layout. Introduction Site plans can be drawn on media ranging in size from 8 ½" × 11" up to 34" × 44" –Depends on purpose –Many local.
Site Plan Requirements © 2010 Project Lead The Way, Inc.Civil Engineering and Architecture.
HIGHWAY DEPARTMENT Tim G. Schulte, P.E. Richland County Engineer.
FINAL BUDGET CITY COUNCIL PUBLIC HEARING SEPTEMBER 27, 2011.
TENTATIVE BUDGET PRESENTATION CITY COUNCIL PUBLIC HEARING SEPTEMBER 8, 2010.
Presentation Outline  Recommendation  Project Background  Public Involvement  Proposed Design  Citizen Comments/Questions  Summary and Recommendation.
Calle Real Campus Design Guidelines. Five-Step Process 1999 Board Direction, create a five phase process--- –Phase 1: Determine Space Needs –Phase 2:
PROPOSED BUDGET PRESENTATION CITY COUNCIL WORKSHOP AUGUST 23, 2011.
Chapter 16 Site Preparation. Objectives After reading the chapter and reviewing the materials presented the students will be able to: Identify tasks required.
Planning Commission Public Hearing: SUB Proposed 6-lot Subdivision at Bland Circle December 2, 2015.
DCA-1 P-03K-01 Within rural Baston Trailer Park its roadways are often impassable with rain events for the residents. Wilkes County proposes to widen and.
COUNTY ROAD 517 Improvements from State Highway 172 to Howe Drive DECEMBER 16, 2015 At Tribal Multipurpose Facility.
DRAFT BUDGET PRESENTATION CITY COUNCIL WORKSHOP AUGUST 10, 2010.
156 th Street Design in Bennington Public Open House Meeting October 28, 2009 City of Bennington, NE.
Ingress and Egress The means of entering and leaving the site Regulated by state and local governments Width Slope Drive radius Pavement composition Encroachment.
EAST CHEROKEE DRIVE PROJECT UPDATE CHEROKEE COUNTY ENGINEERING DEPARTMENT MARCH 31, 2016.
Civil Engineering Surveying Roy Frank. Basic Route Survey and Design 1.Concept for Route 2.Reconnaissance Study 1.Small scale mapping of region (1”-500’
Girvin Road Improvements (Atlantic Blvd. to Wonderwood Dr.) Public Information Meeting March 3, 2016.
CITY OF NEW BERLIN SECTION 35 Neighborhoods G & H Comprehensive Plan Amendment Public Input January 2012.
Gujarat Institute of Technical Studies name: Patel Savan Vasudevbhai Semester: 3 st Sem. Branch: Civil Engineering Enrollment No. : Sub: surveying.
Brookeville Bypass Final Design Presentation Initech May 6, 2004.
City of Snoqualmie Tokul Roundabout Project April 10, 2012.
ELCITA UPDATE March 2017.
Town of Brighton, Department of Public Works
Jefferson County SA Red Rocks Site Approval
IA 122 RECONSTRUCTION PRE-BID MEETING
Construction Management & Inspection
Quarterly Transportation Report 4th Quarter 2011 October 11, 2011
Site Plan Requirements
Walker Street Reconstruction Project 25% Design Public Hearing
Monterey County Project Report for Measure X Expenditures
Presentation transcript:

2003 Roads Report Warm Springs Agency

Project Completion Model Graphic display to show the various phases of project development for the roads program Data includes; –Project Name –Reservation and Route Number –PCAS Accounting Code

Contract Administration Final Close Out Construction Monitoring Contract Award

Road Construction Department Contract Administration Final Close Out many old contracts Completed Construction Monitoring Projects –WSIR 13(4) Wolfe Point (Webster Flat) Road (almost) –WSIR 75(4) Bear Drive –WSIR 803 Aggregate Replacement –BPIR 1(4) Pa’si’go Loop Completed Contract Award –WSIR 29(3) Upper Dry Creek Road –WSIR 943 Chip Seal Contract –WSIR 804 Aggregate Replacement –WSIR 4001(2) Administration to Health Center

Construction Monitored 2003

Wolfe Point Drive Webster Flat P09001 WSIR 13(4)

Wolfe Point Drive (Webster Flat) P09001 WSIR 13(4)

P09001 WSIR 13(4) Asphalt Paving

P09001 WSIR 13(4) Asphalt Pick-up Operation

Wolfe Point CMP Outlet P09001 WSIR 13(4)

P09001 WSIR 13(4) Culvert Bedding

P09001 WSIR 13(4) Compaction of Culvert Bedding

P09001 WSIR 13(4) Compaction Testing

P09001 WSIR 13(4) Hydroseed Operation

Wolfe Point P09001 WSIR 13(4) Broken Cattleguard Wings

Patching P09001 WSIR 13(4) Twin Pipes Fill Settling

Bear Drive Entrance P09352 WSIR 75(4)

Bear Drive (Driveways) P09352 WSIR 75(4)

P09107 WSIR 803

P09107 WSIR 803 Aggregate Spreading

P09010 BPIR 1(4) Parking Lot with Old Sidewalk

P09010 BPIR 1(4) Sidewalk Forms

P09010 BPIR 1(4) Paving Along Valley Gutter

P09010 BPIR 1(4) Pa’si’go Loop Parking and Flag Pole

P09010 BPIR 1(4) Pa’si’go Loop

Contracts Awarded 2003

Upper Dry Creek P09007 WSIR 29(3) 3-Layer BST Beginning of Project End of Project

P09301 WSIR 943 Chip Seal

P09203 WSIR 804 Aggregate Replacement

Administration to Health P09103 WSIR 4001(2) Proposed New Construction Beginning of Project Replace Fruit Tree Add Sidewalks End of Project Relocate Driveway

Administration to Health P09103 WSIR 4001(2) Tenino Road Tenino Road (South View) Existing Pedestrian Path Tenino Road (North View) Proposed Pedestrian Path

NEPA/Environmental Categorical Exclusion Environmental Assessments 404 Permits

Road Construction Department NEPA/Environmental Analysis Understanding the NEPA Process Finished NEPA using the BIA Categorical Exclusion –WSIR 804 Aggregate Replacement –WSIR 943 Chip Seal (Route 3) Wrote Draft Environmental Assessments –WSIR 3002(2) Fish Hatchery Junction –WSIR 33(1) County Line Road Bus Route –WSIR 4(8) East Tenino Drainage –WSIR 8(7) Kahneeta Junction –WSIR 49(1) Mill Access Road –WSIR 7B(5) Mill Creek Bank Protection –UIR 900 County Road –BPIR 5(1) Cemetery Road Applied for a 404 Permit with the US Army Corps of Engineers –WSIR 4001(2) Administration to Health Center

Engineering Design Update previous plans Complete New Plans –50% Review by NWRO –90% Review by NWRO –Print and stamp final plans

Road Construction Department Engineering Design Updated Previous Plans –Klamath plans (Phase 2) –WSIR 3002(1) Fish Hatchery Junction –WSIR 8(7) Kahneeta Junction –UIR 900 County Line Road –WSIR 804 Aggregate Replacement –WSIR 943 Chip Seal (Route 3) Completed New Plans –WSIR 33(1) County Line Road –WSIR 4(8) East Tenino Drainage –WSIR 7B(5) Mill Creek Bank Protection

Survey and Right-of-way Topo Survey Property Line Location Prepare Right-of-way plat

Road Construction Department Survey and Right-of-ways Accomplished control survey for Neah Bay Established Control Network for Warm Springs Surveyed 11 New Projects (Topo and Property Lines) –WSIR 33(1) County Line Road –WSIR 51(2) Simnasho Subdivision –WSIR 24(6) Seekseequa Subdivision –WSIR 13(5) Culpus Turn Lane –WSIR 15(1) Sidwalter Flat –WSIR 7B(5) Mill Creek Bank Protection –WSIR 4(6) East Tenino Drainage –Wolfe Point to Kahneeta –WSIR 241(2) Dry Creek Extension –WSIR 75(6) Greeley Heights Second Access –WSIR 53(8) Hollywood/Tenino Round-a-bout

Warm Springs Survey Network Current Status 48 Permanent Monuments (Three Mile Radius Approx) –23 Previous (USGS/FHWA/ODOT/BIA) –25 New (BIA GPS control points) –Yields 5 calibrated sites for RTK survey on reservation 46 Elevation Control Points (Historical data BAD!!!) 240 Section and Quarter Corners (PLSS) 814 Property Pins (Subdivision Lot Corners) Next year we will try to get historical data from old Unix based Mountain Top Software to TGO (Trimble Geometrics Office) and Autocad format for campus area of reservation.

Warm Springs RTK Base Network

Warm Springs Reservation Survey Base Stations

NGS Survey Monument COYOTE

Grouted in rock4 Inch Pipe in soil USGS Monument 50+ years old

BIA Permanent Monument Note fencepost to aid in finding station license number, and date stamp.

Used for GPS photo control by GIS department Poor GPS survey control Pipe wiggles when pushed by animals Unknown Origin (Not linked to original GLO notes) PLSS Brass Cap (Section Corner) (Public Land Survey System)

Position not stable over time. Too easy to move monument. Bad GPS Control Point Subdivision Lot Corner

Trimble RTK Base Station 4700 Base Receiver set up over monument with broadcast antenna and car battery power supply

Base Station with nearby tree Trees will interfere with GPS signal. Keep base monuments as far away as possible from sources of interference.

GPS Survey of Neah Bay Red Vectors possible errors (tree interference)

GPS Error Sources Electrical interference from transmission tower, Setting up on Reference Monument instead of benchmark (BIG error). Setting up near Chain Link Fences and FLAT water Surfaces….IE Puddles on calm days.

4800 Rover Trimble 4800 Rover with 1.8 meter pole gathering point data (fenceline, cmp, utility locations….)

4700 Rover with Pole 4700 Backpack with 2.0 meter pole gathering point data.

4700 Rover (Continuous Mode) 4700 rover mounted to backpack for topo shots. Points gathered in continuous mode (every 5? Seconds). Note height of antenna varies with operator.

Tahoe Mounted 4700 Rover GPS antenna is mounted to detachable rack on top of Chevy Tahoe to survey above passenger wheel. Height of antenna varies with vehicle. Data gathered every 1 second at 30 mph = 44 feet between points. Light area right of fog line is asphalt extruded curb.

Mounting Bracket for Tahoe Mounting bracket for 4700 receiver on Tahoe. Note : RTK receiving antenna out back window. Driver can control vehicle and start and stop data recording.

GPS Survey Project Examples East Tenino School Site P09405 Upper Dry Creek Extension P09606

Cross-Section Type Survey with Breaklines

Continuous Survey (Tahoe) with Breaklines

Total Topo Points Collected

Contour Map of Project Topo Survey Finished

Dry Creek Extension Subdivision

Transportation Planning Update Tip 638 Contracts to the tribe –Engineering Design –Right-of-way –NEPA/Environmental

Road Construction Department Tribal Engineering Various Water and Sewer Projects Contracts for Landfill and Transfer Sites Transportation Planner for Tribe Located many property corners and lots Administered Design Contract Culpus Bridge Modified old designs to correct deficiencies –P09007 WSIR 29(3) Upper Dry Creek Awarded $250,000 in new design and NEPA/Environmental contracts for various roads projects –P09801 WSIR 3003(6) Sunnyside –P09434 WSIR 24(5) Jackson Trail Road –P09401 WSIR 51(2) Simnasho Subdivision –P09501 WSIR 24(6) Seekseequa Subdivision

Seekseequa Fire Hall New Water System & Buildings

Dry Creek Solid Waste Transfer Site

Proposed Simnasho Solid Waste Transfer Site

Warm Springs Wastewater Treatment Plant

Road Construction Department Program Administration Trained two employees in Eagle Point 2002 Trained one employee in PMS –(Pavement Management System) Trained two employees in TGO –(Trimble Geometrics Office) Trained all employees in field survey for total station and Trimble GPS survey grade equipment Began process to install 4 permanent traffic counters on various routes