Hamid Shoaee Control System Installation 3/16/2007 1 2007 Downtime Readiness Review Hamid Shoaee For LCLS Controls Group.

Slides:



Advertisements
Similar presentations
Stephanie Allison LCLS Event System 14 June LCLS Event System Outline HW Block Diagram Timing Requirements Time Lines EVG.
Advertisements

Wednesday July 19 GDE Plenary Global Design Effort 1 Instrumentation Technical System Review Marc Ross.
XTCAV X-Band Transverse Deflecting Cavity Project Overview Patrick Krejcik Yuantao Ding, Joe Frisch.
Kathleen Ratcliffe BC2/Linac Installation April 16, BC2 / Linac Installation Coordination Kathleen.
26-Sep-11 1 New xTCA Developments at SLAC CERN xTCA for Physics Interest Group Sept 26, 2011 Ray Larsen SLAC National Accelerator Laboratory New xTCA Developments.
HPS MPS OVERVIEW Dan Sexton & the Safety Systems Group JLAB 1.
Richard M. Boyce FAC Review – Accelerator Installation October 29-31, Installation – Accelerator Systems Installation Planning.
Ernest Williams FAC November 2008 Control Systems Software Section 1 Controls System Installation Status Ernest Williams for Controls Department.
FAC review, 10/27 D. Schultz 1 e-Beams System Update Injector System Installation has started. Linac System Preparing for ’06 installation. Controls System.
FAC, 10/12/06 D. Schultz 1 e-Beams Systems Update Linac Injector Undulator Production MMF commissioning ARR David Schultz.
S. Smith LCLS Facility Advisory April 16, BPMs and Toroids Facility Advisory Committee April 16, 2007 System overview.
FAC, 4/20/06 D. Schultz 1 e-Beams System Update Linac System Preparing for downtime installation. Injector System Installation has started. Undulator System.
Paul Emma LCLS FAC April 16, Initial Experience with Injector Commissioning P. Emma, et al. Facilities Advisory Committee.
Patrick Krejcik LCLS April 16-17, 2007 Breakout Session: Controls Controls Commissioning Experience.
LTU & Electron Beam Dump Linac Coherent Light Source Stanford Synchrotron Radiation Laboratory Stanford Linear Accelerator Center LCLS Technical Design.
Kathleen Ratcliffe LTU Installation October 30, LTU Installation Coordination Kathleen Ratcliffe.
Eric Bong LCLS FAC Injector-Linac October 27, 2005 Injector Design / Diagnostics / Gun & Linac RF Design E. Bong LCLS FAC.
FAC, 4/16/07 D. Schultz 1 e-Beams Systems Update People ARR Linac Installation Undulator Production MMF Operations David Schultz.
LCLS Linac System Management Linac Coherent Light Source Stanford Synchrotron Radiation Laboratory Stanford Linear Accelerator Center.
D. Schultz FAC 6/17/08 1 e-Beams Systems Update People Progress the last review LTU and Dump Installation Status Undulator.
Hamid Shoaee LCLS FAC Controls June 17, LCLS Control System Personnel Linac & BC2 Controls progress LTU, Dump Controls.
Eric Bong LCLS FAC Injector-Linac System October 27, 2005 Injector –Linac System Overview E. Bong LCLS FAC October 27, 2005.
E. Bong, SLACLCLS FAC Meeting - April 29, 2004 Linac Overview E. Bong LCLS FAC Meeting April 29, 2004 LCLS.
David H. Dowell Injector April 29-30, 2004 LCLS Injector Overview D. H. Dowell, SLAC FAC Review April 29-30, 2004 Injector.
Dayle Kotturi Facility Advisory Committee Meeting October 12, 2004 Injector/Linac Controls An overview of the status of each of.
Hamid Shoaee LCLS Facility Advisory Committee 20 April Plans for 2006 Installation April 20, 2006 Injector commissioning.
Hamid Shoaee LCLS FAC Review – October Control System Overview Hamid Shoaee Controls System Manager Injector control system commissioning & Support.
Geoff Pile LCLS Und. System Fabrication FAC 29 th, 30 th & 31 st October 2007 LCLS Undulator System Fabrication Schedule FAC.
Hamid Shoaee LCLS Control April 20, 2006 LCLS Control System Organization & Integration with the rest of the lab, Accelerator.
C.E. Rago Inj/Lin Design & 4_20_06 1 Injector / Linac Design & Fabrication C.E. Rago FAC Review 04_20_06.
Arturo Alarcon Undulator Controls Module Status 11/12/2008 SLAC National Accelerator Laboratory 1 Undulator Controls Module Status.
Hamid Shoaee Accelerator Readiness Dec. 2, ‘08 SLAC National Accelerator Laboratory Controls Department LCLS Maintenance.
LCLS-II Linac LLRF Control System – L1, BC1 Zheqiao Geng Final Design Review May 7, 2012.
Hamid Shoaee LCLS Control April 20, 2006 LCLS Control System Controls Organization Overview A Progress Report Hamid Shoaee.
FAC, 10/12/06 D. Schultz 1 Readiness for 2007 Startup Linac Injector Controls ARR David Schultz.
LCLS-II Linac LLRF Control System – L2, L3 Zheqiao Geng Preliminary Design Review May 7, 2012.
Injector/Re-injection Chicane Michael Bevins May 17, GeV Upgrade - Beam Transport Injection, Linac, Extraction, & Correctors Preliminary Design.
Stephen Schuh Vacuum Controls SCR and 16 November 2005 Vacuum Controls System Concept Review and Preliminary Design Review.
David Schultz Accelerator Readiness Dec. 2, ‘08 SLAC National Accelerator Laboratory 1 Undulator Complex Status LCLS Introduction.
LCLS Accelerator SLAC linac tunnel research yard Linac-0 L =6 m Linac-1 L  9 m  rf   25° Linac-2 L  330 m  rf   41° Linac-3 L  550 m  rf  0°
K. Luchini LCLS Injector /BC1 Magnet PS Final Design Review, March 30, Injector and BC1 Magnet PS Controls K. Luchini.
MTCA use in Linac to replace CAMAC Tom Himel June 4,
Marjorie Widmeyer LCLS Injector Magnet Power March 30, LCLS Injector, Sector 21 and BC1 DC Magnet Power and Control.
The recent history and current state of the linac control system Tom Himel Dec 1,
Stephen Norum LCLS Oct. 12, LCLS Machine Protection System Outline Overview of interim MPS Update on the interim MPS.
Hamid Shoaee Control LCLS ARR Oct 31, LCLS Accelerator Readiness Review Control System for Injector Commissioning.
LCLS Control Group FAC – 06 Installation October 27/28, Plans for 2006 Installation October 27, 2005 Installation.
K. Luchini LCLS Injector /BC1 Magnet PS Final Design Review, March 30, Injector and BC1 Magnet PS Controls K. Luchini.
Patrick’s Updates - 8/30/11 (one slide for each of the following) 1.XTCAV Project 2.ASTA Gun Test Facility Instrumentation & Controls 3.Fast wire scanner.
Timing and Event System S. Allison, M. Browne, B. Dalesio, J
LLRF and Beam-based Longitudinal Feedback Readiness
LCLS Linac Update Brief Overview L1 & BC1 Progress LTU & E-Dump Status Continuing Resolution Impact.
Injector –Linac Status & Schedule E. Bong LCLS FAC October 12, 2006
LTU/Undulator Installation Status
Advanced Research Electron Accelerator Laboratory
Linac/BC1 Commissioning P
Electron Beam Systems ETC and Methodology
Injector / Linac Installation Current Status
LCLS Commissioning P. Emma, et al
Linac LLP Outline LINAC Long Lead Procurements
Maximum Credible Beam Event Paul Emma et al
2007 Downtime Controls Installation
LTU/Undulator Installation Status
Control System Overview Hamid Shoaee LCLS Control System Manager
Injector/Linac Design Status C. E
LCLS e- Beams System Overview
Vacuum Controls Stephen Schuh Tom Porter 25 October 2006
LCLS Control System Personnel Linac & BC2 Controls progress
LCLS e- Beams Systems Manager
Control System Overview Hamid Shoaee LCLS Control System Manager
Presentation transcript:

Hamid Shoaee Control System Installation 3/16/ Downtime Readiness Review Hamid Shoaee For LCLS Controls Group (in the following departments) Controls Power Conversion Klystron

Hamid Shoaee Control System Installation 3/16/ Agenda LCLS Control System Installation Readiness Objectives & Scope Schedule & the Process Cable Plant, racks and other infrastructure I&C Systems status and schedule Issues & Concerns

Hamid Shoaee Control System Installation 3/16/ AASSOONNDDJJFFMMAAMMJJJJAASSOONNDDJJFFMMAAMMJJJJ LCLS Installation and Commissioning Time-Line Injector Controls Installation Complete Gun/Inj./BC1 Commissioning Gun/Inj./BC1 Install (8/21 – 2/20) linac/BC2 Install Inj./Linac/BC2 Commissioning LTU/und. Install LTU/und. hall “ready” ControlsCheckout LTU/und. Commissioning First Spont. Light Oct. 19, 2006

SLAC linac tunnel research yard Linac-0 L =6 m Linac-1 L  9 m Linac-2 L  330 m Linac-3 L  550 m BC1 L  6 m BC2 L  22 m DL2 L =275 m ‘Wall region’ undulator L =130 m 6 MeV 135 MeV 250 MeV4.30 GeV13.6 GeV Linac-X L =0.6 m 21-1 b,c,d...existing linac L0-a,b rf gun 21-3b 24-6d X 25-1a 30-8c Commission now 2007 down, Sept-Nov LCLS Accelerator Regions Nov. 1, ’07 Down:Sep., Oct., Nov. of 2007 Run:Dec through ~Aug To:SL2-stopper in BSY (just past linac sector-30)

Remove 8 RF sections (24-7, 8) Remove quad Q24801 Add 4 new bends in sector-24 Add 6 new quads (3 types) Add 1 ‘wide’ BPM Add 1 x-collimator Add 1 OTR screen Modifications in Sector-24 for BC2 (Emma)

Hamid Shoaee Control System Installation 3/16/ Linac Modifications (Fall ‘07) Remove 8 RF sections (24-7, 8) Remove quad Q24801 Add 4 new bends in sector-24 Add 6 new quads (3 types) Add 1 ‘wide’ BPM Add 1 x-collimator Add 1 OTR screen

Hamid Shoaee Control System Installation 3/16/ Linac Modifications (continued) Add 4 new wire scanners in sector-24 Add 3 OTR screens (1 BC1, 2 in sec-25) Move LOLA (trans. deflector) from sec-29 to 25-2 (powered by the 24-8 klystron) Add pulsed horizontal dipole magnet in sec-25 (BXKIK) Move 2 LI28 Wire Scanners, 44 & 544, by meters BPM electronics upgraded (resolution improved) More feedback loops (energy & bunch length)

Hamid Shoaee Control System Installation 3/16/ Linac Modifications (continued) Power Systems BC2 racks & PS (install racks and PS at sector 24) I&C Systems I&C racks and systems (install racks at sector 24) Cable Plant Sector 24 ( install new trays and cable plant from sector 24 racks into Linac; terminate at racks and at loads) BTH West (pull cables from B005, 105, 106 through BSY into BTH West and coil cables; no loads & no racks installed yet) B136 through BSY to BTH West Remove cut cables from FFTB

Hamid Shoaee Control System Installation 3/16/ Plans & Process for BC2 Controls System Installation Controls installation takes place in several steps: Design, procurement and Installation of the cable plant including trays, long haul DC and I&C cables Cables Termination and connection to beam line components (Mechanical Systems) Procurement & preparation of electronics racks Installation of electronics chassis and modules including crates, IOCs, timing modules in the racks Rack installation in the field, AC & cable plant connection

Controls Installation Schedule Overview

Cable Plant Design & Installation Process From the list of devices to be installed… Develop racks layout & cable tray design Generate rack profiles for electronics modules Identify DC & I&C cabling requirements & document in CAPTAR Produce installation bid package from CAPTAR and tray designs Generate installation bid package & award contract Procure trays, cables, connectors, etc. Install cable plant and terminate to beam line components

Hamid Shoaee Control System Installation 3/16/ Typical Sector Cable List (Michael De salvo, Mario Ortega)

Hamid Shoaee Control System Installation 3/16/ Sector 24 Connector List First draft BC2 cable design  13k feet  $245k (cable)  $10k (connectors)

Racks will be pre-loaded in B24 before field installation

Hamid Shoaee Control System Installation 3/16/ BC2 Controls Sub-Systems Cable plant Racks, crates, IOC, etc. Networks Magnet power supply control Vacuum control Safety systems PPS, MPS, BCS Motion control Wire scanners, Collimators, Chicane Timing Beam instrumentation and diagnostics BPM, Toroid, OTR/YAG, Bunch length monitor LLRF

Hamid Shoaee Control System Installation 3/16/ LCLS Controls systems For each system… Technical leads have developed a schedule covering all phases leading to installation and commissioning The schedules include development of appropriate field documents (EI, WD), rack profile/cable plant design, procurement, installation and system checkout Continue Interfacing with Mario Ortega, Bob Fuller, Mike DiSalvo to coordinate procurement and installation We will be reviewing each schedule to identify bottlenecks, dependencies on other systems, resource availability

Hamid Shoaee Control System Installation 3/16/ Safety Systems for BC2,L2,L3 PPS The Linac PPS does not require modification to run LCLS beam to SL-2. There is an AIP project to convert the Linac and BSY to the LCLS PLC- based system in 2008 MPS We will use the current (1553-based) MPS for BC2. Two new ion chambers will be required The system will include 10 LDIM inputs OTR21 (2ea) OTR22 (2ea) OTR_CAV (2ea) BC2 Mover (2ea) CE21 (2ea) We will need to commission AP25 (currently installed but powered down) to accommodate a new PICP module and an LDIM (already installed).

BC2 MPS Schedule Check out 12/3

Hamid Shoaee Control System Installation 3/16/ Concurrently developing new LCLS MPS Response time of less than one pulse at 120 Hz Decoupling from Master Pattern Generator (MPG) Fast communication and processing Knowledge of beam rate Integration of EVR to MPS and fault devices New hardware extended 1.2 km past current MPS Non-CAMAC Ready for photon section

Hamid Shoaee Control System Installation 3/16/ LCLS MPS Features Has response time low enough to protect the undulator (less than 8.3 ms) Communicates with LCLS timing system (EVG) Supports new beam loss monitoring hardware and rate limiting methods Easily extendable and is designed around standards based COTS components Flexible input and output methods

Hamid Shoaee Control System Installation 3/16/ Overview

Hamid Shoaee Control System Installation 3/16/ Core Hardware and Software Hardware and Software Completion DateQuantityCost per Unit Digital Input Card04/16/ Digital Output CardDone4700 MVME /31/ EVR05/31/ Reflective Memory04/02/ Reflective Memory Hub 04/02/ Total Note: These are material costs only. Development labor, installation, etc. costs are not included.

Hamid Shoaee Control System Installation 3/16/ Other MPS Devices Hardware and SoftwareCompletion DateQuantity Beam Loss Monitors05/01/200852–154 Beam Loss Monitor ADC (Argonne) 05/01/200810–25 PLIC Scope Card05/01/20083

Hamid Shoaee Control System Installation 3/16/ Milestones TaskCompletion Date User Interface11/01/2007 Linac Installation11/01/2007 BC2 Commissioning12/03/2007 LTU-Undulator Commissioning05/01/2008 Preliminary Design Review04/16/2007 Final Design Review09/03/2007 Readiness Review10/17/2007

Hamid Shoaee Control System Installation 3/16/ BCS (Beam Containment System) We will use & extend the existing BCS for BC2 commissioning Two possible configurations are being considered 1.New BCS PIC System installation in Sector-24 A 50 conductor trunk from the Sector-28 BCS rack to a new rack in Sector- 24. Long hauls from Sector-24 BCS Rack to the beam line devices in Sector-24 (2 cables per PIC, 1 cable per LION, 1 cable per Flow Switch or Pressure Switch) 2.Use BCS PIC system in Sector-28 (Depends on being able to drive PIC/LION HV and signal four sectors) Long hauls from Sector-28 to the beam line devices in Sector-24 (2 cables per PIC, 1 cable per LION, 1 cable per Flow Switch or Pressure Switch) For either configuration… Install VME Crate and associated hardware/software/network Install new LION Gas system. AC Power to Sector-28 & Sector-24 racks.

BC2 BCS Schedule Check out 11/23

Hamid Shoaee Control System Installation 3/16/ Magnet Power Supply Control The software design is mature and will require little if any changes for BC2 Procurements are well under way and orders have been placed for power supplies, racks, etc. There is a detailed schedule covering bench testing, rack loading, wiring, pre-installation checkout, through field installation The system will be ready 11/30

11/30/07

Hamid Shoaee Control System Installation 3/16/ Vacuum controls uses BC1 design, with detailed procurement list in place

Vacuum controls check out by 11/20/07

Wire scanners, Collimators and BC2 motion control use the same design as BC1, and will be available 11/20/07

Networks will be ready early in October to allow Controls checkout

Hamid Shoaee Control System Installation 3/16/ Timing System The scope is to deliver triggers and timestamp data to all subsystems requiring such. The system can be split into two parts 1.Long-haul distribution of triggers from the EVG to EVRs in Linac and beyond 2.Short-haul back end consisting of the HW & SW to receive the EVG timing signal and generate triggers. This is well-understood and defined. Part 1 requires some engineering development as the event system can only have a maximum link length of 300 meters. We can daisy-chain, but only for 3 hops before exceeding the jitter budget. We need a better solution This is a tractable item and should not have a high level of risk. Another item of concern with the long-haul distribution is timing phase error due to temperature drift – a mechanism is needed to correct for this. This will need some R&D and we need to decide based on short- versus long-term requirements if users can live with this for now. We have to anyway since time is short We have a procurement for the "back end" of the timing system consisting of all the HW (fan-outs, EVRs, crates, cables) to deliver triggers to the end subsystem. The long haul procurement list is pending a design decision

Timing System Schedule

Hamid Shoaee Control System Installation 3/16/ Beam Instrumentation & Diagnostics Profile Monitors There are 3 OTRs in the LINAC: OTR21, OTR22, OTR_TCAV – These use BC1 designs and electronics Design in April, procurement in May, system test July ~ August. Toroids There are two toroids in linac: IMBC2I and IMBC2O We need to re-spin the data acquisition board for small revisions to the artwork Electronics will be ready in August for system testing Bunch Length Monitor BL21 and BL22, similar to BL11 and BL12 in BC1 Procurement in April and test in May ~ June. Dumps and Stoppers SL2 might need some new data monitoring.

Hamid Shoaee Control System Installation 3/16/ Beam Position Monitors The linac BPMs have to be upgraded for better resolution for undulator commissioning in May-June ‘08 Do we need to upgrade for the BC2,L2,L3 commissioning? Do the existing BPM electronics work at 200 pC? Do they trigger reliably at low charge? What resolution do they provide? Test next week with A-Line beam If we need the linac BPM upgrade Install 20 racks Design and install cable plant for 79 BPMs Re-spin BPM analog front-end design Fabricate and test 120 BPM chassis Install 79 BPM chassis If we can defer the upgrade We still have to install the cable plant for all of the linac BPMs in this down time Of the 17 BPMs in switchyard we will connect to only 2 And one BPM in BC2

LLRF Schedule

Hamid Shoaee Control System Installation 3/16/ BC2 Controls Risk Matrix

Hamid Shoaee Control System Installation 3/16/ Testing & Checkout Strategies For each subsystem, we will use test stands to verify the complete system Test stands currently in place include: Timing Vacuum Magnet power supplies Motion control – wire scanners, collimator, etc. Rack loading & testing Need to accomplish as much as possible in B024 prior to Sept. transport to field site. In-field loading (Davis-Bacon) and intra-rack cabling is less efficient.

Hamid Shoaee Control System Installation 3/16/ Rack Assembly Area

Hamid Shoaee Control System Installation 3/16/ Issues & Concerns Schedule & Resources Schedule is very tight, just fits in down time Controls is the systems “integrator” – delays in other systems directly impact our installation Cable Plant Installation Coordination of activities with other installation groups is very important and could jeopardize schedule Linac BPM upgrade could be an added challenge System Functionality Timing System – small concern BPM, Toroid – need verification of design

Hamid Shoaee Control System Installation 3/16/ Summary Controls in general is in good shape for 2007 installation No major design or production issues dominate the plan The schedule is challenging with little float While a large number of sub-systems will be installed on time, some will need attention to stay on schedule