Build to Cost Meeting: Goals, Agenda & New Directions Peter Wizinowich NGAO Team Meeting September 11-12, 2008.

Slides:



Advertisements
Similar presentations
Strategic Planning Process: An Overview
Advertisements

Flow-down of Strategic Priorities to Annual and 5-year WMKO Plan Taft Armandroff Hilton Lewis September 18, 2009 Taft Armandroff Hilton Lewis September.
Calista AVCP Regional Energy Plan. Preliminary Planning and Stakeholder Involvement Resource Inventory and Data Analysis Develop and Review Draft Energy.
Program Management Office (PMO) Design
Preliminary management plan for PACE SDT What are the Goals of PACE? The goals of the PACE mission are: 1-Extend key climate data records on ocean color.
Chapter 2 The Analyst as a Project Manager
NGAO Construction Project Cost Estimation: Initial Thoughts Richard Dekany NGAO Team Meeting #12 December 13, 2007.
Science Group: Status, Plans, and Issues Claire Max Liz McGrath August 19, 2008.
W. M. Keck Observatory’s Next Generation Adaptive Optics Preliminary Design & Path Forward Peter Wizinowich, Sean Adkins, Rich Dekany, Don Gavel, Claire.
NGAO System Design Review Response Peter Wizinowich, Rich Dekany, Don Gavel, Claire Max for NGAO Team SSC Meeting June 18, 2008.
NGAO System Design Phase Update Peter Wizinowich, Rich Dekany, Don Gavel, Claire Max, Sean Adkins for NGAO Team SSC Meeting February 20, 2008.
NGAO Instrumentation Overview September 2008 Updated Sean Adkins.
1 NGAO Instrumentation Studies Overview By Sean Adkins November 14, 2006.
WMKO Next Generation Adaptive Optics: Build to Cost Concept Review Peter Wizinowich et al. ~ March 20, 2009 February 5, 2009 DRAFT.
Trying to connect WBSs with people and phases Relevant questions to my work: How the realistic NGAO strategies will/should affect the work in progress?
PALM-3000 Management Update A. Bouchez Team Meeting #9 10/22/2008.
Functional Requirements Status and Plans Christopher Neyman W. M. Keck Observatory Viswa Velur California Institute of Technology Keck NGAO Team Meeting.
NGAO Report February 18, 2009 Waimea NGAO Report February 18, 2009 Waimea P. Wizinowich for the NGAO Team.
What should we propose to ATI? Peter Wizinowich NGAO Team Meeting September 11-12, 2008.
1 Keck NGAO Proposal: Management Overview Presenter: P. Wizinowich SSC Meeting June 21, 2006.
NGAO System Design: AO System (WBS 3.2) & Laser Facility (WBS 3.3) Design Inputs & Outputs Peter Wizinowich NGAO Team Meeting #9 August 24, 2007.
Build to Cost Directions & Guidelines Peter Wizinowich SSC Meeting November 3, 2008.
NGAO Meeting #3 Introduction NGAO Meeting #3 Peter Wizinowich December 13, 2006.
Planning “Science Operations” tasks for the PD phase NGAO PD Phase D. Le Mignant W. M. Keck Observatory 08/19/2008.
NGAO Management Update Peter Wizinowich NGAO Meeting #11 November 5, 2007.
NGAO System Design Phase Management Report - Replan NGAO Meeting #6 Peter Wizinowich April 25, 2007.
NGAO Team Meeting Management Peter Wizinowich May 26, 2009.
NGAO System Design Phase System & Functional Requirements Documents NGAO Meeting #6 Peter Wizinowich April 25, 2007.
NGAO: Cost Comparison with First Light TMT AO Peter Wizinowich, Richard Dekany, Don Gavel with input & review by Brent Ellerbroek SSC Meeting November.
NGAO Team Meeting Management Peter Wizinowich March 19, 2009.
System Architecture WBS 3.1 Mid-Year Replan Richard Dekany NGAO Team Meeting #6 April 25-26, 2007 UCSC.
Pertemuan Matakuliah: A0214/Audit Sistem Informasi Tahun: 2007.
Major Management & Systems Engineering Ideas for Reducing Costs Peter Wizinowich NGAO Team Meeting September 11-12, 2008.
NGAO Meeting #5 Introduction NGAO Meeting #5 Peter Wizinowich March 7, 2007.
WMKO Next Generation Adaptive Optics: Build to Cost Concept Review Peter Wizinowich et al. December 2, 2008 DRAFT.
NGAO Instrumentation Preliminary Design Phase Planning September 2008 Sean Adkins.
Functional Requirements for NGAO Christopher Neyman W. M. Keck Observatory NGAO Team Meeting #9 August 24, 2007.
Trade Study Report: NGAO versus Keck AO Upgrade NGAO Meeting #5 Peter Wizinowich March 7, 2007.
Build to Cost Meeting: Major NGAO system cost savings ideas Don Gavel NGAO Team Meeting September 11-12, 2008.
Project Plan Development
Overview of the National Science Foundation (NSF) and the Major Research Instrumentation (MRI) Program Office of Integrative Activities National Science.
GMT Instrument Development Gary Da Costa ANU Representative GMT Science Advisory Committee.
October 24, 2000Milestones, Funding of USCMS S&C Matthias Kasemann1 US CMS Software and Computing Milestones and Funding Profiles Matthias Kasemann Fermilab.
NCSX Management Overview Hutch Neilson, NCSX Project Manager NCSX Conceptual Design Review Princeton, NJ May 23, 2002.
BROOKHAVEN SCIENCE ASSOCIATES National Synchrotron Light Source II Project Management Jim Yeck Deputy Director (Project Management)
OFFICE OF SCIENCE 1 3. Cost Estimate Gines, Fisher 2.Are the estimated cost and proposed schedule ranges realistic, consistent with the technical and budgetary.
1 BROOKHAVEN SCIENCE ASSOCIATES NSLS-II Project Baseline Jim Yeck NSLS-II Deputy Project Director NSLS-II PAC Meeting November 20, 2007.
Executive Session Director’s CD-3b Review of the MicroBooNE Project January 18, 2012 Dean Hoffer.
GOVERNOR’S EARLY CHILDHOOD ADVISORY COUNCIL (ECAC) September 9, 2014.
K. Y. LoEVLA Advisory Committee Meeting September 6-7, 2007 Charge to the Committee K. Y. Lo.
SAGE meeting Socorro, May 22-23, 2007 EVLA Science Operations: the Array Science Center Claire Chandler NRAO/Socorro.
DOE Stanford Site Office Office of Science U.S. Department of Energy 1 U.S. Department of Energy’s Office of Science Office of Science Review of the LCLS.
Module 5 Session 5.2 Visual 1 Module 5 Refining Objectives, Scope, and Other Project Parameters Session 5.2 Reviewing the PAR and refining key project.
Atlantic Innovation Fund Round VIII February 5, 2008.
1 Investing in America’s Future The National Science Foundation Strategic Plan for FY OPP Advisory Committee 10/26/06.
Edison Advanced Manufacturing Program (AMP) Webinar James Ruble Ohio MEP Center Director.
Keck Next Generation AO Next Generation Adaptive Optics Meeting #2 Caltech November 14, 2006 P. Wizinowich for NGAO Executive Committee.
Homestake DUSEL Project Management and Systems Engineering Richard DiGennaro LBNL April 20, 2007.
Strykowsky 1Office of Science Review August 15, 2007 Office of Science Project Review NCSX August 15-17, 2007 Cost and Schedule Ron Strykowsky.
Data Infrastructure Building Blocks (DIBBS) NSF Solicitation Webinar -- March 3, 2016 Amy Walton, Program Director Advanced Cyberinfrastructure.
GAO’s Cost and Schedule Assessment Guides U.S. Government Accountability Office Applied Research and Methods Cost Engineering Sciences Jason T Lee, Assistant.
PROPOSED STRATEGIC PLANNING PROCESS DECEMBER 3, 2014 Port of Port Angeles.
Governor’s Office of Emergency Services 1 The Governor’s Office of Emergency Services Application and Benefit Cost Analysis (BCA) Training.
Rob Connatser NSS Instrument Work Packages and XLPM.
Camera PDR/CD1 Planning 19 September 2008
Cost Estimating Investment Planning and Project Management
WGARM Appraisal Decision Assistance Phase 1, Dec. 2002
Template Guidelines Please use this template to create your LDRD presentation- we highly recommend that you address all aspects of the proposal as outlined.
Click to add title Planning for LSST Verification George Angeli LSST All Hands Meeting Tucson August 15, 2016.
Preliminary Project Execution Plan
Presentation transcript:

Build to Cost Meeting: Goals, Agenda & New Directions Peter Wizinowich NGAO Team Meeting September 11-12, 2008

2 Presentation Sequence Goals of Meeting 1.First step in design to cost –Identify core science & Observatory requirements –Identify base NGAO system 2. Planning for Internal Review of Build to Cost concept –Identify concept review success criteria –Identify tasks & schedule leading up to review Agenda Build to Cost (B2C) –Directions & Guidelines from Directors –Implications –Concept review success criteria –Plan

3 New Directions & Guidelines $60M cost cap in then-year dollars –From start of system design through completion –Includes science instruments –Must include realistic contingency –Cap of $17.1M in Federal + Observatory funds ($4.7M committed) Reviews –NFIRAOS cost comparison report at Nov/08 SSC meeting To better understand the fidelity of the SDR costing –Internal review of build to cost concept –Report on internal review no later than Apr/08 SSC meeting

4 Implications of New Directions & Guidelines New work required to reduce costs to fit in $60M cap –NGAO estimate at SDR, plus SD phase, ~ $53M (then-year $) –Science instrument estimate at proposal ~ $27M (then-year $) –Need to provide a major breakthrough in science capability for $ Need Science Advisory Team New work required on science instruments –Cost cap requires NGAO project to integrate all costs & planning including instruments During PD phase, instrument program management will continue for instruments, but integrated with NGAO (moved under NGAO project management at the same level as WMKO, COO and UCO project management; see Fig. 1 of NGAO PD phase SEMP) This will be re-evaluated for future phases during PD phase –Need to develop at least system designs, preferably preliminary designs, & costs during the NGAO PD –Need to identify funds & people for this (none in WMKO FY09 plan) & determine impact on NGAO PD plan

5 Implications of New Directions & Guidelines Report/Reviews –NFIRAOS cost comparison already planned –Cancel phased implementation & descopes review Need something for PDR, but not for build to cost concept review –Need success criteria, & plan to prepare, for build to cost review Budget –Cost cap does not need to include funding contingency –Team expected to raise up to $12.4M through government proposals, plus support proposals to private foundations –Do we charge indirect costs to government funding? Could reduce cost cap unless indirect costs not included in cost cap or we can use this infrastructure money –Can we place long lead procurements after PDR? Impacts schedule & then-year dollars

6 Build to Cost Concept Review Success Criteria –We have a believable approach to producing an NGAO facility within the cost cap –We have dealt with contingency properly –We have made the proper science benefit choices Assumptions –We will use our SD cost estimate refined by the NFIRAOS cost comparison –Better cost estimates will be produced for the PDR

7 Draft B2C / Cost Comparison Schedule

8 Science Instruments “Management Path Forward” Need to identify: minimum NGAO facility including science instruments science instrument success criteria for PDR resources needed for PD phase funds to support PD phase instrument work personnel to support PD phase instrument work near-term instrument project plan PD phase instrument project plan Will need to include: supporting B2C process further development of cost estimates

9 Science Instruments “Path Forward” Priorities –Support PDR success Design and build to cost objectives Systems engineering goals Interface definitions –Move instrument designs forward Address most challenging design aspects Develop firm interface definitions with AO system Support other design activities Develop full plans for design and fabrication Initial Plan –Limited in scope due to funding uncertainty –Focused on “minimum” needs to support AO system design –Pragmatic, based on heritage designs and proven concepts –Takes advantage of design overlaps between imagers –Seeks to develop synergy for probe arms between TT and d-IFS

10 Summary Further discussion of meeting goals? 1.First step in design to cost –Identify core science & Observatory requirements –Identify base NGAO system 2. Planning for Internal Review of Build to Cost concept –Identify concept review success criteria –Identify tasks & schedule leading up to review Further discussion of cost guidelines or path forward? Let’s take this opportunity to brainstorm & identify a successful path forward. Agenda

11 Cost Comparisons