MICE RF TEST STAND Major Milestones (2006) –Testing of BURLE 4616 circuit September 2006 –Testing of 4616 circuit with full amplitude and phase control.

Slides:



Advertisements
Similar presentations
ILCTA-MDB RF Power Status 9/21/06 Reid 1 ILCTA-MDB Status 1.3 GHz RF Power Meson Detector Building 3.9 GHz RF Power A0 Building September 21, 2006 [John.
Advertisements

Andrew Moss ASTeC MICE Project Board 28 th June 2011 MICE RF System.
Project Managers Update Roy Preece Particle Physics Department, STFC MICE Video Conference, 18 th September 2014.
BEPCII RF POWER SYSTEM RF group, IHEP Sep ~ April 1.The 1 st transmitter had finished installing,commissioning and SAT (Site Acceptance Test).
MICE Refurbishment of CERN RF equipment for MICE M. Vretenar, CERN AB/RF.
Collaboration meeting, RAL, 4 th – 7th November 2009 Andrew Moss ASTeC Collaboration meeting, RAL, 10 th – 13 th november 2009 MICE RF Amplifier Status.
Andrew Moss Daresbury Laboratory Collaboration Meeting th 19 th October 2012 RAL MICE RF System review.
Andrew Moss Daresbury Laboratory August 2013 Latest results of MICE amplifier testing.
MICE RF & Controls Paul Drumm. RF Layout 2 MW Amplifier Master Oscillator Controls etc 201 MHz Cavity Module 2 MW Amplifier 201 MHz Cavity Module CERN.
THE MICE RF SYSTEM J.F.Orrett* A.J.Moss, ASTeC, Daresbury Laboratory, WA4 4AD, UK Accelerator Science and Technology Centre
Daresbury MICE Progress Andrew Moss Joe Orrett Peter Corlett.
Ion source RF system Andy Butterworth BE/RF Mauro Paoluzzi BE/RF 14/11/2013Linac4 ion source review.
Andrew Moss ASTeC 7 th December 2011 MICE RF System.
Andrew Moss Daresbury Laboratory Collaboration Meeting th -16 th February 2013 Coseners House MICE RF HP System rprogress.
ILCTA_NML Progress at Fermilab Jerry Leibfritz September 10, 2007.
LARG week 07/01 Paul Poffenberger University of Victoria Endcap Feedthrough Production at Victoria Status Summary.
1 MICE-Video Conference Status of MICE Hall Contents: General status Electrical Mechanical Preparing for Steps II & III Risks and worries Andy Nichols,
1 MICE RF Daresbury Laboratory Support Joe Orrett - ASTeC.
MICE: overview K. Long, 18 March, Contents ► Introduction ► Beam line ► Infrastructure ► MICE steps ► Phase II (comment) ► Conclusions.
Control and Monitoring System / EPICS Pete Owens Daresbury Laboratory.
P. 1Mario Deile – TOTEMino: Infrastructure Status and Schedule Mario Deile Zone 2.Gas system 3.Cabling 4.Cooling water 5.Counting-Room 6.Safety.
Building for Learning Project Photo Progress Report 3 October 2009 – November 2009 Project commencement 21 st September 2009.
LBT Q Engineering Review DYB. 26-Oct-2007LBT Q Engineering Review Highlights (Q3/2007) Currently in Commissioning Phase Currently in Commissioning.
MOM Report Galina Vankova RAL, MICE Video Conference.
RF power & FPC status Eric Montesinos, CERN BE-RF on behalf of all people involved, great thanks to all of them !
MICE RF – TIARA and General Progress Tim Stanley RAL 5 June 2013.
Andrew Moss ASTeC Collaboration meeting CM29 15 th - 18 th February 2011 MICE RF System.
1 paul drumm, 19 th May 2004 MICE RF By Phone at 16:00 FNAL: Al Moretti LBNL: Derun Li
Electrical Integration CM38 Steve Griffiths & Ian Mullacrane.
February NSTX-U Team Meeting. Engineering Operations Feb. 11, 2014 NSTX-U In-Vessel installations and Calibrations to conclude in late March (3/28/2014)
I Wilmut CCLRC1 End-cap Engineering 8 September 2004 Ian Wilmut, RAL.
Electrical & Control Power Supplies Trevor Hartnett.
July LEReC Review July 2014 Low Energy RHIC electron Cooling Al Pendzick LEReC Civil Construction.
Andrew Moss ASTeC CM32 9t h February 2012 RAL MICE RF System.
MICE RF System Power Supplies, Control and Monitoring Status report February 2012 Chris White, STFC Daresbury Laboratory MICE Collaboration Meeting CM32,
1 MICE Hall and Infrastructure - Progress since CM18 Chris Nelson MICE CM19 Oct 2007.
September 19-20, 2007 L. Snydstrup Controls, Diagnostics, Vacuum, Cooling Systems, Installation DOE Annual Review Controls, Diagnostics, Vacuum, Cooling.
Proton Improvement Plan Keith Gollwitzer January 5th, 2015 All Experimenters’ Meeting 11/5/2015Gollwitzer AEM.
Decay Solenoid – what do we have to do to make it work?
Gas System production for LHC detectors Stefan Haider EP / TA1 - Gas.
MICE Project Report Alan Bross (for Paul Drumm). Project Issues ● Key dates: – ISIS Synchrotron start-up scheduled for 1st August ● Shielded area around.
Summary Plans Content Module assembly at CERN and Dubna Readout DAQ Procurement Stacking Summary.
LIU-SPS RF Power upgrade | 09 December 2015.
Andrew Moss ASTeC TIARA Mid term meeting 12 th 14 th June 2012 CIEMAT ICTF Progress on the MICE RF System.
MICE RF System Overview Derun Li Center for Beam Physics Lawrence Berkeley National Laboratory Andrew Moss STFC Daresbury Laboratory MICE UK.
RF Review CM37 Andrew Moss. Amplifier results at Daresbury 2MW at 35kV, good efficiency and gain.
Gas system for NA62 Straw detector Roberto Guida On behalf of Gas Service Team NA62 Straw working meeting, March 26, 2012 Outline: P&I Drawing Schedule.
MICE RF Power Status Paul Drumm ~ Sunday August 1 st 2004.
LS1 Mid-Point Status Report of the PSB Low Level RF, Transverse Feedback & High Level RF. Autumn 2013 A. Akroh, M.E. Angoletta, A. Blas, L. Arnaudon, A.
ACS news RF cabling campaign: DONE Final tests cavity tuning motor (ctrl): in progress recabling software upgrade Water cooling: ADT static pressure test:
NML - RF Unit Test Facility Jerry Leibfritz Fermilab.
MICE RF – Installation at RAL Tim Stanley RAL 7 November 2013.
MICE RF – Installation at RAL Tim Stanley, MICE RF Engineer, RAL 2 June 2014.
201 MHz Cavity Plans Derun Li Center for Beam Physics Lawrence Berkeley National Laboratory February 11, 2011 MAP Friday Video Conference Meeting.
HiLumi-LHC/LARP Crab Cavity System External Review 5-6 May 2014, BNL SPS - RF Power and Coupler status Erk Jensen, Eric Montesinos, CERN BE-RF.
CV Activities for PSB-LIU POPS-B (new MPS for the PSB-LIU) B 245 PSB Demi water cooling plant Stefano Moccia, EN-CV Meeting 07/03/16.
Upgrade activities DT-LHCb coordination meeting 14 March 2016.
ILCTA_NML Progress at Fermilab Jerry Leibfritz August 16, 2007.
ILCTA-MDB RF Power Status 4/27/06 Reid 1 ILCTA-MDB Status 1.3 GHz RF Power 3.9 GHz RF Power Meson Detector Building April 27, 2006 [John Reid]
10/3/2014 Proton Source Update. RIL Update Source B is back in place and under vacuum It will be baked over the weekend It will be started early next.
P. Bosland CEA-Saclay Collaboration Board meeting Copenhagen 14/04/ Status of the French activities under the responsibility of CEA Philippe CHOMAZ.
Andrew Moss ASTeC, Daresbury Laboratory October 2010 MICE RF Amplifier Status.
PSB and PS test systems status. M. Haase September 14 th Finemet Review.
S A Griffiths CM42 June 2015 Electrical & Control.
Update on the PSB Cooling and Ventilation Systems
MICE RF System Power Supplies, Control and Monitoring Status report
MICE Target Report Video Conference 29/11/07
ACS news Circulator TCU: control tests in progress All cavity racks
Vacuum Controls Stephen Schuh Tom Porter 25 October 2006
Full Service Plumbing Columbus, Ohio. plumbing The art and science of creating and maintaining sanitary conditions in a building used by humans. It is.
Presentation transcript:

MICE RF TEST STAND Major Milestones (2006) –Testing of BURLE 4616 circuit September 2006 –Testing of 4616 circuit with full amplitude and phase control November 2006 –Work beginning on refurbishment of TH116 circuit September 2006

Current progress 4616HT Power supply –Power supply is being constructed by DL power supply group, and is progressing well. –All major components are on order, or have been delivered Auxiliary Rack –Heater control system has been purchased –Screen pulser is currently being designed. –PLC control system has been procured ready for programming

HT power supply Rack 4616HT Power supply rack –Construction almost finished

Low level RF Low level components are under investigation –Oscillator on the basis of DDS (Direct digital synthesis) has been procured –RF detector prototypes have been produced –Basic low level system components are available (no phase and gain control) –Full Low level system to be produced by NOV 2006 (with phase and gain control)

High Power Coaxial Components Directional coupler and water load are now on site. –Ready for installation

4616 circuit refurbishment Circuit is in surprisingly good condition! –Flexible water pipes to be replaced –Rubber o-rings to be replaced –Redundant ancillary equipment has been removed. –Minor repairs to finger stock in progress. –Cleaning of RF surfaces in progress.

Tubes 2 x BURLE 4616 Tubes Have been delivered, and are ready for installation

Test Area Area is still being prepared for MICE equipment

Test area Water panel is now in place. Electrical services will be installed in the next few weeks