Patrick Krejcik LCLS April 16-17, 2007 Breakout Session: Controls Controls Commissioning Experience.

Slides:



Advertisements
Similar presentations
XTCAV X-Band Transverse Deflecting Cavity Project Overview Patrick Krejcik Yuantao Ding, Joe Frisch.
Advertisements

LCLS Control System Overview Mike Zelazny SLAC ICD Software Department Accelerator Directorate.
R. Akre, P. Emma, P. Krejcik LCLS April 29, 2004 LCLS RF Stability Requirements LCLS Requirements The SLAC Linac.
S. Smith LCLS Facility Advisory April 16, BPMs and Toroids Facility Advisory Committee April 16, 2007 System overview.
Paul Emma LCLS FAC April 16, Initial Experience with Injector Commissioning P. Emma, et al. Facilities Advisory Committee.
Patrick Krejcik LCLS April 29, 2004 Breakout Session: Controls Physics Requirements Overview P. Krejcik.
Hamid Shoaee High Level Physics 20 April 2006 High Level Physics Applications Update on Plans, New Directions Fairley,
Patrick Krejcik LCLS June 16-18, 2008 High Level Applications Facility Advisory Committee Meeting June 17, 2008 Applications Team.
June 17, 2008 LCLS FAC D. Fairley MATLAB Feedback Phase II Commissioning.
Mike Zelazny FAC April 17 th, 2007 Matlab Applications Image Management Bunch Length Measurement Feedback Software Engineers.
Hamid Shoaee LCLS Facility Advisory Committee April Control System Overview April 16, 2007 Hamid Shoaee for the LCLS Controls.
Diane Fairley High Level October 24-28, 2005 High Level Physics Applications LCLS Week / FAC October 24-28, 2005.
Dayle Kotturi LCLS Diagnostics and Commissioning Workshop September 23, 2004 LCLS Controls and Data Acquisition September 23, 2004.
LCLS Linac System Management Linac Coherent Light Source Stanford Synchrotron Radiation Laboratory Stanford Linear Accelerator Center.
SNS Integrated Control System SNS Machine Protection System EPICS Workshop April 27, 2005 Coles Sibley.
Availability Performance of LCLS X-Ray FEL at SLAC William Colocho for the LCLS team.
Hamid Shoaee LCLS FAC Controls June 17, LCLS Control System Personnel Linac & BC2 Controls progress LTU, Dump Controls.
David H. Dowell Injector April 29-30, 2004 LCLS Injector Overview D. H. Dowell, SLAC FAC Review April 29-30, 2004 Injector.
Ron Akre, Dayle Kotturi LCLS LLRF April 16, 2007 Linac.
Hamid Shoaee LCLS FAC Review – October Control System Overview Hamid Shoaee Controls System Manager Injector control system commissioning & Support.
November 12, 2008 Controls Software D. Fairley LCLS Feedback.
Oct. 30, 2007 LCLS FAC D. Fairley MATLAB Feedback Phase II Commissioning.
Henrik Loos High Level 17 June 2008 High Level Physics Applications for LCLS Commissioning Henrik Loos.
Diane Fairley High Level October High Level Applications FAC Review October 12, 2006 High Level Applications.
Hamid Shoaee LCLS Control April 20, 2006 LCLS Control System Organization & Integration with the rest of the lab, Accelerator.
Patrick Krejcik LCLS November 11-12, 2008 SLAC National Accelerator Laboratory 1 Post-commissioning Controls Enhancements.
Hamid Shoaee Accelerator Readiness Dec. 2, ‘08 SLAC National Accelerator Laboratory Controls Department LCLS Maintenance.
8/21/2015J-PARC1 Data Management Machine / Application State Data.
Hamid Shoaee LCLS Control April 20, 2006 LCLS Control System Controls Organization Overview A Progress Report Hamid Shoaee.
SNS Integrated Control System EPICS Collaboration Meeting SNS Machine Protection System SNS Timing System Coles Sibley xxxx/vlb.
Control and Monitoring System / EPICS Pete Owens Daresbury Laboratory.
Managed by UT-Battelle for the Department of Energy Kay Kasemir ORNL/SNS Jan Control System Studio, CSS Overview.
Adrian Oates Daresbury Laboratory ALICE Control System July 08.
K. Luchini LCLS Controls, July 1, 2005 SLAC Aware IOC EPICS Magnet Functional Requirements Introduction Magnet Functions.
Transverse Profiling of an Intense FEL X-Ray Beam Using a Probe Electron Beam Patrick Krejcik SLAC National Accelerator Laboratory.
Henrik Loos LCLS 6 February 2009 SLAC National Accelerator Laboratory High Level Physics Applications for LCLS Commissioning.
Dayle Kotturi System Concept Review/Preliminary Design Review November 16, 2005 LLRF Outline System Concept Review Requirements.
LCLS Control Group EPICS Collaboration April 27, 2005 Controls Overview April 27, 2005 Outline Goals Status update.
Stephanie Allison LCLS Controls Software Meeting Dec 6, 2007 How To Set Up for the Event System on an IOC with an EVR(s) Assumes.
Laser Heater Controls Overview 21 August 2008 Matt Boyes Laser Heater Controls Design Overview EPICS IOC Team Meeting Matt Boyes.
1 Franz-Josef Decker 1 Multi-Bunch Operation for LCLS Franz-Josef Decker March 17, Definitions and goals multi-bunch within.
1 P. Chu 1 Adapting XAL for LCLS EPICS Meeting, Vancouver Adapting XAL for LCLS Paul Chu - SLAC May 1, 2009.
LCLS Control Group FAC – 06 Installation October 27/28, Plans for 2006 Installation October 27, 2005 Installation.
Current NML Layout.  Overall length of building is 72M 3 cryomodules with feed and end cans ~40M Not enough room for both photoinjector and downstream.
Patrick’s Updates - 8/30/11 (one slide for each of the following) 1.XTCAV Project 2.ASTA Gun Test Facility Instrumentation & Controls 3.Fast wire scanner.
Tuning Techniques And Operator Diagnostics for FACET at SLAC National Accelerator Laboratory Chris Melton SLAC Accelerator Operations.
Status of the AWAKE Control System Edda Gschwendtner, Janet Schmidt, Marine Gourber-Pace, Roman Gorbonosov, Peter Sherwood AWAKE Technical Board, 27 January.
Debbie Rogind Diane Fairley SLC-Aware BSAC Facility Requirements Review May 26, 2005 SLC Aware IOC BSAC* Facility Requirements Review *Beam Synchronous.
First Electrons at the Fermilab superconducting test accelerator Elvin Harms Asian Linear Collider Workshop 2015, Tsukuba 24 April 2015.
Debbie Rogind LCLS Magnet June 15, 2006 LCLS Magnet Control Challenging Design Issues Subsystem architecture, or… “How.
LCLS MPS Upgrade Gasper Jansa, Luciano Piccoli, Jeff Olsen, Garth Brown, Sonya Hoobler, Stephen Norum, Stephanie Allison, Kim Kukhee Adding BSA.
Control System Tools for Beam Commissioning Timo Korhonen Controls Division Chief Engineer April 8, 2014.
LCLS MD Downtime William Colocho June 2014 to June 2016.
LCLS Commissioning & Operations High Level Software
Operations Machine Simulator.
Slice Parameter Measurements at the SwissFEL Injector Test Facility
LCLS Commissioning & Operations High Level Software
Maintain a single control room for all accelerator programs
High Level applications development status
High Level Physics Applications for LCLS Commissioning
LCLS Injector/Diagnostics David H. Dowell, SLAC April 24, 2002
Breakout Session SC5 – Control Systems
Diagnostics RF and Feedback
Linac Diagnostics Commissioning Experience
LCLS Injector Commissioning P
Control System Overview Hamid Shoaee LCLS Control System Manager
Low Level RF Status Outline Overview showing hardware instances
Control System Overview Hamid Shoaee LCLS Control System Manager
SLC-Aware IOC Magnet Functional Requirements
High Level Physics Applications Lehman Review February 7 - 9, 2006
Presentation transcript:

Patrick Krejcik LCLS April 16-17, 2007 Breakout Session: Controls Controls Commissioning Experience

Patrick Krejcik LCLS April 16-17, 2007 First Beam LCLS commissioned a new injector with beam AND commissioned a new Control System

Patrick Krejcik LCLS April 16-17, 2007 Overview This presentation summarizes which control system components are currently working for the injector commissioning phase Screen shots from EPICS show functionality of each system Data from the Elog is shown to illustrate acquisition Comments on what works and what doesn’t are included Summary includes lessons learned and what still needs to be done

Patrick Krejcik LCLS April 16-17, 2007 Everything is accessible from this screen

Patrick Krejcik LCLS April 16-17, 2007 Beam line graphic used for most GUIs e.g. injector vacuum summary

Patrick Krejcik LCLS April 16-17, 2007 PPS Summary status displays

Patrick Krejcik LCLS April 16-17, 2007 BCS Summary status display: - Calibration of detectors not completed yet - SubBooster Interface timing “difficult”

Patrick Krejcik LCLS April 16-17, 2007 MPS - working with SLC processor and timing - ion chambers do trip beam - several MPS inputs (limit switches on obstructions) not available yet New optical fiber Loss monitor screen

Patrick Krejcik LCLS April 16-17, 2007 Conventional facilities - interfaced to EPICS controls - gun LCW temp feedback working ok at 30 Hz - need to add alarm interface for temperatures, flows etc.

Patrick Krejcik LCLS April 16-17, 2007 Timing System - see separate presentation by S. Allison - LCLS Event system and SLC Timing working in consort

Patrick Krejcik LCLS April 16-17, 2007 Laser Systems - Image Acquisition and Steering Feedback

Patrick Krejcik LCLS April 16-17, 2007 Magnet Controls

Patrick Krejcik LCLS April 16-17, 2007 Low Level RF Control

Patrick Krejcik LCLS April 16-17, 2007 Gun RF Feedback in Operation - closing the loop between PAD and PAC

Patrick Krejcik LCLS April 16-17, 2007 RF Phase Scans Data acquired with Matlab Data acquired with SCP Correlation Plot (diagnose a satellite peak from laser)

Patrick Krejcik LCLS April 16-17, 2007 Profile monitors - control and diagnostics through EDM screens

Patrick Krejcik LCLS April 16-17, 2007 Image acquisition with Matlab Gun spectrometer YAG Profile Monitor Screen Using physicist’s scripts up till now ImageManager package coming online now

Patrick Krejcik LCLS April 16-17, 2007 Beam Position Monitors - see separate presentation from S. Smith

Patrick Krejcik LCLS April 16-17, 2007 Asynchronous Beam Acquisition via SCP e.g. Gun charge vs. laser power Measured on the SCP Correlation Plot But some people still plotting data offline

Patrick Krejcik LCLS April 16-17, 2007 Beam Synchronous Acquisition is working through Matlab – example of orbit display - BSAP via the SCP coming next

Patrick Krejcik LCLS April 16-17, 2007 Motion control -BC1 chicane movers in use - next to be commissioned: wire scanners, collimators

Patrick Krejcik LCLS April 16-17, 2007 Generic Tools that are working SCP Configuration save and restore EPICS Channel Watcher Correlation plots Strip chart tools Archive Viewer Alarm handler Electronic logbook Matlab for higher level applications

Patrick Krejcik LCLS April 16-17, 2007 Strip Tool monitoring gun temperatures during RF trips

Patrick Krejcik LCLS April 16-17, 2007 Electronic logbook gives instant overview

Patrick Krejcik LCLS April 16-17, 2007 Control Room Conditions Still a Bit Cramped (first beam to end of BC1!) Reorganizing the control room layout Purchasing more workstations Injector commissioning involved 12 or more in the room, so its likely to increase as the linac and undulator systems are commissioned

Patrick Krejcik LCLS April 16-17, 2007 Summary and lessons learned Remarkable commissioning achievement for the control system Controls commissioning time was squeezed How do we ask for more? Planned BC2–linac installation is tight Improve liaison with mechanical engineering We are still learning how to handle large number of IOCs and the huge number of PVs e.g. Restoring after a reboot Large number of EDM displays can confuse operators at times (looking for a screen that may be already open) Controls group is a great TEAM!