Microsoft Project 2002 Sessions 5-6. Entering Tasks During this first session we will enter a set of tasks that comprise building a shed – data sheet.

Slides:



Advertisements
Similar presentations
Connoizor Enabling Performance for Businesses through Software Website: Contact:
Advertisements

©2003 Rolls-Royce plc The information in this document is the property of Rolls-Royce plc and may not be copied or communicated to a third party, or used.
Budget Management. 57 Budget Management Budget Development Good scheduling skills and abilities Understanding of the project scope Well developed WBS.
 Costs are planned, measured, analyzed and controlled in terms of project activities.  Expenditure for any activity is incurred evenly over the duration.
Monitoring and Control Earned Value Management (EVM)
CSSE Oct.2008 Monitoring and reporting project status Chapter 10, pages
Chapter 10: Monitoring and Controlling Change
Monitoring and Controlling
Project Cost Management
Using Earned Value Management System (EVMS) Briefing for ATC Engineering & Test Division (ACT-200) Managers and Leads.
Earned Value Management
OPMA 5364 Project Management Part 6 Project Control
Advanced Project Management Project Cost Management Ghazala Amin.
Chapter 10 Project Monitoring and Control
Project Management in Practice
Earned Value Analysis by John Cornman. Introduction “Earned Value Analysis” is an industry standard way to measure a project’s progress, forecast its.
Project Monitoring and Control. Monitoring – collecting, recording, and reporting information concerning project performance that project manger and others.
Project Management Methodology Project monitoring and control.
Controlling cost ( lecture + seminar ). Why control cost? To satisfy financial auditors and support data for the government (obligatory). To satisfy the.
1 ev14a Interactive Session 4 u Tuesday, July 17 7pm to 10pm u Build a sqa plan for the dental office software u Assume a 3-person, development team, a.
1. Earned Value Analysis (EVA) Earned value is a measure of progress enables us to assess the “percent of completeness” of a project using quantitative.
Chapter 4: Schedule, cost, and situation analysis (pt. 2) ISE 443 / ETM 543 Fall 2013.
Cost Estimation and Budgeting. Cost management Data collection & cost estimation Cost accounting Cost controll Copyright © 2010 Pearson Education, Inc.
Earned Value JOEL VIRAY TOPICS What is Earned Value Management? –Why do I need it? –How do I do it? Earned Value Reporting Earned.
Monitoring and Information Systems
Chapter 15 Cost Control.
EARNED VALUE MANAGEMENT (EVM)
Controlling cost 2 ( seminar ). Budget preparation Data collection WBS Cost centres Indirect expenses & the use of hammocks –direct –overhead (indirect)
Earned Value Management System (EVMS). Given: –total budget of $100,000 –12 month effort –produce 20 units Status: –spent to date: $64,000 –time elapsed:
10/19/ :26 AM 1 Project Cost Control. 10/19/ :26 AM 2  Controlling involves making sure that the results achieved are in line with the planned.
Earned Value SOS section Sp8Jan24ev3. Earned Value Analysis One approach to measuring progress in a software project is to calculate how much.
Earned Value management This presentation is just a short introduction to a few terms and concepts. I am sure there will be training sessions in the next.
Chapter 9 Project Development. What to manager Client experience  Clients are very important  Happy or not is largely dependent on their expectations.
Project Management Part 6 Project Control. Part 6 - Project Control2 Topic Outline: Project Control Project control steps Measuring and monitoring system.
1 Project Management – Unit 4 – Part 1 Cost Model ACWP: Actual cost of work performed: Actual costs in performing the work so far. BCWP: Budgeted cost.
Stage III: Project Execution and Control Earned Value Analysis B: Chapter 8: pages B: Chapter 12: the entire chapter.
Advanced Project Plan Tracking Lesson 15. Skills Matrix SkillsMatrix Skill Record actual start, finish, and duration values of tasks Enter actual start.
Project Cost Management
Mohawk Vehicle - MEGA HERZ ELEC & VEN - MOH-2 F C-0050 J:\CS40\Data Analysis\- Standard Analysis Package/Sample Standard Analysis Package.
Ev3 1 In House Software Development:… Verner, etal IEEE Software, Jan?feb 2005.
Introduction To Earned Value November 14, Definition Earned Value is a method for measuring project performance. It compares the amount of work.
Department of CS & Eng. MSSE Program, © Fissure 1 SOFTWARE PROJECT MANAGEMENT COURSE Executing, Monitoring and Controlling Session #7.
Earned Value Analysis Tracking Project Progress. Introduction | Components | Project Scenario | Values | Calculations | Forecasts | Summary l What Is.
1 Earned value analysis Planned value (PV) or Budgeted cost of work scheduled (BCWS) – original estimate of the effort/cost to complete a task (compare.
EVM – Do You Really Know What the Numbers Mean? Booz | Allen |Hamilton Seth Huckabee EVP, PMP, PMI-SP.
1 Understanding Earned Value in Under an Hour Breakout Session # A11 Name: Wayne Brantley, MS Ed, PMP, ITIL Senior Director of Professional Education.
Information Technology Project Management, Seventh Edition Note: See the text itself for full citations.
Schedule Control (Earned Value)
Project Cost Con trol. 1.To identify those work types having excessive costs and to give an indication of how serious those overruns are. 2.To forecast.
What Is It ? Why Do I Need It ? How Do I Do It? Earned Value Analysis.
Agenda ‒ Cost Management ‒ Cost Budgeting ‒ Cost Control Learning Goals 1.Cost Control 2.Earned Value Management.
Project Management 1 Project Control. Project Management 2 Topics Project Control Status Reporting Earned Value Analysis.
Earned Value Management
Measuring Progress HNC Project Management. Measuring Schedule Performance Break project tasks up into small work units. Work units that are too large.
Earned Value Analysis by Miles M. Hamby, PhD Copyright©2014 Miles M
Project Monitoring
TOPIC-8B- PROJECT COST CONTROL
CHAPTER:7 Project Cost Management
Earned Value Management
5. Cost resources & PLAN DURATION
Project Cost Management
Work Packages / Deliverables Completed
Progress and Performance Measurement and Evaluation
Earned Value - What is it
An Introduction to Earned Value Performance Measurement
Earned Value Measures Planned Value (PV) Earned Value (EV)
فرآيند كنترل پروژه.
Earned Value Management
5. Cost resources & PLAN DURATION
5. Project PLAN & cost estimation
Presentation transcript:

Microsoft Project 2002 Sessions 5-6

Entering Tasks During this first session we will enter a set of tasks that comprise building a shed – data sheet will be supplied

Cost Data The following slides we will go through cost terms and some data These terms will be used in future weeks

Cost Data Overview Factors Earned Value 50/50 Rule Examples

Factors BCWS - Budgeted Cost Work Scheduled - Budget entry numbers ACWP - Actual Cost Work Performed - Actuals, what you spent BCWP - Budgeted Cost Work Performed - Earned Value, what you have accomplished

Factors BAC - Budget at Completion - the total of all the budget numbers, the bottom line EAC - Estimate at Completion - based on your rate of expenditures, what you probably will spend by the end of the project CV - Cost Variance, BCWP - ACWP = CV SV - Schedule Variance, BCWP - BCWS = SV

Factors CPI - Cost Performance Index BCWP/ACWP = CPI SPI - Schedule Performance Index BCWP/BCWS = SPI

BCWP - Earned Value Calculating Earned Value should be easy if you set up your budget correctly. Earned Value or BCWP is the value of what you have produced. If you have produced $500,000 worth of the $1,000,000 project, your BCWP is $500,000 or 50%.

BCWP - Earned Value Let’s use a wall as an example:  There are $50 per foot in materials  It will take 4 labor hours per foot to build at $20/hour  There will be $200 in other labor charges  There is a crew of four working  The wall is 80 feet long  On the first and last days the crew has 8 hours of set up and tear down time each

BCWP - Earned Value Budget  Materials - $50 X 80 = $4000  Labor for wall - 4 X 80 X $20 = $6400  Labor for set up and tear down - 16 X $20 = $320  Additional Labor - $200  Total = $10,920

Budget for Wall

Wall Question  How would you do this budget different?

Actual Construction

Actuals For Wall Day 1 Set up – 6 hours 10 feet done Materials - 10 X $50 = $500 Labor = $ (32 X $20) = $ Total = $ BCWS = $ ACWP = $ BCWP = ?

BCWP How would you allocate the budget so you could determine BCWP?

BCWP Easiest is to take total costs and prorate over some easy thing to measure, like the length of the wall. $10,920/80 = $ / foot completed

Actuals For Wall Day 1 Set up – 6 hours 10 feet done or a value of (10 X $136.50) = $ or $ /10,920 complete = 12.5% complete Materials - 10 X $50 = $500 Labor = $ (32 X $20) = $ Total = $ BCWS = $ ACWP = $ BCWP = $

Actuals for Wall - Day 1 BCWS = $ ACWP = $ BCWP = $ CV = BCWP - ACWP = = $ Positive so it is favorable SV = BCWP - BCWS = = $ Positive so it is favorable CPI = BCWP/ACWP = 1365/ = or for every dollar that is spent, we earn $1.17 in value SPI = BCWP/BCWS = 1365/ = 1.42 or we are doing about 40% better on schedule than anticipated. EAC = BAC/CPI = $10,920/1.17 = $

Actuals For Wall Day 2 It rained - no work performed Labor = $ (32 X $20) = $ Total = $ BCWS = $ ACWP = $ BCWP = $

Actuals for Wall - Day 2 BCWS = $ ACWP = $ BCWP = $ CV = BCWP - ACWP = = - $ Negative so it is unfavorable SV = BCWP - BCWS = = - $ Negative so it is unfavorable CPI = BCWP/ACWP = 1365/ = 0.74 or for every dollar that is spent, we earn $0.74 in value SPI = BCWP/BCWS= 1365/ = 0.67 or we are doing much worse than we budgeted EAC = BAC/CPI = $10,920/0.74 = $

Actuals For Wall Day 3 Sunny day, crew motivated, did 14 feet today. Materials = 14 X $50 = $700 Total Done = 24 BCWP = 24 X = $ Labor = $ (32 X $20) = $ Total = $ BCWS = $ ACWP = $ BCWP = $

Actuals for Wall - Day 3 BCWS = $ ACWP = $ BCWP = $ CV = BCWP - ACWP = = $71.46 Positive so it is favorable SV = BCWP - BCWS = = $ Positive so it is favorable CPI = BCWP/ACWP = 3276/ = 1.02 or for every dollar that is spent, we earn $1.02 in value SPI = BCWP/BCWS= 3276/ = 1.06 or we are doing much worse than we budgeted EAC = BAC/CPI = $10,920/1.02 = $10,705.89

S - Curves Ok, so now we can calculate the statistics Next we want to be able to graph the numbers and see where we are from a visual perspective.

S Curves S Curves are a good way to see at a glance what is going on. The following curve shows our data on a graph.

S Curves BCWS BCWP ACWP

S Curves BCWS BCWP ACWP

S Curves BCWS BCWP ACWP

S Curves BCWS BCWP ACWP

S Curves BCWS BCWP ACWP

S Curves BCWS BCWP ACWP

S Curves BCWS BCWP ACWP

S Curves BCWS BCWP ACWP

Wall Example Continued The following Excel example shows how the curves can be used.

50/50 Rule Frame has an easier way to calculate earned value. It is called the 50/50 rule. With this rule, you earned 50% of the earned value the instant you start a task and the other 50% when the task is complete.

50/50 Rule Task 1 = $50k Task 2 = $25k Task 3 = $40k

50/50 Rule Task 1 = $50k: Started so, we have earned $25k Task 2 = $25k Task 3 = $40k BCWP = ?

50/50 Rule Task 1 = $50k: Started so, we have earned $25k Task 2 = $25k Task 3 = $40k BCWP = 25K

50/50 Rule Task 1 = $50k: Started so, we have earned $25k Task 2 = $25k: Started so have earned $12.5k Task 3 = $40k BCWP = ?

50/50 Rule Task 1 = $50k: Started so, we have earned $25k Task 2 = $25k: Started so have earned $12.5k Task 3 = $40k BCWP = $37.5K

50/50 Rule Task 1 = $50k: Finished so, we have earned $50k Task 2 = $25k: Started so have earned $12.5k Task 3 = $40k: Started so we have earned $20k BCWP = $82.5K

Reminders BCWP can never exceed BCWS At the end of a project the schedule variance will always equal zero Cost variance can exceed BCWS