K. Long, 14 June, 2015 Target K. Long, Friday, 24 th April 2009
Critical path: No particular issues, but: – Vacuum tubes ready to be sent to Sheffield – Stator assembly ready for vacuum tubes at Sheffield – Weld trials successful – Parts in manufacture
Manufacturing: highlights:
Installation and commissioning schedule: Presented / discussed at Target w/s last Friday Revised version to be presented / discussed at CM24 Need to have Target w/s with ISIS in June: – Make sure manufacturing remains on track; – Discuss installation and commissioning plans; – Ensure manpower assumptions for shutdown are valid