COMP6703 : eScience Project III ArtServe on Rubens Emy Elyanee binti Mustapha Supervisor: Peter Stradzins Client: Professor Michael Greenhalgh
Background It is established in January 1994 by Professor Michael Greenhalgh, who is the client for this project A website containing mainly visual images (photos from around the world) ArtServe has attracted many users up to in July 2005
Background - Continue Problems are: lack of proper database, lack of proper search tool within the website, poor usability Previous semester, an eScience student has chosen this project and solves the problems For this semester, I will be installing and implementing Nhi Ha’s codes on the real machine and do a proper software testing to ensure its correctness and compatibility. As well as a couple of additional functions.
Requirements Installing, implementation and testing of the prototype Guest book for visitors to interact with Admin Export images and convert to appropriate presentation style
Timetable WeekDateDescriptionDeliverable 118 – 23 July- Choosing project title - Analysis of previous student’s report - Meeting with client and supervisor 225 – 29 July- Meeting with client - Analysis of previous student’s codes - Analysis of the project requirement - Analysis of current web site Aug- Draft report of project requirement - First project presentation - Presentation slides - Draft report 48 – 12 Aug- Modelling and learning of chosen techniques phase - Installing prototype on the real machine - Preparation for the testing of the prototype - Prototype installed and working - Test Plan 515 – 19 Aug- Modelling phase completed - Testing of the prototype on the real machine - System Analysis Diagrams 622 – 26 Aug- Beginning of implementation phase - Testing of the prototype on the real machine complete - Test result - Small release 729 Aug – 2 Sept- Implementation- Small release
Timetable - continue 85 – 9 Sept- Implementation- Small release 912 – 16 Sept- Mid-project result- Prototype for guest book - Draft report 1019 – 23 Sept- Comments by supervisors 1126 – 30 Sept- Implementation of comments - Usability Test conducted - Usability test result 124 – 7 Oct- Debugging - Usability test result evaluation and GUI adjustment - Usability report 1310 – 14 Oct- Documentation - Implementation continue - Small release 1417 – 21 Oct- Implementation completed- All system components 1524 – 28 Oct- Documentation - User Guide / System documentation - Final testing - User Guide documentation - Final test result 1631 Oct – 4 Nov- Project Presentation- Presentation Slides 177 – 11 Nov- Documentation 1814 – 18 Nov- Report Completed- Final version of report