Review problem 1 QP dolls, Inc., has developed a new doll it feels could turn into a “collector’s item” through proper advertisement. The PERT/ CPM network.

Slides:



Advertisements
Similar presentations
Chapter 7 Project Management
Advertisements

Project Management Projects are unique, one-time operations designed to accomplish a specific set of objectives in a limited timeframe Project managers.
Project Scheduling: PERT/CPM
Chapter 13 Project Scheduling: PERT/CPM
Chapter 9 Project Scheduling: PERT/CPM
1 1 Slide © 2008 Thomson South-Western. All Rights Reserved Slides by JOHN LOUCKS St. Edwards University.
F O U R T H E D I T I O N Project Management © The McGraw-Hill Companies, Inc., 2003 supplement 3 DAVIS AQUILANO CHASE PowerPoint Presentation by Charlie.
1 1 Slide © 2001 South-Western College Publishing/Thomson Learning Anderson Sweeney Williams Anderson Sweeney Williams Slides Prepared by JOHN LOUCKS QUANTITATIVE.
Terminology Project: Combination of activities that have to be carried out in a certain order Activity: Anything that uses up time and resources CPM: „Critical.
1 Topics to cover in 2 nd part ( to p2). 2 Chapter 8 - Project Management Chapter Topics ( to p3)
Project Scheduling Basic Approach. projectA project is a collection of tasks that must be completed in minimum time or at minimal cost. activitiesIt is.
1 1 Slide © 2005 Thomson/South-Western Q 5 – 13 x 1 = the probability that Station A will take Sitcom Rerun x 2 = the probability that Station A will take.
1 1 Slide © 2004 Thomson/South-Western Chapter 12 Project Scheduling: PERT/CPM n Project Scheduling with Known Activity Times n Project Scheduling with.
Tutorial 2 Project Management Activity Charts (PERT Charts)
Project Management Operations -- Prof. Juran. 2 Outline Definition of Project Management –Work Breakdown Structure –Project Control Charts –Structuring.
1 1 Slide © 2011 Cengage Learning. All Rights Reserved. May not be scanned, copied or duplicated, or posted to a publicly accessible website, in whole.
Project Scheduling Basic Approach. projectA project is a collection of tasks that must be completed in minimum time or at minimal cost. activitiesIt is.
MGMT 483 Week 8 Scheduling.
MGMT E-5050 Scott Corey CPAs Project Crashing Homework Solution.
1 1 Slide © 2009 South-Western, a part of Cengage Learning Slides by John Loucks St. Edward’s University.
1 7.1 Introduction A project is a collection of tasks that must be completed in minimum time or at minimal cost. Tasks are called “activities.” –Estimated.
1 1 Slide © 2005 Thomson/South-Western Chapter 10 Project Scheduling: PERT/CPM n Project Scheduling with Known Activity Times n Project Scheduling with.
1 1 Slide © 2008 Thomson South-Western. All Rights Reserved Slides by JOHN LOUCKS St. Edward’s University.
Chapter 10 Project Scheduling: PERT/CPM
1 Slide © 2005 Thomson/South-Western Chapter 10 Project Scheduling: PERT/CPM Project Scheduling with Known Activity Times Project Scheduling with Known.
Project Scheduling Professor Stephen Lawrence Leeds School of Business University of Colorado Boulder, CO
EMGT 501 HW #2 Answer. 020/3 X 3 05/601-1/62/3050/3 X 6 0-5/300-2/3-1/3180/3 (c).3/230with )3/80,0,0,3/50,3/20,0(*)*, ( solution Optimal   Z.
EMGT 501 HW #2 Solutions Chapter 6 - SELF TEST 21 Chapter 6 - SELF TEST 22.
Project Scheduling The Critical Path Method (CPM).
Project Scheduling Professor Stephen Lawrence Graduate School of Business Administration University of Colorado Boulder, CO
Project Management © Wiley 2007.
Prosjektstyring bma ACTIVITY A B C D E A 4 / 5 / 6 B 8 / 10 / 13 C 9 / 12 / 16 D 7.
OPER 576 Project Management Reducing Project Duration or Project Crashing Greg Magnan, Ph.D. May 20, 2004.
Operations Management Contemporary Concepts and Cases Chapter Fourteen Project Planning and Scheduling Copyright © 2011 by The McGraw-Hill Companies,
8-1 Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall Project Management Chapter 8.
Quick Recap Monitoring and Controlling. 2 Control Project Cost.
Project Management Chapter 8 (Crashing).
Network Planning Techniques Program Evaluation & Review Technique (PERT): Developed to manage the Polaris missile project Many tasks pushed the boundaries.
To Accompany Russell and Taylor, Operations Management, 4th Edition,  2003 Prentice-Hall, Inc. All rights reserved. Chapter 17 Project Management Part.
1 1 Project Scheduling PERT/CPM Networks. 2 2 Originated by H.L.Gantt in 1918 GANTT CHART Advantages - Gantt charts are quite commonly used. They provide.
1 1 © 2003 Thomson  /South-Western Slide Slides Prepared by JOHN S. LOUCKS St. Edward’s University.
1 1 Slide © 2005 Thomson/South-Western Chapter 10 Project Scheduling: PERT/CPM n Project Scheduling with Known Activity Times n Project Scheduling with.
8-1 Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall Project Management Chapter 8.
8-1 Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall Project Management Chapter 8.
Project Planning with PERT and CPM Chapter 14
Welcome to MM305 Unit 7 Seminar Dr. Bob Project Management.
CPM – Critical Path Method Can normal task times be reduced? Is there an increase in direct costs? Additional manpower Additional machines Overtime, etc…
Chapter 7 : Risk Management – part 2
Project Management Chapter 13 Sections 13.1, 13.2, and 13.3.
1 TCOM 5143 Lecture 11 Project Management. 2 What’s Project Management? Project management involves planning and scheduling the different activities of.
Prof.Dr. Ahmet R. Özdural – Class Notes_06 - KMU417 Project Planning and Organization – Fall Semester.
Project Planning & Scheduling What is a “project”? Objectives and tradeoffs Planning and Control in Projects Scheduling Methods Constant-Time Networks.
Chapter 8 - Project Management1 Lecture 2 Today’s lecture covers the followings: 1.To study “project crashing” concept 2.LP formulation for project management.
PERT / CPM – Time-Cost Tradeoffs BSAD 30 Dave Novak Source: Anderson et al., 2015 Quantitative Methods for Business 13 th edition – some slides are directly.
Project Management Chapter 8.
Project Management Chapter Topics
Project Planning & Scheduling
Basic Project Scheduling
Project Planning & Scheduling
Basic Project Scheduling
Chapter 8 - Project Management
Projects: Critical Paths
PROJECT MANAGEMENT WITH CPM/PERT.
Probabilistic Time Estimates
Project Scheduling: networks, duration estimation, and critical path
Welcome to MM 305 Unit 8 Seminar!
Project Management Operations -- Prof. Juran.
Project Management CPM/PERT Professor Ahmadi.
Planning and Managing Projects
Presentation transcript:

Review problem 1 QP dolls, Inc., has developed a new doll it feels could turn into a “collector’s item” through proper advertisement. The PERT/ CPM network shown models the activities (or work packages) of the project. A C B E D H F G I

Distribution of the total budgeted cost of $5,280,000 and expected completion times (in weeks) for each of the work packages are summarized in the following table

a. Determine an earliest and latest schedule for each work package. Go to file ch7-16.cpm

Review problem 1 - Continued Consider the situation faced by QP Dolls, Inc. in problem 16. Management is giving some thought to putting extra resources into the project so that it can be completed within one-half year (26 weeks). Accordingly, each work package has been studied, and a set of crash times in weeks and costs has been developed:

Compare

a.Determine a schedule for the work packages which minimizes the total cost of completing the project within 26 weeks. What is the minimum total cost? Go to file ch7-18a.cpm

b. Suppose QP will incur administrative and operational costs totaling $24,000 per week during this project. Modify your model to take into account these costs and solve for the optimal scheduling of the work packages. Did it change from the solution in part (a)? Go to file ch7-18b Let us first understand how to model the crash Problem using linear programming. Look at the following small example.

A D C B Finish E Normal Crash Activity Cost Time Cost Time A B C D E Define X as the start time of an activity. Define Y as the amount of time an activity is crashed. Notice that an activity cannot start before all its immediate predecessors are completed. This observation leads to the following relationship between activity A and B (for example) XB >= XA + time to complete activity A, or XB >= XA + (10 – YA) Start time of BStart time of AActual time to complete A after it was crashed. This is how you build all the network constraints one constraint for each arc, covering all the arcs. Also, note that X(FIN) >= XD+(8-YD) and X(FIN) >= XE+(8-YE). Due date =20

Therefore we have to add the following set of constraints YA <= 2 (10-8) YB <= 4 (12-8) ……. The objective function is determined by the case we solve: Case 1: To minimize crash costs formulate the objective function as follows: Minimize2000YA+ 625YB+…+500YE and add the due date constraint to the model, such as X(FIN) = 20. Otherwise, the optimal solution will be “not to crash” and incur “zero” crash costs. Case 2: To minimize the time to complete the project change the objective to Minimize X(FIN) [don’t forget that X(FIN) is the duration of the project]. You need to eliminate the constraint X(FIN) =20 since you try to minimize X(FIN), and instead limit the amount of funds used to a given budget by adding the constraint 2000YA+625YB+…+500YE<=Total budget available – Total normal costs. Case 3: To minimize the total crash costs+ operating costs we assume the operating costs are proportional to the time it takes to complete the project. Suppose the operating costs are $100 per one time unit (a week for example). Then we add 100X(FIN) to the objective function formulated in case 1 and eliminate the constraint X(FIN) = 20. ( )/(10-8) Sometimes the Total budget – Total normal costs has already been computed, so you need to read the information given carefully. In addition to these constraints, there are constraints on the time each activity can be crashed. For example, activity C can be crashed by 1 at most, but activity D can be crashed by 3 at most.

b. Suppose QP will incur administrative and operational costs totaling $24,000 per week during this project. Modify your model to take into account these costs and solve for the optimal scheduling of the work packages. Did it change from the solution in part (a)? Go to file ch7-18b

X(FIN) >= XI+8-YI or -XI+X(FIN)+YI>=8 Note that the objective function consists of crashing costs + operational costs.

The solution did not change

c. Suppose QP only budgeted $6 million for this project. What is the minimum time to complete this project if the weekly fixed costs are included in the model.Go to file ch7-18c2 This objective function minimizes the completion time of the project for a given budget. 6,000,000-5,280,000=720,000

Minimum time = 30 weeks with a crash budget of $720,000

Review problem 2 Text problem 21 Golden West Homes is developing a new modular home model. The following table outlines the activities of the project. Times are expressed in days:

a. Determine the expected completion time and the critical path for this project. Go to file ch 7-21c for a solution without a consultant Expected completion time = 117 days. Critical path: A B C D E J L N R Finding critical path

b. Because of production considerations, Golden West will lose $ 10,000 if this project is not completed within 114 days. What is the probability that the project will be completed within 114 days? Perform probability analysis with WINQSB (in Results menu): P(Completion in 114 days) =.2957 Calculating probabilities - using WINQSB

c. Suppose Golden West were to hire a meeting planning consultant to hold the dealer meetings (activity N). This would cost Golden West an additional $1000, but the activity is guaranteed to take exactly three days. Considering the $10,000 loss if the project is not completed in 114 days, should Golden West hire the consultant? Go to file ch 7-21cc (with consultant). Because there is no variance, all the time estimates of activity N are the same. Applying the Expected value criterion

Expected cost (No consultant)=.2957(0)+( )(10000)=$7043 Expected cost (w/consultant)=.4284(0)+( )10000)+1000=$6716 With activity N expected to be completed in 3 days, the project is expected to be completed in 115 days. The probability to complete in 114 days is Hire the consultant

d. What is the most Golden West should be willing to pay for a meeting planning consultant who could hold dealer meetings in exactly three days? = $1327