SDHM Hydromodification Overview

Slides:



Advertisements
Similar presentations
Western Washington Hydrology Model Version 3 AWRA Washington Section January 2007 Doug Beyerlein, P.E. Clear Creek Solutions, Inc.
Advertisements

Permeable Heavy Use Area for Livestock Farms Presentation for Kitsap County DCD, September 28 th, 2006, Lab Test Findings and Calculated Storm Water Performance.
Infiltration Trenches Dave Briglio, P.E. MACTEC Mike Novotney Center for Watershed Protection.
UW LID Workshop Permeable Pavement Modeling June 2008 Doug Beyerlein, P.E. Clear Creek Solutions, Inc.
Simplified Sizing Tool for LID Practices in western Washington Alice Lancaster, PE Herrera Environmental Consultants.
LID Site Design and Drainage Dan Cloak Environmental Consulting May 23, 2011.
UW LID Workshop Bioretention Flow Control Modeling May 2008
Leah Johanson, Water Environment Services
INLAND EMPIRE ASCE & APWA LOW IMPACT DEVELOPMENT (LID) SEMINAR INLAND EMPIRE ASCE & APWA LOW IMPACT DEVELOPMENT (LID) SEMINAR LID FACILITY DESIGN Prepared.
CHARACTERISTICS OF RUNOFF
Runoff Processes Daene C. McKinney
Soil Conservation Service Runoff Equation
Hydrological Modeling for Upper Chao Phraya Basin Using HEC-HMS UNDP/ADAPT Asia-Pacific First Regional Training Workshop Assessing Costs and Benefits of.
Introduction to Surface Water Hydrology and Watersheds Lecture 1 Philip B. Bedient Rice University November, 2000.
Low Impact Development Overview  Alternative to end of pipe approach to SWM  Maintain hydrologic function of local ecosystem  Treat stormwater close.
Runoff Processes Reading: Applied Hydrology Sections 5.6 to 5.8 and Chapter 6 for Tuesday of next week.
OKLAHOMA STATE UNIVERSITY Biosystems and Agricultural Engineering Department Hydrology 101 OKLAHOMA STATE UNIVERSITY Biosystems and Agricultural Engineering.
Wake County Stormwater Workshop Guidance on the New Stormwater Ordinance and Design Manual August 29, 2006.
Green Roof Hydrology by Doug Beyerlein, P.E. Joe Brascher Clear Creek Solutions, Inc. Mill Creek, WA.
Western Washington Hydrology Model Version 3 Vancouver, WA, Workshop October 17, 2007 PM.
Hydrologic Theory One of the principal objectives in hydrology is to transform rainfall that has fallen over a watershed area into flows to be expected.
Why and How; What’s Working and What Isn’t.  How Low Impact Development can mitigate effects of urban drainage  Applying design criteria for bioretention.
Upper Brushy Creek Flood Study – Flood mapping and management Rainfall depths were derived using USGS SIR , Atlas of Depth Duration Frequency.
1 Quantifying Hydromodification Impacts and Developing Mitigation Using a Four Factor Approach Judd Goodman CASQA Conference November.
Reading: Applied Hydrology, Sec 15-1 to 15-5
Wes Marshall, P.E. University of Connecticut May 2007 CE 276 Site Design Final Exam Outline.
HYDROLOGIC COMPUTER MODELING Washington Hydrology Society March 2006 Joe Brascher, President Clear Creek Solutions, Inc.
Western Washington Hydrology Model Version 3
Engineering Hydrology (ECIV 4323)
Stormwater Infrastructure for Water Quality Management Dr. Larry A. Roesner, P.E. CE 394K.2 Surface Water Hydrology University of Texas, Austin April 8,
For Stormwater Treatment and Flow Control Dan Cloak Environmental Consulting December 14, 2010 Contra Costa Clean Water Program.
Bernie Engel Purdue University. Low-Impact Development (LID) An approach to land development to mimic the pre-development site hydrology to: 1)Reduce.
Clear Creek Solutions, Inc. Providing software and consulting services to solve hydrology and stormwater problems throughout the world.
STEP 3: SITING AND SIZING STORM WATER CONTROLS Section 6.
Background and Overview Stormwater NPDES Compliance For New Developments.
Bay Area Hydrology Model Doug Beyerlein, P.E. Joe Brascher Shanon White Clear Creek Solutions, Inc.
Stormwater 101 Ohio Lake Erie Commission Best Local Land Use Practices Kirby Date, AICP.
ODOT 2015 Geo-Environmental Conference
James River in Richmond, Virginia looking upriver from the Robert E. Lee bridge. Belle Isle is on the right, November What is happening in this.
Stormwater Treatment and Flow Control Dan Cloak, P.E. Presentation to the San Diego Region Co-permittees Hydromodification Workgroup December 6, 2006 Contra.
Seattle’s Testing and Application of Low Impact Development BMPs in WWHM3 July 2006 Doug Beyerlein, P.E. Clear Creek Solutions, Inc.
Bernie Engel, Larry Theller, James Hunter Purdue University.
CE 424 HYDROLOGY 1 Instructor: Dr. Saleh A. AlHassoun.
Stormwater Water Quality Treatment Options Alvin Shoblom, P.E. Hydraulics Engineer.
Hydrograph Modification Management in Contra Costa County Dan Cloak, P.E. Dan Cloak Environmental Consulting.
Term Project Presentation CE 394K.2 Hydrology Presented by Chelsea Cohen Thursday, April 24, 2008.
Horsley Witten Group, Inc. Stormwater Management and Elements of Low Impact Development Protecting Our Water Resources – An Ecological Approach to Land.
Why Single-Event Modeling Doesn’t Work for LIDs presented at Stormcon 2009 Anaheim, CA August 2009 Doug Beyerlein, P.E. Clear Creek Solutions, Inc.
PSGB Ecosystem Conference The Effectiveness of LIDs in Reducing Stormwater Runoff February 9, 2009 Doug Beyerlein, P.E. Clear Creek Solutions, Inc.
Western Washington Hydrology Model 2005 AWRA Annual Conference Doug Beyerlein, P.E. Joe Brascher Shanon White Clear Creek Solutions, Inc.
STORMWATER MANAGEMENT
State Board Modeling Needs and Interests Eric Berntsen, PH, CPESC, CPSWQ State Water Resources Control Board CWEMF Hydrology and Watershed Modeling Workshop.
Sizing Stormwater Control Facilities to Address Stream-Bank Erosion Control Anthony M. Dubin, PE Brown and Caldwell Anthony M. Dubin,
Surface Water Surface runoff - Precipitation or snowmelt which moves across the land surface ultimately channelizing into streams or rivers or discharging.
Modeling Stream Flow of Clear Creek Watershed-Emory River Basin Modeling Stream Flow of Clear Creek Watershed-Emory River Basin Presented by Divya Sharon.
Kitsap County Department of Public Works CRAB – November 04, 2015 Bioretention Stormwater BMP Benson Burleson Design Engineer
Hydromodification Compliance in the Bay Area
Storm Water Runoff Storm Water Runoff
Clear Creek Solutions, Inc. LID Hydrology and Hydraulics Doug Beyerlein, P.E. Clear Creek Solutions, Inc.
ASCE LID Conference LID Analysis Considerations in Western Washington November 17, 2008 Doug Beyerlein, P.E. Clear Creek Solutions, Inc.
WWHM3 LID Stormwater Modeling Snohomish County August 2006 Doug Beyerlein, P.E. Clear Creek Solutions, Inc.
Sanitary Engineering Lecture 4
City Council March 4, Introduction The UCRA recommends the development of a storm water storage basin just to the east of FM 1223, south of Avenue.
Construction of On-Site Stormwater Treatment and Flow Control Facilities Dan Cloak, P.E. Principal Dan Cloak Environmental Consulting.
BUILDING AND RUNNING THE HYDROLOGICAL MODEL
Where Does Storm Water Go?
Storm Water Runoff Storm Water Runoff
Northern California LID Hydrology and Hydraulics
Doug Beyerlein, P.E., Clear Creek Solutions, Inc.
What we have developed is…
Presentation transcript:

SDHM Hydromodification Overview Doug Beyerlein, P.E. Joe Brascher Clear Creek Solutions, Inc. www.clearcreeksolutions.com

Why HMP Modeling? Impacts of land use changes: Increase in impervious surface Decrease in amount of vegetation Grading and compaction of soils Construction of drainage facilities

Why HMP Modeling? Effects of land use change on stormwater runoff: Less infiltration and evapotranspiration More surface runoff (increased volume) Runoff leaves the site faster (increased peak flows) Runoff occurs more often (increased duration) Runoff conveyed directly to creek (increased connectivity)

What is HMP Modeling? HMP modeling is quantifying the hydrologic impacts caused by land use changes in terms of: (1) frequency (2) duration

Frequency Frequency is the probability of a certain size event occurring: 2-year (50% probability) 5-year (20%) 10-year (10%) 25-year (4%) 50-year (2%) 100-year (1%)

Frequency Traditionally we have used single-event design storms to size facilities based on frequency. Design storm assumption: 25-year rainfall causes 25-year flood.

Single-event design storm methodology doesn’t work for HMP design because: Single-event flow frequency standards are based on inappropriate assumptions. Single-event modeling cannot compute flow durations (percent of time flows exceed a specific value).

Duration Flow Duration Analysis: Percent of time the flow exceeds a specific flow value.

Durations Flow duration standard: based on erosive flows. Western Washington: 50% of 2-yr to 50-yr

Durations Flow duration standard: based on erosive flows. Santa Clara, San Mateo, Alameda: 10% of 2-yr to 10-yr

Durations Flow duration standard: based on erosive flows. San Diego County: 20% of 5-yr to 10-yr

Based on continuous simulation hydrology: HSPF (SDHM) HEC-HMS SWMM HMP Modeling Options Based on continuous simulation hydrology: HSPF (SDHM) HEC-HMS SWMM

HYDROLOGIC SIMULATION PROGRAM - FORTRAN HSPF: HYDROLOGIC SIMULATION PROGRAM - FORTRAN Continuous simulation model Natural and developed watersheds and water systems Land surface and subsurface hydrology and quality processes Stream/lake hydraulics and water quality processes Time series data management and storage Time series data statistical analysis and operations Core watershed model in EPA BASINS and Army Corps WMS Development and maintenance activities sponsored by U.S. EPA and U.S. Geological Survey

HSPF: History 1966 – Stanford Watershed Model by Linsley and Crawford 1972 – HSP by Hydrocomp 1973 – ARM (Agricultural Runoff Management) Model for EPA by Hydrocomp 1974 – NPS (Non-Point Source) Model for EPA by Hydrocomp 1979 – HSPF (combining HSP, ARM, and NPS) for EPA by Hydrocomp

HSPF: Glossary (Greek to English) UCI: User Control Input (file type) WDM: Watershed Data Management (file type) PERLND: Pervious land area IMPLND: Impervious land area RCHRES: Conveyance/routing reach FTABLE: Stage-storage-discharge table SURO: Surface runoff IFWO: Interflow (shallow, subsurface runoff) AGWO: Active groundwater/base flow

HSPF: File Types UCI file: User Control Input (text file) Land area (soil, vegetation, slope, impervious) values Conveyance parameter values Display of annual peak flows Duration analysis WDM file: Watershed Data Management (binary file) Precipitation time series Potential evapotranspiration time series Simulated runoff time series

HSPF Made Easy: SDHM San Diego Hydrology Model (SDHM). SDHM is HSPF in an easy to use package.

HSPF Made Easy: SDHM HSPF UCI and WDM files are automatically created by SDHM and are transparent to the user, but are available for review.

SDHM Available free to local municipal agency staff from www.clearcreeksolutions.com. Available to consultants for a fee.

SDHM Based on the same software platform as BAHM and WWHM3. Customized for San Diego County.

WDM Data: Precipitation Requirements: continuous record (no data gaps or missing data) 30-50 years of data hourly or smaller time interval Example: San Diego Airport National Weather Service data Note: Need to scale precipitation data to project site. Take ratio of station mean annual precip and project site mean annual precip.

WDM Data: Potential Evapotranspiration Requirements: continuous record (no data gaps or missing data) 30-50 years of data daily or smaller time interval Example: local pan evaporation data If using pan evap data need to include pan evap coefficient to convert to PET data.

WDM Data: Irrigation? Requirements: continuous record (no data gaps or missing data) 30-50 years of data daily or smaller time interval Example: Representative of urban landscape watering patterns.

Simulation Period 30-50 years dependent on start and end dates of precip and PET time series should start in a dry period (water year: Oct 1 – Sep 30)

PERLNDs (Pervious Land Areas) Designation of PERLND types is based on soil type (A, B, C, D) vegetation type forest/trees scrub/shrub natural grasslands bare earth/dirt urban landscape vegetation (irrigated) land slope flat (0-5% slope) moderate (5-10% slope) steep (10-20% slope) very steep (>20% slope)

PERLNDs (Pervious Land Areas) Simulate the water movement and storage in the different components/pathways in the hydrologic cycle.

IMPLNDs (Impervious Land Areas) Designation of IMPLND types is based on land slope flat (0-5% slope) moderate (5-10% slope) steep (10-20% slope) very steep (>20% slope)

Three types of runoff IFWO (interflow) AGWO (groundwater/base flow) SURO (surface runoff) IFWO (interflow) AGWO (groundwater/base flow) Stormwater runoff is usually defined as the sum of SURO+IFWO (surface runoff + interflow).

RCHRES (Conveyance reach system) Precipitation on Reach Surface Evaporation Outflow through exit 1 Volume of Water in a Reach Exit 2 Inflow (upstream sources, direct drainage) Exit (N = up to 4) Exit can represent infiltration through bottom of reach

RCHRES (Conveyance reach system) RCHRES can represent any type of conveyance/storage system: open channel stormwater pond stormwater vault pipe system bioretention cell planter box porous pavement

RCHRES (Conveyance reach system) All conveyance/storage systems are described using an FTABLE. An FTABLE is a table with: Stage (feet) Surface area (acres) Storage volume (acre-feet) Discharge (cfs)

RCHRES (Conveyance reach system) Open channel:

RCHRES (Conveyance reach system) Stormwater pond:

RCHRES (Conveyance reach system) Stormwater pond discharge: Riser and notch discharge based on weir equation. Orifice discharge based on orifice equation.

RCHRES (Conveyance reach system) Riser notch options: Rectangular V-Notch Sutro

RCHRES (Conveyance reach system) Stormwater vault:

RCHRES (Conveyance reach system) Pipe system:

RCHRES (Conveyance reach system) Bioretention cell: Need HSPF Special Actions to check on the ability to discharge from the surface storage to Layer 1.

RCHRES (Conveyance reach system) Planter box: Need HSPF Special Actions to check on the ability to discharge from the surface storage to the soil layer.

RCHRES (Conveyance reach system) Porous pavement: Storage in the pavement layer and gravel subgrade. Infiltration to the underlying native soil is optional.

Downstream Point of Compliance Point of Compliance (POC) is at the downstream exit from the project site.

Two Model Scenarios Existing Post-development Compute stormwater runoff for both existing and post-development conditions. Existing Post-development

Flow Frequency To compute frequency the maximum hourly annual existing flow values are needed.

Flow Frequency Computational Methods Weibull Plotting Position P = (m-a)/(N-a-b+1) where P = probability m = rank N = number of years a = constant b = constant Return period, Tr (years) = 1/P

Duration Analysis Flow Duration Analysis: Percent of time the flow exceeds a specific flow value.

Duration Analysis Comparison Flow Duration Table for flows from 20% of the 5-year to 100% of the 10-year frequency value.

Duration Analysis Comparison Flow Duration Curves for flows from 20% of the 5-year to 100% of the 10-year frequency value.

Other Analysis: Drawdown For vector management: Want to know the water level drawdown/retention depth (or stage) for 1-5 days plus maximum stage and drawdown time. Use stage time series.

SDHM Steps for sizing hydromod facilities: Locate project site on county map. Input existing land conditions. Input future developed land conditions. Create hydromod mitigation facility. Create Point of Compliance. Automatically size hydromod mitigation facility. Run HSPF. Compute flow durations. Compute drawdown (optional).

SDHM 1. Locate project site on county map: Place red dot on county map

SDHM 2. Input existing land conditions:

SDHM 3. Input future developed land conditions:

SDHM 4. Create hydromod mitigation facility: User can select from a menu of different types.

SDHM 5. Create Point of Compliance:

SDHM 6. Automatically size hydromod mitigation facility: SDHM will automatically size many facilities.

SDHM 7. Run HSPF:

SDHM 8. Compute flow durations: Automatically computes frequency and duration analysis for POC.

SDHM 9. Compute drawdown (optional)

SDHM Create project report: Includes all input and output info plus analyses.

SDHM: LID/BMP Options SDHM includes the following LID/BMP options: Dispersion of impervious surface runoff on adjacent pervious surface (example: roof runoff to lawn). Bioretention/rain gardens/landscape swales to retain and infiltrate stormwater. Planters/dry wells/infiltration trenches/porous pavement to retain and infiltrate stormwater. Vegetated/grassy (dry) swales/sand filters to provide water quality enhancements.

SDHM Project files created by SDHM: WHM: Binary project file. WH2: Text project file. WDM: Binary Watershed Data Management file.

Free download for agency staff and consultants at SDHM User Manual: Free download for agency staff and consultants at www.clearcreeksolutions.com

SDHM Questions? Contact: Doug Beyerlein 425.892.6454 beyerlein@clearcreeksolutions.com Joe Brascher 360.943.0304 brascher@clearcreeksolutions.com