GLAST LAT ProjectLAT Mgr’s Meeting November 17, 2004 1 LAT Planning Meeting Mechanical/Thermal Systems November 2004 Marc Campell.

Slides:



Advertisements
Similar presentations
Mech Systems Proposed EMI Modifications Marc Campell 9/2/03.
Advertisements

GLAST LAT Project May 25, 2006: Pre-Environmental Test Review Presentation 5 of 12 Subsystem Acceptance 1 GLAST Large Area Telescope Pre-Environmental.
GLAST LAT ProjectLAT Mgr’s meeting July 17-18, LAT Planning Meeting Mechanical Systems Marc Campell.
GLAST LAT ProjectQuarterly Review of the GLAST/LAT Project, August 14, 2001 Martin Nordby1 GLAST Large Area Telescope: Mechanical Systems Martin Nordby.
GLAST LAT ProjectLAT Mgr’s Meeting October 13, LAT Planning Meeting Mechanical/Thermal Systems October 2004 Marc Campell.
GLAST LAT ProjectLAT F2F Mgrs Meeting November 17, Tanya Boysen LAT Project Controls Manager WBS Instrument Management.
1 GLAST LAT ACD FTF 3/17/05 GLAST Large Area Telescope: Face to Face Meeting March 17, 2005 AntiCoincidence Detector (ACD) Subsystem WBS: David J.
GLAST LAT ProjectDOE/NASA Mechanical Systems Peer Review, March 27, 2003 Document: LAT-PR-0XXXX Section 1.1 Management 1 GLAST Large Area Telescope: Mechanical.
1 GLAST LAT ProjectMechanical Systems Mechanical Systems Mechanical / Thermal Hardware November 2004 Status Marc Campell, Subsystem Manager.
GLAST LAT ProjectDOE/NASA Mechanical Systems Peer Review, March 27, 2003 Section Mechanical Systems Radiator and X-LAT Assy1 GLAST Large Area Telescope:
1 GLAST LAT ProjectMechanical Systems Mechanical Systems Mechanical / Thermal Hardware July 2005 Status Marc Campell, Subsystem Manager.
GLAST LAT ProjectDOE Rebaseline Review, February 13, GLAST Large Area Telescope: Lowell A. Klaisner Stanford Linear Accelerator Center Chief Engineer.
GLAST LAT ProjectDOE/NASA Review of the GLAST/LAT Project, Feb , 2001 Martin Nordby1 Mechanical Systems Martin Nordby Stanford Linear Accelerator.
GLAST LAT ProjectDOE/NASA Review of the GLAST/LAT Project, Feb , 2001 Martin Nordby1 Martin Nordby Stanford Linear Accelerator Center Stanford University.
GLAST LAT ProjectLAT Mgr’s Meeting LAT Planning Meeting Mechanical/Thermal Systems March 17, 2005 Marc Campell.
GLAST LAT ProjectF2F, June 15, 2005 GLAST Large Area Telescope: Performance & Safety Assurance Joseph Cullinan SLAC Performance & Safety Assurance Manager.
GLAST I&T January T Borden 1 Tracker EM Mechanical Mock-up T Borden I&T Tracker Mock-up.
GLAST LAT ProjectSLAC Pre - Baseline Review, April 16, 2002 ` 1 GLAST Large Area Telescope: I&T Overview WBS: Elliott D. Bloom Stanford Linear Accelerator.
GLAST LAT ProjectSubsystem Managers Meeting May 12, GLAST Large Area Telescope: Lowell A. Klaisner Stanford Linear Accelerator Center Project Manager.
GLAST LAT ProjectLAT Planning Meeting July 17 th and 18 th Integration and Test 1 GLAST Large Area Telescope: I & T Input to LAT Planning Meeting.
LAT Design Integration1 GLAST LAT ProjectDecember 2003 LAT Planning Meeting December 10, 2003 Design Integration LAT Planning Meeting December 10, 2003.
GLAST LAT ProjectDecember 2, 2003 R. Johnson Engineering Meeting 1 GLAST Large Area Telescope: Tracker Subsystem WBS Tracker EM Vibration Test Status.
GLAST LAT ProjectNovember 17, 2004 AntiCoincidnce Detector 1 GLAST Large Area Telescope: Face to Face Meeting November 17, 2004 AntiCoincidence Detector.
GLAST LAT ProjectIntegration and Test CDR Peer Review, March 28, 2003 Document: LAT-PR Section 7 - Page 1 GLAST Large Area Telescope: I & T Peer.
GLAST Large Area Telescope:
GLAST LAT ProjectDOE/NASA Mechanical Systems Peer Review, March 27, 2003 Section Mechanical Systems X-LAT Assy1 GLAST Large Area Telescope: Mechanical.
GLAST LAT ProjectDOE/NASA Mechanical Systems Peer Review, March 27, 2003 Document: LAT-PR-0XXXX Section 5.1 Grid Box Design 1 GLAST Large Area Telescope:
GLAST LAT ProjectDOE/NASA Mechanical Systems Peer Review, March 27, 2003 Document: LAT-PR-0XXXX Section 6.0 Subsystem Verif. Test Plan 1 GLAST Large Area.
GLAST LAT ProjectI&T&C Pre PDR Presentation– Oct. 2, I&T&C Organization Chart I&T&C Manager Elliott Bloom WBS I&T Engineer B. Grist WBS
LAT Design Integration and Analysis1 GLAST LAT Project1 Sep 2005 LAT Monthly Status Review 1 Sep 2005 Design Integration and Analysis LAT Monthly Status.
GLAST LAT ProjectMarch 24, B Tracker Peer Review, WBS GLAST Large Area Telescope: Tracker Subsystem WBS B: Schedule Summary; Critical.
GLAST LAT Project – Cost and Schedule ReviewJanuary 27, 2004 AntiCoincidence Detector 1 GLAST Large Area Telescope: Cost/Schedule Review January 27, 2005.
1 GLAST LAT ProjectMechanical Systems Mechanical Systems Mechanical / Thermal Hardware December 2004 Status Marc Campell, Subsystem Manager.
GLAST LAT Project September 15, 2006: Pre-Shipment Review Presentation 8 of 12 Thermal Vacuum Test 1 GLAST Large Area Telescope LAT Pre-Shipment Review.
GLAST LAT ProjectDOE/NASA Mechanical Systems Peer Review, March 27, 2003 Section Mechanical Systems Radiator Assy1 GLAST Large Area Telescope: Mechanical.
GLAST LAT Project May 25, 2006: Pre-Environmental Test Review Presentation 10 of 12 Mechanical Test 1 GLAST Large Area Telescope Pre-Environmental Test.
1 PFDPU Mechanical Packaging PEER REVIEW MAVEN PFDPU Particle and Fields Data Processing Unit Mechanical Packaging and Design Overview May 09, 2011 Bill.
Strykowsky 1Project Review November 2, 2005 NCSX Project Review November 2, 2005 Cost and Schedule Ron Strykowsky.
1 GLAST LAT ProjectMechanical Systems Mechanical Systems September 2003 GSFC Status Marc Campell, Subsystem Manager.
LAT Design Integration and Analysis1 GLAST LAT Project24 May 2005 LAT Monthly Status Review 24 May 2005 Design Integration and Analysis LAT Monthly Status.
LAT-PR Section 11-1 GLAST LAT ProjectMechanical Design Integration Peer Review, March 2003 Mechanical Design Integration Peer Review, March 2003.
LAT MPSRLAT Structural Analysis-1 GLAST LAT ProjectNov-04 Structural Analysis: Completed Tasks LAT System Level –LAT Environmental TIM Support A success.
GLAST LAT ProjectDOE/NASA Mechanical Systems Peer Review, March 27, 2003 Document: LAT-PR-0XXXX Section 5.3 Fab & Assy Plans 1 GLAST Large Area Telescope:
1 GLAST LAT ProjectMechanical Systems Mechanical Systems November 2003 GSFC Status Marc Campell, Subsystem Manager.
GLAST LAT Project April 27, 2006: LAT Pre-Ship Review Presentation 10 of 12 Mechanical Test 1 GLAST Large Area Telescope LAT Pre-Shipment Review Mechanical.
GLAST LAT Project13 June 2005 LAT System EngineeringLAT Test Planning Meeting GLAST LAT GLAST LAT System Engineering Gamma-ray Large Area Space Telescope.
GLAST Large Area Telescope:
Bill Raynor Naval Research Lab
GLAST Large Area Telescope:
Mechanical Integration
Environmental Test Planning
GLAST Large Area Telescope:
GLAST Large Area Telescope:
GLAST Large Area Telescope: I&T Integration Kickoff Meeting
GLAST Large Area Telescope: Cost/Schedule Review September 1, 2005
1. Introduction and Overview
GLAST Large Area Telescope:
GLAST Large Area Telescope:
Thermal Vacuum Test: Plans and Procedures
GLAST Large Area Telescope:
GLAST Large Area Telescope:
GLAST Large Area Telescope:
Integration and Test Organization Chart
GLAST Large Area Telescope:
Mechanical/Thermal Systems
GLAST Large Area Telescope
Introduction and Overview
GLAST Large Area Telescope:
Design Integration and Analysis
GLAST Large Area Telescope:
Presentation transcript:

GLAST LAT ProjectLAT Mgr’s Meeting November 17, LAT Planning Meeting Mechanical/Thermal Systems November 2004 Marc Campell

GLAST LAT ProjectLAT Mgr’s Meeting November 17, THE GRID IS HERE!

GLAST LAT ProjectLAT Mgr’s Meeting November 17, MECH Milestones Dates TBR

GLAST LAT ProjectLAT Mgr’s Meeting November 17, LM ETC Formal ETC from LM is in progress. This data has not been submitted by LM.

GLAST LAT ProjectLAT Mgr’s Meeting November 17, LM Risks Radiator –Timely headcount roll-off –First time use of bonding/assembly tool & procedures (No full sized Dev hardware). MFG marching army costs –Radiator Assembly design doesn’t accommodate repairs –Handling risks – large, fragile hardware –Cost over runs in testing Fixture design (Acoustic) Facility scheduling – competing with other LM priority programs Resolution of TCS anomalies during Thermal Balance testing. Test marching army costs –Satisfactory replacement of key personnel

GLAST LAT ProjectLAT Mgr’s Meeting November 17, LM De-scope Options Radiator Vibe testing –Current plan Hz low level sine sweep in 3 axes 5-50 Hz sine sweep in 2 axes Hz low level sine sweep in 3 axes Acoustic test Hz low level sine sweep in 3 axes (plan to substitute - 6 dB acoustic run for this)

GLAST LAT ProjectLAT Mgr’s Meeting November 17, LM De-scope Options (cont) Radiator Vibe testing - De-scope options –Defer Hz sine sweep until LAT level Perform twang and/or tap test of Radiator for model validation (first modes only) –Delete Hz sine sweep for post test signatures Perform -6 dB Acoustic runs before & after P/Qual level Acoustic test for pass/fail evaluation –Delete 5-50 Hz sine sweep Qual by analysis (LM is defining where there are inadequate margins for this) Interface potted inserts are tested by witness coupons that are bonded simultaneously on the sides of the Radiator panel during layup –These actions carry low to moderate risk per J. Ku –Cost savings ~$160,000 (8 LM EM x.75 month)?

GLAST LAT ProjectLAT Mgr’s Meeting November 17, LM De-scope Options (cont) X-LAT Thermal Testing –Perform Thermal Cycle test in air instead of thermal vacuum –This is primarily a workmanship test and there is low risk. –Violates MAR requirement for 4 Thermal Vacuum cycles. –Tom McCarthy indicated that 8 thermal cycles in air would be acceptable to him. –Need to implement now to maximize savings (test preparations are underway). –LM will investigate the feasibility of this change. –Cost Savings ~$50,000 (~1/2 of quoted cost)

GLAST LAT ProjectLAT Mgr’s Meeting November 17, Grid #2 Static Load Test To Go SLT budget –Grid Box #2 Assy Operations $34,170 –Design & Fab MGSE/fixtures $78,650 –Test $180,000 –Total$292,820 –Note: This test does not drive LAT schedule Risks –Test house not selected –If FE model doesn’t correlate then additional test cases will be required –There is sufficient budget for these contingencies De-scope options –None. This test allows deletion of LAT Sine Vibe (LAT de- scope). –The number of load cases required has been reduced.

GLAST LAT ProjectLAT Mgr’s Meeting November 17, BACK-UP

GLAST LAT ProjectLAT Mgr’s Meeting November 17, MECH ETC

GLAST LAT ProjectLAT Mgr’s Meeting November 17, MECH BOE Mechanical Systems Labor Increases $140.5K This increase consists of $40K for the Multi- Layer Insulation (MLI) blanket design. Very early on in the program, the ACD subsystem was responsible for the LAT MLI design and fabrication. Because of the complexity of the MLI interfaces with the Spacecraft, Radiators and LAT external features, it was decided to pull this work back to SLAC. Additionally, Thermal Engineering support is now available at SLAC to support this task. $100.5K has been added for Mechanical Systems support of the LAT I & T efforts at the end of FY05. These tasks include X-LAT Plate installation and Radiator fit check and shimming operations on the LAT prior to LAT shipment.

GLAST LAT ProjectLAT Mgr’s Meeting November 17, MECH BOE (con’t) Mechanical Systems Material Increases $1,620.5K This increase consists of $1,580.5K (TBR) additional funding to complete the Lockheed Martin contract. There are two main cost drivers: 1) Lockheed schedule delays and 2) SLAC imposed changes. 1) LM overran the following tasks: –Radiator design, –Radiator analysis (structural development), –Radiator tooling design & fab, –Radiator Thermal Controls design and –X-LAT Plate analysis. These overruns have left insufficient budget for the remaining tasks to be completed.

GLAST LAT ProjectLAT Mgr’s Meeting November 17, MECH BOE (con’t) 2) The following changes were made after Lockheed submitted their February 2004 cost proposal and resulted in extra costs (WAG $150K). –Additional thermal analyses for the X-LAT plate to electronics box interface, for the thermal combs (heat shunt for the GASU box) and for the U-shaped heat pipes that were added then removed from the X-LAT plate, –MLI blanket design consultant, –Radiator EMI coupon testing, –Added keying features to the Radiator There is also an additional $40K for the Multi- Layer Insulation (MLI) blanket fabrication. Very early on in the program, the ACD subsystem was responsible for the LAT MLI fabrication. Because of the complexity of the MLI interfaces with the Spacecraft, Radiators and LAT external features, it was decided to pull this work back to SLAC.