GLAST LAT ProjectI&T&C Particle Beams - Pre PDR Presentation– Oct. 2, 2001 Gary Godfrey1 I&T&C Organization Chart I&T&C Manager Elliott Bloom WBS 4.1.9.

Slides:



Advertisements
Similar presentations
The Gamma-Ray Large Area Space Telescope: UNDERSTANDING THE MOST POWERFUL ENERGY SOURCES IN THE UNIVERSE Anticoincidence Detector for GLAST Alexander Moiseev,
Advertisements

TeVPA, July , SLAC 1 Cosmic rays at the knee and above with IceTop and IceCube Serap Tilav for The IceCube Collaboration South Pole 4 Feb 2009.
Status of the MICE SciFi Simulation Edward McKigney Imperial College London.
GLAST LAT ProjectLAT Engineering Meeting, April 1, 2003 GLAST Large Area Telescope: Performance & Safety Assurance Darren S. Marsh Stanford Linear Accelerator.
GLAST LAT Project ISOC Peer Review - March 2, 2004 Document: LAT-PR Section 6.1 Ground Operations Software 1 Gamma-ray Large Area Space Telescope.
GLAST LAT ProjectDOE/NASA Review of the GLAST/LAT Project, Feb , 2001 S. Ritz 1 GLAST Large Area Telescope: Instrument Design Steven M. Ritz Goddard.
GLAST LAT Project11/18/04 I&T Two Tower IRR 1 GLAST Large Area Telescope: Integration and Test Two Tower Integration Readiness Review Particle Test Elliott.
A.Chekhtman1 GLAST LAT ProjectCalibration and Analysis group meeting, April, 3, 2006 CAL on-orbit calibration with protons. Alexandre Chekhtman NRL/GMU.
GLAST LAT Project 1 Tracker “mini-tower” Full Size Calorimeter module Face to Face IDT meeting March 20, 2002 Convener: E. do Couto e Silva Engineering.
GLAST LAT ProjectDOE/NASA Review of the GLAST/LAT Project, Feb , 2001 Martin Nordby1 Martin Nordby Stanford Linear Accelerator Center Stanford University.
GLAST June 8, 2000, P. Roger Williamson, BFP - 1 Balloon Flight Planning Roger Williamson June 8, 2000.
GLAST LAT Project July 19, 2005 E. do Couto e Silva 1/17 Science Verification Analysis and Calibration GLAST Large Area Telescope Eduardo do Couto e Silva.
GLAST LAT Project May 25, 2006: Pre-Environmental Test Review Presentation 6 of 12 LAT Test Results 1 GLAST Large Area Telescope Pre-Environmental Test.
GLAST LAT Project11/18/04 I&T Two Tower IRR 1 GLAST Large Area Telescope: Integration and Test Two Tower Integration Readiness Review Particle Test Gary.
GLAST LAT ProjectSLAC Pre - Baseline Review, April 16, 2002 ` 1 GLAST Large Area Telescope: I&T Overview WBS: Elliott D. Bloom Stanford Linear Accelerator.
T. BurnettGeant Workshop user presentation 1 Geant4 and GLAST Description of the mission and instrument Simulation requirements How we are a little.
GLAST LAT Project Collaboration Meeting 8/30/ Beam Test Plan - SLAC End Station A Secondary Beams Gary Godfrey August 30, 2005 GLAST Collaboration.
GLAST LAT Project SE Test Planning meeting October 4, 2004 E. do Couto e Silva 1/13 SVAC Data Taking during LAT SLAC Oct 4, 2004 Eduardo.
GLAST LAT ProjectDOE/NASA Status Review, March 30 & 31, 2004 Integration and Test 1 Integration, Facilities, Configuration, and Test (IFCT) Flow Procedure.
GLAST Simulations Theodore E. Hierath Louisiana State University August 20, 2001.
GLAST LAT ProjectI&T PDR – Jan. 9, 2002 Gary Godfrey1 Integration and Test Organization Chart I&T&C Manager Elliott Bloom WBS I&T Engineer B. Grist.
GLAST LAT ProjectIntegration and Test CDR Peer Review, March 28, 2003 Document: LAT-PR Section 8 - Page 1 GLAST Large Area Telescope: I & T Peer.
GLAST LAT ProjectI&T PDR Presentation – Jan. 9, 2002 R. Claus1 Integration and Test Organization Chart I&T&C Manager Elliott Bloom WBS I&T Engineer.
GLAST LAT ProjectI&T&C Pre PDR Presentation– Oct. 2, I&T&C Organization Chart I&T&C Manager Elliott Bloom WBS I&T Engineer B. Grist WBS
GLAST LAT ProjectI&T&C Pre PDR, October 2, 2001 E. do Couto e Silva1 I&T&C Organization Chart I&T&C Manager Elliott Bloom WBS I&T Engineer B. Grist.
ATLAS Liquid Argon Calorimeter Monitoring & Data Quality Jessica Levêque Centre de Physique des Particules de Marseille ATLAS Liquid Argon Calorimeter.
GLAST LAT ProjectCDR/CD-3 Review May 12-16, 2003 Document: LAT-PR-01967Section 1 Introduction & Science Overview 1 GLAST Large Area Telescope: Introduction.
GLAST LAT ProjectI&T PDR Presentation (IFCT Dept.) – January 9, 2002 Larry Wai Integration and Test Organization Chart I&T Manager Elliott Bloom WBS
GLAST LAT ProjectFace to Face Managers Meeting 04/14/ Integration and Test 1 GLAST Large Area Telescope: I & T Input to Face to Face Managers.
Gus Sinnis Asilomar Meeting 11/16/2003 The Next Generation All-Sky VHE Gamma-Ray Telescope.
GLAST's GBM Burst Trigger D. Band (GSFC), M. Briggs (NSSTC), V. Connaughton (NSSTC), M. Kippen (LANL), R. Preece (NSSTC) The Mission The Gamma-ray Large.
1 Stepping in everyone’s toes ( but for a good cause….) Eduardo do Couto e Silva Software Meeting – January 2001.
Feb. 7, 2007First GLAST symposium1 Measuring the PSF and the energy resolution with the GLAST-LAT Calibration Unit Ph. Bruel on behalf of the beam test.
Gamma-ray Large Area Space Telescope 15th INTERNATIONAL WORKSHOP ON VERTEX DETECTORS September , 2006 Perugia, Italy GLAST Silicon Tracker beam.
GLAST LAT ProjectLAT Muons at NRL 28 Feb 2006 J. Eric Grove Naval Research Lab Washington DC LAT Muon Data Taking During Environmental Test at NRL J. Eric.
GLAST LAT ProjectI&T&C Pre PDR Presentation – Oct 2, 2001 B. Grist1 I&T&C Organization Chart I&T&C Manager Elliott Bloom WBS I&T Engineer B. Grist.
GLAST LAT Project IA Workshop 4 July 14, 2005 E. do Couto e Silva 1/7 Introduction to the Instrument Analysis Workshop 4 Eduardo do Couto e Silva July.
5-9 June 2006Erika Garutti - CALOR CALICE scintillator HCAL commissioning experience and test beam program Erika Garutti On behalf of the CALICE.
CHIPP meeting Appenberg, 24 Aug 2009 Preparation for LHC beam, Jeroen van Tilburg 1/15 Jeroen van Tilburg (Universität Zürich) LHCb: Preparation for LHC.
GLAST LAT ProjectI&T&C Pre PDR Presentation– Oct. 2, 2001 E. Bloom1 Elliott Bloom Integration and Test and Calibration Manager
GLAST LAT ProjectDOE/NASA Baseline-Preliminary Design Review, January 8, 2002 Document: #1 GLAST Large Area Telescope: I&T Overview Elliott D. Bloom Stanford.
GLAST LAT ProjectI&T&C Pre PDR Presentation– Oct 2, 2001 Darren Marsh1 I&T&C Organization Chart I&T&C Manager Elliott Bloom WBS I&T Engineer B. Grist.
1 Study of Data from the GLAST Balloon Prototype Based on a Geant4 Simulator Tsunefumi Mizuno February 22, Geant4 Work Shop The GLAST Satellite.
Feb. 3, 2007IFC meeting1 Beam test report Ph. Bruel on behalf of the beam test working group Gamma-ray Large Area Space Telescope.
GLAST LAT ProjectMini-Review, 30 January 2003 LAT-PR-#####-## 1 I & T Responsibility LAT I&T, Verification, and Calibration Flow VibeRandom vibrate/sine.
GLAST LAT Project I&T Integration Kickoff Meeting 03/09/ Particle Test 1 GLAST Large Area Telescope: Particle Test “Roadmap to Integration”
Report of GLAST Balloon Flight October Annual meeting of Astronomical Society of Japan T. Mizuno and other GLAST Balloon Team
GLAST LAT ProjectNovember 18, 2004 I&T Two Tower IRR 1 GLAST Large Area Telescope: Integration and Test Two Tower Integration Readiness Review SVAC Elliott.
I&T&C Organization Chart
GLAST Large Area Telescope:
Gamma-ray Large Area Space Telescope ACD Final Performance
Preparation for CERN test beam
Gamma-ray Large Area Space Telescope
Integration, Test, and Calibration
GLAST Large Area Telescope:
GLAST Large Area Telescope: I&T Integration Kickoff Meeting
Gamma-ray Large Area Space Telescope
GLAST Large Area Telescope Instrument Science Operations Center
Integration and Test Organization Chart
Preparation of the CLAS12 First Experiment Status and Time-Line
LAT Test Results GLAST Large Area Telescope LAT Pre-Shipment Review
Integration and Test Organization Chart
GEANT Simulations and Track Reconstruction
GLAST Large Area Telescope
Mini Tower Preliminary Results
Integration and Test Organization Chart
Introduction and Overview
Integration & Test Instrument Operations Coordination
Analysis of GLAST Balloon Experiment Data
Overview of Beam Test Benoit, Ronaldo and Eduardo Nov 8 , 2005 thanks to Steve and Bill for helping to consolidate all the information.
Presentation transcript:

GLAST LAT ProjectI&T&C Particle Beams - Pre PDR Presentation– Oct. 2, 2001 Gary Godfrey1 I&T&C Organization Chart I&T&C Manager Elliott Bloom WBS I&T Engineer B. Grist WBS Reliability & QA D. Marsh WBS Environmental Test Manager M. Lovellette Online Manager R. Claus Science Verification, Analysis, and Calibration E. do Couto e Silva Particle Test Manager G.Godfrey Integration, Facilities, Configuration, and Test O.Millican (Acting) Instrument Operations Coordinator S. Williams Mechanical Ground Support Equipment TBD I&T Preparation EM1 Model I&T&C Calibration Unit I&T Flight LAT I&T Mission I&T Support I&T Preparation EM1 Model I&T&C Calibration Unit I&T Flight LAT I&T Mission I&T Support I&T Preparation Flight LAT I&T Mission I&T Support I&T Preparation EM1 Model I&T&C Calibration Unit I&T Flight LAT I&T Mission I&T Support

GLAST LAT ProjectI&T&C Particle Beams - Pre PDR Presentation– Oct. 2, 2001 Gary Godfrey2 Verification Matrix Requirements flow down from –LAT Science Requirements Document – Level II Specification LAT-SS (found in LAT-SS-9.1) –Summarized by the Instrument Scientist (Steve Ritz)

GLAST LAT ProjectI&T&C Particle Beams - Pre PDR Presentation– Oct. 2, 2001 Gary Godfrey3 Verification Matrix

GLAST LAT ProjectI&T&C Particle Beams - Pre PDR Presentation– Oct. 2, 2001 Gary Godfrey4 Verification Matrix

GLAST LAT ProjectI&T&C Particle Beams - Pre PDR Presentation– Oct. 2, 2001 Gary Godfrey5 Verification Matrix

GLAST LAT ProjectI&T&C Particle Beams - Pre PDR Presentation– Oct. 2, 2001 Gary Godfrey6 Particle Beam Sources Cosmics rays on the ground –All individual towers and the full LAT Van de Graff (17.6 Mev  ) –EM tower + qualification towers + only known energy  into full LAT SLAC End Station A positrons (7 days) (1-45 Gev) –Four qualification towers –Calibrate energy response SLAC End Station A photons (22 days) –Four qualification towers –Measure PSFs and effective areas SLAC End Station A protons (30 days) –Four qualification towers –Measure proton rejection Cosmic rays in airplane (25, ,000 feet) (few hours) –Full LAT

GLAST LAT ProjectI&T&C Particle Beams - Pre PDR Presentation– Oct. 2, 2001 Gary Godfrey7 Ground Cosmics Each tower as it becomes available at SLAC –~10 6 ~20 Hz x 1 day (use 3 in-a-row tracker trigger) –Natural cosmic solid angle distribution. No muon telescope. Four Tower Calibration Unit Full LAT –~10 8 ~300 Hz x 4 days (use 3 in-a-row tracker trigger) –Calibrate individual CsI xtals ADC chans/Mev Positional dependence –Calibrate tracker Dead and noisy strip map Straight tracks survey relative tray and tower positions –Calibrate ACD ADC chans / Mev Calibrate discriminator thresholds Efficiency vs position –Trigger and DAQ Search for problems Efficiency vs position

GLAST LAT ProjectI&T&C Particle Beams - Pre PDR Presentation– Oct. 2, 2001 Gary Godfrey8 Van de Graff (450 Kev) P + Li 7  Be 8 +  (17.6 Mev) (~1 Hz into 2  sr) EM tower and qualification towers –Calibrate energy response and resolution –10 4 Hz x 1day Full LAT –Only known energy  the full LAT DAQ will see before orbit Xtal Ball spectrum. Sum of 37 NaI xtals. ~1800  in the 17.6 Mev peak. It’s 7% FWHM is due to the resolution of the detector. The bump at 14.4 Mev is due to a broad excited state of Li7.

GLAST LAT ProjectI&T&C Particle Beams - Pre PDR Presentation– Oct. 2, 2001 Gary Godfrey9 Strategy First, calibrate Four Tower Calib Unit energy response and resolution –1–45 Gev e+ with variety of x,y,θ,Φ (7 days) (extrapolate to  response with MC) –.1,.2,.5, 1, 2, 5, 10, 30 Coherent brems  peaks, norm incid ( 3 days) –20 and 50 Mev channeling radiation  peaks, norm incid (2 days) –17.6 Mev  from Van de Graff Second, measure PSF and effective area –Bremsstrahlung  beam at one e + energy (30 Gev) ( 17 days) –Simultaneously measures all  energies from 20 Mev to 30 GeV –Brems spectrum has equal numbers of  per % width energy bin. –Use already calibrated LAT to bin the photons into ±25% energy bins. –An example of bin edges= [Gev] –.017,.026,.038,.057,.086,.19,.29,.44,.65,.98, 1.5, 2.2, 3.3, 5.0, 7.4, 11, 17, 25 Third, switch to hadron beam –~200 K /pulse x 30 Hz x 30 days x.58 accel effic –This is the number of protons we recorded in 30 days in Beamtest 99.

GLAST LAT ProjectI&T&C Particle Beams - Pre PDR Presentation– Oct. 2, 2001 Gary Godfrey10 End Station A Hardware Same as GLAST Beamtest ’99 except: –Upstream quartz radiator and dump magnet replaces our old copper radiator and tagger magnet. –Instrument goniometer (“Beamzilla”) to be upgraded to hold 4 towers in a clean, controlled, monitored, and approved environment. –Only certified people to work with flight hardware Schedule (abbreviated) –Aug ’03First qual tower arrives at SLAC –Jan 5, ‘03 - Mar 7, ‘04Requested 2 months of ESA running around this period. –Jul ’04Full LAT flies to environmental test

GLAST LAT ProjectI&T&C Particle Beams - Pre PDR Presentation– Oct. 2, 2001 Gary Godfrey11 ESA Test Beams and GLAST Tower ( Beamtest ’99)

GLAST LAT ProjectI&T&C Particle Beams - Pre PDR Presentation– Oct. 2, 2001 Gary Godfrey12 Runtime Estimate: ESA Positrons

GLAST LAT ProjectI&T&C Particle Beams - Pre PDR Presentation– Oct. 2, 2001 Gary Godfrey13 Runtime Estimate: ESA Coherent Brem Calculation (Peter Bosted) of  spectrum for four different beam energies and diamond xtal angles.

GLAST LAT ProjectI&T&C Particle Beams - Pre PDR Presentation– Oct. 2, 2001 Gary Godfrey14 Runtime Estimate: ESA Channeling Radiation Positron bounces back and forth between two lattice planes in a xtal. Graphs below are for 6 Gev positron beam on a 50 um thick diamond xtal  / e + in the third plot’s peak Only ~.0001  / positron pollution of peak from bremsstrahlung (if e+ channels) Possible problem: Angular divergence of secondary e + beam is larger than the channel’s acceptance. The many e + that don’t channel will just cause brems background.

GLAST LAT ProjectI&T&C Particle Beams - Pre PDR Presentation– Oct. 2, 2001 Gary Godfrey15 Runtime Estimate: ESA Channeling Radiation

GLAST LAT ProjectI&T&C Particle Beams - Pre PDR Presentation– Oct. 2, 2001 Gary Godfrey16 Brems Beam Measurements of PSF and Effective Area (Photons / Pulse vs. Photon Pollution) Average number of photons / pulse =1 maximizes the Poisson probability of exactly 1 photon in the pulse, but: –Sometimes 2  /pulse (eg: 20 Mev Mev). PSF can’t tell which converted. –If the 980 Mev  converts we measure the correct 1 Gev PSF. –If the 20 Mev  converts we put tails on the 1 Gev PSF Calculation for 30 Gev positron beam and two #  /pulse (1 and.13) –Brems  ’s detectable 20 Mev to 30 Gev, ±25% calorimeter energy bins Therefore, trade off #  /pulse (runtime) vs. PSF pollution –Must always use MC to unfold the true instrument PSF at a given energy

GLAST LAT ProjectI&T&C Particle Beams - Pre PDR Presentation– Oct. 2, 2001 Gary Godfrey17 Calculation That Gives the Photon Pollution Plot

GLAST LAT ProjectI&T&C Particle Beams - Pre PDR Presentation– Oct. 2, 2001 Gary Godfrey18 Runtime Estimate: ESA Bremsstrahlung Use 30 Gev e + beam. Choose n  avrg to give 22% lower energy  pollution for 1 Gev  bin. This is ~same pollution as in Beamtest 99.

GLAST LAT ProjectI&T&C Particle Beams - Pre PDR Presentation– Oct. 2, 2001 Gary Godfrey19 Runtime Estimate: Protons Avrg of 1 particle/pulse maximizes the exactly 1 particle pulses Mostly positrons and pions.0044 protons/pulse (measured in Beamtest ’99) ~200 K /pulse x 30 Hz x 30 days x.58 accel effic Choose a select variety of x,y,θ,φ Full proton rejection = ACD rejection x Pattern cut rejection Expect pattern cut rejection of 10 2 to get full rejection of –Ignore the ACD (otherwise the scintillator will reject ~all the protons!) –Only measure the pattern cut rejection factor and validate the MC

GLAST LAT ProjectI&T&C Particle Beams - Pre PDR Presentation– Oct. 2, 2001 Gary Godfrey20 Cosmics in Airplane Full LAT in an airplane (during airplane ride to NRL environmental test) L1T trigger rate measured in single tower during Balloon Flight At 25,000 feet verify the flight hardware at orbital L1T rates –~25 (BFEM size towers) x 540 Hz = 13.5 kHz –DAQ doesn’t crash –Software filter handles the rate and produces the expected downlink rate –Livetime is accurately measured At 35,000 feet test the flight hardware at > orbital L1T rates –~22 kHz saturates the LAT trigger –DAQ should not crash Altitude [Feet] BFEM L1T [Hz] Notes 025Ground 25,000540Same rate as in orbit 35,000900Airplane flight 50, Pfotzer max 127,000540~Orbital rate 0 140,000 feet

GLAST LAT ProjectI&T&C Particle Beams - Pre PDR Presentation– Oct. 2, 2001 Gary Godfrey21 LAT Shipping Box Features Capabilities already present from taking cosmics in Bldg 33. –Mechanical support points on grid –Liquid cooled heat exchangers bolted to grid radiator surfaces –LAT only works in horizontal position because of grid heat pipes –Portable 1-2 Kw liquid chiller (<0° C for SLAC pre-thermal-vac tests?) –Pseudo solid state recorder on the 30 Mbit/sec data cable –Cat 5 cable to the GSE computer (=Laptop computer in plane) –LAT runs on 28vdc New shipping box features –Shock mounts to support points on grid –Box thermal insulation so elec power + chiller stabilizes temperature –MicroDAQ (3 of them) Monitors (Temp,Press,Hum,3 axises accel) –Flow dry nitrogen to keep humidity low DAQ philosophy (like Balloon flight) –Turn on 28 v power and LAT comes up recording data in a preset config. –Laptop is for realtime voltage, current, environmental monitoring –Laptop is for limited “mission creep” (few commands, event display,..?) –~No new software beyond existing flight and GSE

GLAST LAT ProjectI&T&C Particle Beams - Pre PDR Presentation– Oct. 2, 2001 Gary Godfrey22 LAT Shipping Box Conceptual Drawing

GLAST LAT ProjectI&T&C Particle Beams - Pre PDR Presentation– Oct. 2, 2001 Gary Godfrey23 Schedule