RIT Senior Design I, Project Review P07310: Electronic Shifted Manual Transmission George Slack Team Guide Jason BotterillTeam Leader, Mechanical Engineer Vaibhav KothariIndustrial Engineer Richard ChengElectrical Engineer Yi-Fan ZhangMechanical/Testing Engineer Sponsor: Polaris Industries P07310: Polaris ESMT 1
RIT Senior Design I, Project Review P07310: Project Description Semi-automatic shifting system for the Polaris Outlaw 525 high-performance ATV. Target market: High-performance sport ATV riders. P07310: Polaris ESMT 2
RIT Senior Design I, Project Review P07310: Key Specifications and Features Specifications: Weight:< 7 lbs. Shift Time:<.1 sec. Cost:< 5000 units built Features: Push-Button Shift Control Reverse Lockout Gear indicator P07310: Polaris ESMT 3
RIT Senior Design I, Project Review P07310: Control Interface Design Upshift Downshift P07310: Polaris ESMT 4
RIT Senior Design I, Project Review P07310: System Flowchart Rider pushes shift button System cuts ignition System shifts transmission System restores ignition Rider resumes normal operation P07310: Polaris ESMT 5
RIT Senior Design I, Project Review P07310: Project Risk Assessment Risk: Slow electrical design progress PLC not sufficiently specified Sensor parameters not sufficiently defined Motor control scheme not defined Proposed Mitigation: Increased supporting professor consultation Accelerated deliverables timetable P07310: Polaris ESMT 6
RIT Senior Design I, Project Review P07310: Project Risk Assessment Risk: Lack of suitable test bench design No working design has yet been produced Current designs are inherently flawed Proposed mitigation: Consult with advising professors Propose simplified design Design/build in parallel with other systems work Backup plan: Use ATV on jack stands for systems testing P07310: Polaris ESMT 7
RIT Senior Design I, Project Review P07310: Project Risk Assessment Risk: Complex mechanical system Mechanical shifting system is inherently complex Proposed mitigation: Develop secondary plan in parallel with primary solution P07310: Polaris ESMT 8
RIT Senior Design I, Project Review P07310: Project Risk Assessment Risk: Shortened design schedule ATV arrived after concept review (week 5) True concept review occurred in week 8 (3 weeks late) Detailed design phase running behind schedule Proposed Mitigation: Accelerate deliverables timetable Increase supporting professor input to decrease development time Reduce scope to necessary functions and features only P07310: Polaris ESMT 9
RIT Senior Design I, Project Review P07310: Product Development Process Phase Phase 0: Planning Phase 1: Transmission Concept Development Phase 2: System Level Design Phase 3: Detailed Design Phase 4: Testing and Refinement MSD IMSD II Current Phase of Development Alpha Prototype P07310: Polaris ESMT 10
RIT Senior Design I, Project Review P07310: Current State of Design Control interface system meets customer needs Mechanical system meets customer needs (confirmation tests pending) Electrical system is incomplete Test bench design is incomplete On target for $250 cost per unit Current projected cost per unit: Mitigations: Development timetables for electrical system and test bench accelerated Cost per unit projections need to be adjusted for 5000 unit run P07310: Polaris ESMT 11
RIT Senior Design I, Project Review P07310: MSD II Schedule Highlights Wk 2: Design finalized and all components on order Wk. 4: Test bench completed and instrumented Wk. 4: Prototype systems completed Wk. 6: Test bench program completed, begin ATV testing Wk. 8: Function and performance review Wk. 9: Documentation completed (Formal paper, poster, etc.) Wk. 10: Final design review P07310: Polaris ESMT 12