1 Project Manager Report Andy Nichols, STFC – RAL MICE Collaboration Meeting, Harbin, 13-17th January 2009.

Slides:



Advertisements
Similar presentations
1 UK Project Alan Grant, STFC. Finance How savings are made Update on stepIV position Milestones Critical Path - stepIV Concerns 2.
Advertisements

1 MICE Project Board Schedule and risk discussion Introduction Project Management comment Schedule considerations Adapting the schedule/reacting to circumstances.
1 MICE CM31 Key schedule drivers for Step IV Schedule table Milestone summary Comment on Step V Step VI Andy Nichols, STFC, 3/11/11.
1 MICE Video Conference Installations to date Future installation work Plans for May shutdown MICO organisation Use of Technical Board.
1 MICE PM Report General Update –Phase I civil engineering –R5.2 in June –Phase II design work –Phase II hardware –A few questions –Schedule, milestones.
1 MICE Funding Agency Committee Technical Status of the MICE Project Contents: Technical organisation of project Target Decay solenoid Infrastructure Moving.
1 UKNF/MICE Oversight Committee Open session Integration of the MICE project Background & local history Progress since 2007 Schedule & planning considerations.
March 2003 Paul Drumm MICE Collaboration Meeting, CERN 1 Beam Line & Installation Plans Paul Drumm CLRC Rutherford Appleton Laboratory.
1 Subsystem Reviews Reviews this week: RFCC modules RF Power Infrastructure MICE Infrastructure LH2 system.
1 MICE PM Report Installations to date Future installation work Preparations for Phase Two Target status MICE Video Conference, 22nd May, 2008.
1 MICE Project Board Schedule and milestones Reconstructing the schedule Present status Monitoring and feedback Key schedule drivers and concerns Andy.
1 RF Power infrastructure Andy Nichols, STFC – RAL MICE Collaboration Meeting, Harbin, 13-17th January 2009.
1 Infrastructure issues Andy Nichols, STFC – RAL MICE Collaboration Meeting, Harbin, 13-17th January 2009.
1 Implications Of Infrastructure Build The Infrastructure Project is bigger than anyone thought, but now it’s understood The cost was underestimated, but.
1 MICE-UKNF Oversight Committee MICE Project Manager Report Contents: General Technical organisation and status Target update Decay solenoid update Infrastructure.
1 Summary of MICE beamline & hall installations This is a very rough summary of the progress since mid-December Richard Apsimon & Andy Nichols MICO meeting.
1 Project Manager Report Andy Nichols, STFC MICE Collaboration Meeting, RAL, June 2009.
1 MICE PM Report Phase One installations to date Phase One remaining items Progress with Phase Two Phase Two planning sequence Worries Don’t have time.
1 MICE Video Coference Project Manager Report Contents: Technical organisation of project Target and upstream beamline Muon beamline Infrastructure and.
1 MICE CM32 Summary Scheduling and planning; aims for this year Schedule update Main schedule drivers Keeping us on schedule Comment on Steps V & VI Detail.
1 MICE-Video Conference Status of MICE Hall Contents: General status Electrical Mechanical Preparing for Steps II & III Risks and worries Andy Nichols,
1 Hall & Beamline Installation Richard Apsimon, Andy Nichols, Willie Spensley MICE Collaboration Meeting, th Feb 2008.
1 Technical Co-ordination, Phase One The shared post of PM/TC has worked quite well Six months ago there was much for us to learn:  Revised the WBS 
1 MICE - INFRASTRUCTURE MICO meeting 7 th February 2008 Tim Hayler.
UKNF/MICE PSAG, 3/5/11 Spectrometer solenoids: –Repair plan still ‘in approval’, already two months late –Workshop/mini review at LBNL 10 th /11 th May.
Infrastructure Update As at 11 th March 2009 Remaining four plates now fitted to North shield wall North & South walls and all galleries are considered.
1 MICE PM Report Phase One installations to date Problems with target & decay solenoid and rolling platforms Phase One remaining items Progress with Phase.
1 MICE PSAG PM report Brief overview Re-planning the project Solenoids, decay and spectrometer Open issues and worries Andy Nichols, STFC, PSAG, 5/5/10.
1 UK PM Report Costs & Schedule Alan Grant, STFC.
1 MICE PM Report Completion of Infrastructure Target, solenoids Phase Two planning & schedule Non-MICE costs Staffing & visitors Don’t have time for a.
Project manager report paul drumm CM16 October 2006.
K. Long, 10 October 2015 Project Manager’s report Status/progress since CM18 Looking forward Organisation Conclusions.
Preparations in the MICE hall Video Conference 25 th June 09 Tim Hayler Andy Lintern Peter Lau Geoff Barber.
1 MICE CM28 PM Report Progress since CM27 Schedule, dates, milestones Electrical substation Visiting RAL Andy Nichols, STFC 4 th October 2010.
1 MICE CMPB Contents: Progress to date Project management things Plans for the May shutdown Steps towards Phase Two Problems and open issues summary Andy.
Electrical Integration CM38 Steve Griffiths & Ian Mullacrane.
1 Project Manager Report Andy Nichols, STFC – RAL MICE Collaboration Meeting, RAL, nd October 2008.
1 Project Manager Report Andy Nichols, STFC – RAL MICE Collaboration Meeting, DL, 4 th -7 th June 2008.
Technical Board and Safety Summary Michael S. Zisman Center for Beam Physics Accelerator & Fusion Research Division Lawrence Berkeley National Laboratory.
1 MICE Hall construction status Richard Apsimon MICE VC meeting 29th Nov 2007.
1 MICE Hall and Infrastructure - Progress since CM18 Chris Nelson MICE CM19 Oct 2007.
1 MICE PM Report Outcome of Reviews held at CM22 –Motivation for holding them –Outcomes & actions –Observations & follow-ups MICE Video Conference, 20.
MICE Status & Plans MICE-UK paul drumm 15 th September 2004.
1 MICE PM report Target News Outcome of Spectrometer Solenoid Review New plans for Steps II & III RF Power news MICE CMPB, 4th December, 2009.
1 MICE PM Report Summary since CM21 Decay solenoid Infrastructure progress Step One Installation Worries MICE Video Conference, 19 th June, 2008.
1 MICE Beamline Installation, status & plans Contents: Upstream & Target, BPM Decay solenoid DSA, D2, Q4,5,6 cKOV support Q7,8,9 Open issues & concerns.
1 MICE CM27 PM Report Re-defining the UK project this FY Schedule things Apologies and accommodation Andy Nichols, STFC 7 th July, 2010.
MICE Project Report Alan Bross (for Paul Drumm). Project Issues ● Key dates: – ISIS Synchrotron start-up scheduled for 1st August ● Shielded area around.
1 Engineering Session Summary Andy Nichols, STFC MICE Collaboration Meeting, RAL, June 2009.
Pre-CM33 schedule planning SuperMICO meeting, June 6th Motivation: For all of us to understand the main drivers behind the top-level MICE schedule So that.
OsC mtg 24/4/2014 OsC mtg Alan Grant. 2 OsC mtg 24/4/ MICE Finances - Forward Look.
MICE VC Alain Blondel 1 1. MOM is now Victoria 2. Linda Coney is new MICE Online Group coordinator (rep Jean-Sebastien) May we held.
1 MICE PM Report General Update –Phase I nearing completion –MICE Power –Actions for Decay solenoid & target –Follow-ups from last VC –Conclusions MICE.
1 MICE PM Report Infrastructure/integration progress Electrical work AFC, diffuser, etc Help with project control & staffing issues Worries & problems.
1 MICE Schedule Review no 1 Aims of review and description of review charge Motivation and external drivers Aims of the review A few of the problems Description.
MICE CM20 Alain Blondel 10 February The International Muon Ionization Cooling Experiment MICE CM20 Spokesmouse remarks.
Status of the MICE Construction Project Resource Loaded Schedule Review 29 th April 2014 Roy Preece.
1 Project Infrastructure for steps I-III Tim Hayler, STFC – RAL MICE Collaboration Meeting, RAL, nd October 2008.
MICE CM23 Introduction and Meeting Goals Michael S. Zisman Center for Beam Physics Accelerator & Fusion Research Division Lawrence Berkeley National Laboratory.
Malcolm Ellis – Brunel University – 8th April The International Muon Ionization Cooling Experiment.
Technical Board Summary Alan Bross MICE CM17 CERN February 25, 2007.
1 UK Project Roy Preece – STFC Alan Grant, STFC. Finance Staffing Update on stepIV position Milestones Critical Path – stepIV Magnetic field mitigation.
1 MICE PM Report Phase One installations to date Phase One remaining items Progress with Phase Two Worries Don’t have time for a detailed status report,
Schedule and Milestones Roy Preece STFC RAL FAC 17 th April 2015.
1 UK Project Finance & Schedule. Overview Finance  Budget Setting 2013/14  June Finance  Forward look to complete stepVI Schedule  Overview 2.
1 MICE CM29 Engineering Summary Cooling channel moving platforms – Norbert Floor Beams and plates – Andy L Magnetic modelling – Mike RF Engineering – Andy.
1 MICE CM25 Engineering Session Summary Contents: Infrastructure Diffuser Coupling Coils Radiation Shutter AFC module EMR Andy Nichols, STFC, 4-7 th November.
MICE CM31 Schedule summary
MICE PM Report Progress with the Infrastructure A few problems
Presentation transcript:

1 Project Manager Report Andy Nichols, STFC – RAL MICE Collaboration Meeting, Harbin, 13-17th January 2009

2 Contents: Achievements since CM22 Decay solenoid & target Infrastructure Cooling channel elements Preparations for Phase Two Project Organisation

3 Achievements since CM22 Briefly: –Both shield walls complete (except for four plates, delivery 23 Jan) and painted –All galleries and stairways installed –TOF1 installed and commissioned –Sliding beamstopper at DSA working –DSA roof and walkways installed (at long last) –Significant progress with false floor –LH2 project has ‘re-started’ –RF cavities ready to start manufacture –Air conditioning project started –Online Group formed More detail will follow later in the week I’m sure

4 Decay solenoid & target Decay solenoid –Currently the top priority for MICE right now! –Linde cooling plant is working reliably with adequate cooling power –But the solenoid still has coil 10 normally conducting –Can take ~ 200 amps before quenching –Powering tests being done, much voltage data taken, being analysed now –Dismantling being planned: Part removal of cold mass Hardware is complete Experts from PSI should be present –If we have to remove cryostat from synchrotron aperture, we compromise shielding No work in Hall! –So we are building a steel shield inside synchrotron, finish 20 th Jan –Aim to get solenoid working by end March

5 Decay solenoid & target Target: –Another popular issue! –The installed target in ISIS has given very good service, but failed terminally in December –Due to be extracted 10 th January, subject to radiation survey we can then examine it – very interesting to compare with seized off-line target –In any case, the target upgrade is now a robust plan: –Time constrains us to keep with current reciprocating blade running in bearings configuration –But shaft will be simplified and made stiffer –Bearings simplified –Shaft/bearing interface better controlled –Surface finish and coatings better understood and controlled –More detail from Chris

6 Infrastructure South Shield Wall –All plates are on and painted –LH2 gallery is complete North Shield wall –All plates on and painted, (except four! Delivery 23 Jan) –RF gallery and stairways installed False floor –A few problems, drilling floor anchors – hard bits in concrete floor and struck water – about three weeks’ delay all fixed now though –Steel fabrication is complete –Floor installation complete 31 st Jan DSA walkways and roof –After a long saga – done Air conditioning –Tender action has started – timetable made to complete North-East corner of Hall by 31 st March 2009 – vital for operation of Linde plant

Infrastructure Electrical & PPS –Is going much better now –Regular attendance by DL staff –Ian Mullacrane has thoughtfully collected the tasks and made milestones – monthly progress meetings now alternate between DL & RAL –Non DL electrical effort continues to be a worry Fire alarms Lighting upgrade Smoke detection Are all now quite late 2 MVA Substation upgrade –Lower cost option (£50K) worked out by DL engineers –Approved by both STFC electrical authority and MICE TB –Strictly a non-MICE cost – hopeful for funding by STFC Operations Board –It’s a significant open issue

8 Cooling channel elements Focus Coils –Good progress with Tesla Engineering, more useful design review held –Problems with coil former getting clearer –But about two month delay in schedule RFCC –Good progress with coil winding –Successful Production-Readiness Review of cavities in October – essentially ready for manufacture LH2 system –R&D hardware manufacture has re-started after visits to vendor –Control system philosophy is being understood better – this must be reported back to MICE formally –Recruitment has been approved for STFC LH2 project: One engineer/scientist (March 2009) One graduate mechanical engineer (summer 2009)

9 Preparations for Phase Two Planning & organisation: –Many thanks to those who provided milestone dates and review material at CM22 –Enabled a detailed project plan to be started – but I’m still working on it – However, Alain’s aspirational schedule is based on it Practicalities –CAD drawings of each discrete MICE step are making progress –These will form top level integration document –Integration/design team have visited DL to think about installing RF amplifiers (not so easy) –Have also had useful exchange with RFCC group – this will be the most complicated bit –Manufacture of Phase Two subsystems seems to be going pretty well on the whole

10 Project Organisation Not much to say here: –MICE EB agreed that the TB should also be responsible for local safety policy – new members co-opted, two meeting held so far –Throughput of visitors increasing, no real problems though –Rose Hayes now established as Liaison Officer –There have been some breaches of the CDM rules in the MICE Hall; these must stop! The PM and Principal Contractor are working on ways to reinforce the procedures –Online Group has been formed –A revised Target working Group established