Luminosity Monitor MWPCs. Status and plans. A.Kiselev OLYMPUS Collaboration Meeting DESY, Hamburg,
Current activity Funding Electronics, infrastructure, etc GEANT3 Monte-Carlo simulations Space limitations? Construction plans
Space limitations 180x180mm possible? Wire chamber frame/cabling? Coil installation tolerance? degree view19.45 degree view0.00 degree view
Tentative schedule Design, materials, etcMay-Jul 2010 First 3 chambers readyDec 2010 Test run installationDec 2010 – Feb 2011 Test runFeb-Jul 2011 Remaining chambers readyJul 2011 Final installationJul-Aug 2011 CommissioningAug-Dec 2011