Paul Emma, et al. LCLS FAC May 13, 2008 1 LCLS Commissioning: Results & Plans P. Emma, for the LCLS Commissioning Team LCLS FAC.

Slides:



Advertisements
Similar presentations
Joe Frisch LCLS FAC Oct. 30, Linac/BC2 Commissioning (Dec through Sep., 2008) J. Frisch, et al. LCLS FAC Meeting.
Advertisements

P. Emma FAC Meeting 7 Apr Low-Charge LCLS Operating Point Including FEL Simulations P. Emma 1, W. Fawley 2, Z. Huang 1, C.
Hal Tompkins FEE/FEL June 16, FEE/FEL Commissioning Overview By Hal Tompkins Photon Beam Systems Deputy.
Paul Emma LCLS FAC April 16, Initial Experience with Injector Commissioning P. Emma, et al. Facilities Advisory Committee.
October 30, 2007 Heinz-Dieter Nuhn, SLAC / LCLS Undulator Commissioning Plans 1 Undulator Commissioning Plans Heinz-Dieter Nuhn,
James Welch October 30, FEL Commissioning Plans J. Welch, et. al. FEL Commissioning Plans J. Welch, et. al. Accelerator.
1 Daniel Ratner 1 Gain Length and Taper August, 2009 FEL Gain length and Taper Measurements at LCLS D. Ratner A. Brachmann, F.J.
P. Emma, SLACLCLS Commissioning – Sep. 22, 2004 Linac Commissioning P. Emma LCLS Commissioning Workshop, SLAC Sep , 2004 LCLS.
Heinz-Dieter Nuhn, SLAC / LCLS LTU/Undulator Commissioning Plans June 16, LTU/Undulator Commissioning Plans Heinz-Dieter.
P. Emma, SLACLCLS FAC Meeting - April 29, 2004 Linac Physics, Diagnostics, and Commissioning Strategy P. Emma LCLS FAC Meeting April 29, 2004 LCLS.
P. Emma FAC Meeting 27 Oct Physics Update P. Emma FAC Meeting October 27, 2005 LCLS.
Feedback and CSR Miniworkshop on XFEL Short Bunch, SLAC, July 26 – 30, 2004 Juhao Wu, SLAC 1 Juhao Wu Stanford Linear Accelerator.
Eric Bong LCLS FAC Injector-Linac October 27, 2005 Injector Design / Diagnostics / Gun & Linac RF Design E. Bong LCLS FAC.
Accelerator Issues and Design Linac Coherent Light Source Stanford Synchrotron Radiation Laboratory Stanford Linear Accelerator.
Paul Emma LCLS Commissioning Status Nov. 11, 2008 SLAC National Accelerator Laboratory 1 LCLS Commissioning Status P. Emma for The.
James Welch October 29, 2007 Injector Commissioning Injector Commissioning Results presentated to the Facilities Advisory Committee,
D. Schultz FAC 6/17/08 1 e-Beams Systems Update People Progress the last review LTU and Dump Installation Status Undulator.
Feedback and CSR Miniworkshop on XFEL Short Bunch, SLAC, July 26 – 30, 2004 Juhao Wu, SLAC 1 Juhao Wu Stanford Linear Accelerator.
Hamid Shoaee LCLS FAC Controls June 17, LCLS Control System Personnel Linac & BC2 Controls progress LTU, Dump Controls.
Eric Bong LCLS FAC Injector-Linac System October 27, 2005 Injector –Linac System Overview E. Bong LCLS FAC October 27, 2005.
E. Bong, SLACLCLS FAC Meeting - April 29, 2004 Linac Overview E. Bong LCLS FAC Meeting April 29, 2004 LCLS.
LCLS Transition to Science DOE Status Review of the LUSI MIE Project Near term opportunities for LCLS 'upgrades' J. Hastings for the LCLS Experimental.
RF Systems and Stability Linac Coherent Light Source Stanford Synchrotron Radiation Laboratory Stanford Linear Accelerator Center.
Hamid Shoaee LCLS FAC Review – October Control System Overview Hamid Shoaee Controls System Manager Injector control system commissioning & Support.
Paul Emma Injector/BC1 Commissioning April 20, Injector/BC1 Commissioning (Dec. 1, ’06 through Aug. 1, ‘07) P. Emma LCLS.
Henrik Loos High Level 17 June 2008 High Level Physics Applications for LCLS Commissioning Henrik Loos.
P. Emma, SLACICFA XFEL July 29, 2004 Electron Bunch Measurements with a Transverse RF Deflector P. Emma ICFA XFEL 2004 Workshop July 29, 2004 ICFA.
Diane Fairley High Level October High Level Applications FAC Review October 12, 2006 High Level Applications.
LCLS Status and Micro-Bunching Workshop at LBNL Torsten Limberg.
Injector Accelerator Readiness Review, 10/31/06 Henrik Loos 1 Beam Losses During LCLS Injector Phase-1 Operation Scope of phase 1 operation Operating modes.
S2E in LCLS Linac M. Borland, Lyncean Technologies, P. Emma, C. Limborg, SLAC.
David Schultz Accelerator Readiness Dec. 2, ‘08 SLAC National Accelerator Laboratory 1 Undulator Complex Status LCLS Introduction.
SPPS, Beam stability and pulse-to-pulse jitter Patrick Krejcik For the SPPS collaboration Zeuthen Workshop on Start-to-End Simulations of X-ray FEL’s August.
LCLS Accelerator SLAC linac tunnel research yard Linac-0 L =6 m Linac-1 L  9 m  rf   25° Linac-2 L  330 m  rf   41° Linac-3 L  550 m  rf  0°
Henrik Loos LCLS 6 February 2009 SLAC National Accelerator Laboratory High Level Physics Applications for LCLS Commissioning.
Optimizing X-ray FEL performance for LCLS at SLAC Sean Kalsi on behalf of SLAC MCC operations group, WAO August 8, 2012.
A bunch compressor design and several X-band FELs Yipeng Sun, ARD/SLAC , LCLS-II meeting.
1 Franz-Josef Decker 1 Multi-Bunch Operation for LCLS Franz-Josef Decker March 17, Definitions and goals multi-bunch within.
Diagnostics Overview for the LCLS Presented by Josef Frisch For the LCLS ANL / LBNL / LLNL / SLAC.
John N. Galayda DESY October 8, LCLS Commissioning in 2008 J. Galayda, for The LCLS Construction/Commissioning.
J. Wu J. Wu working with T.O. Raubenheimer, J. Qiang (LBL), LCLS-II Accelerator Physics meeting April 11, 2012 Study on the BC1 Energy Set Point LCLS-II.
P. Krejcik LINAC 2004 – Lübeck, August 16-20, 2004 LCLS - Accelerator System Overview Patrick Krejcik on behalf of the LCLS.
‘S2E’ Study of Linac for TESLA XFEL P. Emma SLAC  Tracking  Comparison to LCLS  Re-optimization  Tolerances  Jitter  CSR Effects.
J. Wu J. Wu working with T.O. Raubenheimer LCLS-II Accelerator Physics meeting May 09, 2012 Study on the BC1 Energy Set Point LCLS-II Accel. Phys., J.
FEL Spectral Measurements at LCLS J. Welch FEL2011, Shanghai China, Aug. 25 THOB5.
Franz-Josef Decker 14-Dec-2011 CSR is a big deal limiting performance Tolerance studies beforehand helped a lot Tor’s List Software adaptability helped.
PAL-XFEL Commissioning Plan ver. 1.1, August 2015 PAL-XFEL Beam Dynamics Group.
A single-shot method for measuring fs bunches in linac-based FELs Z. Huang, K. Bane, Y. Ding, P. Emma.
Applications of transverse deflecting cavities in x-ray free-electron lasers Yuantao Ding SLAC National Accelerator Laboratory7/18/2012.
Slice Parameter Measurements at the SwissFEL Injector Test Facility
Short pulse, low charge LCLS operation
Beam-Based Feedback in LCLS-II
LCLS Linac Update Brief Overview L1 & BC1 Progress LTU & E-Dump Status Continuing Resolution Impact.
Time-Resolved Images of Coherent Synchrotron Radiation Effects
Commissioning Status of the LCLS Accelerator and Undulator Systems
LCLS Longitudinal Feedback and Stability Requirements
Linac/BC1 Commissioning P
LCLS Commissioning P. Emma, et al
Overview Pre-Beam Checkouts
LCLS Tracking Studies CSR micro-bunching in compressors
High Level Physics Applications for LCLS Commissioning
LCLS Commissioning: Results & Plans P
Linac Physics, Diagnostics, and Commissioning Strategy P
Diagnostics RF and Feedback
Linac Diagnostics Commissioning Experience
Operational Experience with LCLS RF systems
LCLS Injector Commissioning P
P. Emma, for the LCLS Commissioning Team LCLS DOE Review May 14, 2009
Linac Design Update P. Emma LCLS DOE Review May 11, 2005 LCLS.
Physics Update P. Emma FAC Meeting October 27, 2005 LCLS.
Presentation transcript:

Paul Emma, et al. LCLS FAC May 13, LCLS Commissioning: Results & Plans P. Emma, for the LCLS Commissioning Team LCLS FAC Meeting June 16, 2008 LCLS Phys. Rev. publication:

Paul Emma, et al. LCLS FAC May 13, LCLS Accelerator Layout SLAC linac tunnel research yard Linac-0 L =6 m Linac-1 L  9 m  rf   25° Linac-2 L  330 m  rf   41° Linac-3 L  550 m  rf  0° BC1 L  6 m R 56   39 mm BC2 L  22 m R 56   25 mm DL2 L =275 m R 56  0 DL1 L  12 m R 56  0 undulator L =130 m 6 MeV  z  0.83 mm    0.05 % 135 MeV  z  0.83 mm    0.10 % 250 MeV  z  0.19 mm    1.6 % 4.30 GeV  z  mm    0.71 % 13.6 GeV  z  mm    0.01 % Linac-X L =0.6 m  rf =  21-1 b,c,d...existing linac L0-a,b rfgun 21-3b24-6d X 25-1a30-8c Injector Commissioned (‘07) Commissioned in Jan beam parked here

Paul Emma, et al. LCLS FAC May 13, OTR screens (7) YAG screens (7) Wire scanners (7) Dipole magnets (8) Beam stoppers (2) S-band RF acc. sections (5) RF Gun Solenoid GunSpectrometer RFDeflector X-band RF acc. section BC1 L1S L0a L0b 2-km point in 3-km SLAC linac LCLS Injector Layout 135-MeVSpectrometer EmittanceScreens/Wires EmittanceScreen/Wires 135 MeV 6 MeV 250 MeV TD11stopper Commissioned in ‘07

Paul Emma, et al. LCLS FAC May 13, LCLS BC2 Area Layout (sector 24/25) OTR screens (3) Dipole magnets (4) S-band RF acc. sections 4.3 GeV (not to scale) BC2 OTR21 OTR22(25-3d) OTR_TCAV(25-9) BXKIK Kicker magnet (1) TCAV3(25-2d) 4 wire-scanners “de-scoped” Transverse RF deflector (1) 4 wire-scanners in sec-28 (300 m downstream) PH03 BPMS21 Phase monitor cavity (1) CE21 Collimator jaws (2 New installation in fall ‘07

Paul Emma, et al. LCLS FAC May 13, Commissioning Highlights Injector commissioning: April through August, 2007 (DONE) Phase-II commissioning: Dec.  Complete 3/31/08 (BC2 + Linac) Up to 1 nC of bunch charge available (mostly 0.25 & 0.5 nC used) Great laser uptime (99%) and good performance (again) Emittances  1  m after BC1 at 1 nC, 250 MeV (fairly routine) Routine e  to 14 GeV (24/7 except Wed. - ~90% up-time) BC1 dipoles & chicane motion fixed! No emittance growth in X-band RF cavity when best steered BC2 compression demonstrated (no dipole field quality issues) CSR effects measured in BC1 & BC2 – agree with codes so far Many beam (8) & RF (8) feedback systems running well Tested energy switching: 14, 10, 7.0, 4.3 GeV (<5 min. switch) Coherent OTR observed – compromises nearly all screens Gun RF probes changed in April ’08 (allows 120-Hz)

Paul Emma, et al. LCLS FAC May 13, Design and Typical Measured Parameters

Paul Emma, et al. LCLS FAC May 13, “Problems/Issues” from July ‘07 DOE Review Gun Faraday cup broken Gun toroid shorted during installation Some YAG screens not installed properly BC1 motion control limited (300 mm  260 mm) Cathode QE about 5-times lower than design Some controls tools late (orbit displays, fitting, magnet control & alarms) MCOR power supply ADC readback noise (fixed) Laser phase drift and lock trouble until mid-June ALL FIXED

Paul Emma, et al. LCLS FAC May 13, Laser Spatial and Temporal Shaping Temporal shape (6.6 ps FWHM) Spatial shape on cathode using iris S. Gilevich, G. Hays, P. Hering, A. Miahnahri, W. White 99% Drive Laser up time! 7.2 ps R = 1.4 mm ps 2008

Paul Emma, et al. LCLS FAC May 13, Quickly minimize emittance by scanning any parameter H. Loos Watch profiles as scan proceeds Powerful Scanning/Correlation Application

Paul Emma, et al. LCLS FAC May 13, Projected Emittance <1.2 μm at 1 nC (135 MeV)  x = 1.07 μm  y = 1.11 μm meetsinjectorgoals  = 60 μm

Paul Emma, et al. LCLS FAC May 13, Injector Emittance Measured Over 3 Days (0.25 nC)  x  y OTR screen at 135 MeV wire-scanner at 250 MeV after BC1  x  = 0.91,  y  = 1.01  x  = 0.83,  y  = 0.83 J. Welch injector is stable

Paul Emma, et al. LCLS FAC May 13, Laser & Electron-Based Feedback Systems L0 gun L3L2 X DL1BC1 DL2 L1 z1z1z1z1 1111 1111 V1V1V1V1 z2z2z2z2 2222 2222 V2V2V2V2 3333 V3V3V3V3 0000 V0V0V0V0 D. Fairley J. Wu J. Frisch Longitudinal Loops: DL1 energy BC1 energy BC1 bunch length BC2 energy BC2 bunch length Final energy (old loop) BC2 Laser Transverse Loops: Laser spot on cathode (2) Gun launch angle Injector trajectory X-band cavity position Linac trajectory (2 old) Undulator traj. (future) nowrunning BPMs CSR detectors Steering Loop (bunch length feedback still needs work)

Paul Emma, et al. LCLS FAC May 13, Bunch Length & Energy Feedback Systems Q = 0.25 nC  Q 2  1/2 /Q = 1.5% bunchcharge DL1 energy BC1 energy BC2 energy DL2 energy BC2 peak current BC1 peak current 216 ± 12 A 2170 ± 217 A 0.09% rms 0.03% rms 0.05% rms 0.03% rms Charge feedback:

Paul Emma, et al. LCLS FAC May 13, BC1 Dipole Field Quality Fixed Aug. ‘07 Nov. ‘07 Sext.tolerance J. Welch, S. DeBarger, N. Li, et al. ±3  beam fixed Poles were milled off and wider poles were bolted on and then the fields were shimmed.

Paul Emma, et al. LCLS FAC May 13, BC2 Dipole Field Quality OK No measurable quad field and sextupole is just at tolerance ±3  beam Beam energy scans confirm BC2 dipole field quality meets requirements OK

Paul Emma, et al. LCLS FAC May 13, Operating Point Summary Display H.-D. Nuhn Shows operators the main machine parameter targets and their present settings & includes save/restore files

Paul Emma, et al. LCLS FAC May 13, BPM-Measured CSR Energy Loss in BC1 at 0.25 nC (compares well with tracking) BPM Chicane Bend Y. Ding, Z. Huang A Phase shift of  0.4 deg is added to the Elegant curves CSR energy loss after BC1 measured with BPM Bunch length after BC1 measured with transverse RF Elegant BC2OFFBSY (14 GeV) TCAV (5.0 GeV) BC1 (250 MeV) L1SBPM operatingpoint  eeee

Paul Emma, et al. LCLS FAC May 13, Now plot horizontal emittance after BC1  º  x = 38  m  x = 55  m  º  x = 246  m  º Hor. CSR Emittance Growth after BC1 (250 MeV, 0.25 nC) ElegantMeas-1Meas-2ElegantMeas-1Meas-2 Horizontal emittance after BC1 vs. RF phase Vertical emittance after BC1 is almost unaffected Y. Ding, Z. Huang Elegant Data also exists at 1 nC and BC2 data (0.25 nC) also shows decent results Elegant operatingpoint

Paul Emma, et al. LCLS FAC May 13, RF Phase and Amplitude Stability (e.g., L0a) 0.05º rms (<0.07º) 0.05% rms (<0.07%) 20-second sample at 10 Hz New inj. RF systems meet jitter tolerances R. Akre, D. Kotturi, J. Craft, V. Pacak, et al. RF Feedback Running

Paul Emma, et al. LCLS FAC May 13, Normalized phase space centroid jitter after BC1 (~4% of rms beam size) D. Ratner Stability is not so far off of our goals (~10%) … near end of linac (~12% of rms beam size, but sometimes larger) Thanks to Controls group for new BPM electronics! RMS A xN = 14% RMS A yN = 9%  E/E jitter  0.03%  Q/Q jitter  1.5% RMS A xN = 3.9% RMS A yN = 3.4% 1-  beam size Q = 0.25 nC

Paul Emma, et al. LCLS FAC May 13, BC2 Chicane in the Linac at 4.3 GeV Chicane length 24 m, 4.3 GeV, 2º bends BobFuller

Paul Emma, et al. LCLS FAC May 13, Bunch Compression Measured after BC2 (0.25 nC)  z > 25  m BC2 (4.3 GeV) BSY (14 GeV) TCAV (5.0 GeV) 550 m  z < 10  m old screen used – poor res. Bunch length after BC2 measured with transverse RF  2 º shift applied to simulation  z  10  m L2 resolution limit

Paul Emma, et al. LCLS FAC May 13, Bunch is Over-Compressed L2 phase =  41 deg Chirp knob =  450 MeV Bunch is Under-Compressed L2 phase =  41 deg Chirp knob =  450 MeV Longitudinal Phase Space at 14 GeV older screen has poor resolution Vertical scale only approx. LiTracksimulation LiTracksimulation PR55 PR55 measurement measurement Transverse RF is ON Q = 1 nC

Paul Emma, et al. LCLS FAC May 13,  y = 0.9  m Q = 0.25 nC  y = 0.9  m Q = 0.25 nC Emittance measured 300 m after BC2 at 10 GeV with 10  m bunch length Emittance Measurements at End of Linac Using Wire Scanners  x = 76  m  x = 38  m  x = 49  m  x = 47  m wire scans Results still variable – requires careful work F.-J. Decker R. Iverson

Paul Emma, et al. LCLS FAC May 13, (3.3 days) May 24, :01 to May 27 09:00 weekend run at 0.25 nC, with no tuning Emittance Near End of Linac Over Long Weekend  (  x  y ) 1/2 = 1.04  m Saturates at 1.5 Å in 100 m (assuming BBA, etc)

Paul Emma, et al. LCLS FAC May 13, Now measure BPM jitter both with transverse RF OFF, and then ON (at constant phase)  t  ±0.6 ps slope =  2.34 mm/deg 9  m rms 110  m rms TCAV ON TCAV OFF BPM Y Position (mm) Measuring Bunch Arrival Time Jitter eeee V(t)V(t)V(t)V(t) S-band (2856 MHz) BPM Timing Jitter (w.r.t. RF) = (110  m)/(2.34 mm/deg) = deg  46 fsec rms Q = 0.25 nC

Paul Emma, et al. LCLS FAC May 13, LCLS Installation and Commissioning Time-Line LTU/Und/Dump Install Re-commission Inj/BC2 to SL2 LTU/UndComm. First Light in FEE PEP-II run ends FEE/NEH Install PPS Cert. LTU/Dump FEH Install CD-4 (7/31/2010) X-Rays in NEH First Light in FEH NEH Operations/ Commissioning JJFFMMAAMMJJJJAASSDDJJFFMMAAMMJJJJAASSOONNDDJJFFMMAAMMJJJJ ON A A Down PPS A A M M now Linac/BC2 Commissioning FEEComm. May 2, 2008 FEH Hutch BO Und. Seg. Install

Paul Emma, et al. LCLS FAC May 13, LTU/Undulator/FEE/FEL Commissioning See break-out presentations: LTU & Undulator Commissioning Plans (H.-D. Nuhn) FEL/FEE Overview Commissioning Plans (H. Tompkins) FEE Diagnostics & Commissioning (R. Bionta) See break-out presentations: LTU & Undulator Commissioning Plans (H.-D. Nuhn) FEL/FEE Overview Commissioning Plans (H. Tompkins) FEE Diagnostics & Commissioning (R. Bionta) H. Tompkins

Paul Emma, et al. LCLS FAC May 13, Problems/Issues End-of-linac x-emittance difficult to minimize and maintain, especially at 1 nC (CSR + micro-bunching?) Some wire-scanner vibration issues (~fixed in April ‘08) Most OTR screens are unusable due to COTR (laser heater should solve this in FY2009) Most linac BPMs need upgrade – 22 of 83 done with great resolution improvement (50  5  m - more on AIP List) BC2 bunch length monitor noisy or real jitter – (need beam synchronous acquisition for RF & BPMs or  -bunching?) RF phase jumps/drifts not uncommon – sometimes beyond feedback control range

Paul Emma, et al. LCLS FAC May 13, Summary Drive laser very reliable – performs well (great team) Injector in very good shape – runs well after setup Many measurements made – getting to know machine Emittances at end of linac difficult to tune, but nice results are possible with effort (  y is done!) Very encouraging results: e  beam supports 1.5-Å SASE We look forward to next phase (LTU, undulator, FEL, …) – preparations have begun (plans, software, checkout, …) Thanks to dedicated Commissioning Team + Controls, RF, Engineering, Operations, ASD, Maintenance, etc

Paul Emma, et al. LCLS FAC May 13, DONE

Paul Emma, et al. LCLS FAC May 13, BC2 Emittance Growth vs. Peak Current Q = 0.5 nC  x near end of linac (µm) BC2 Peak Current Feedback Set-Point (A)

Paul Emma, et al. LCLS FAC May 13, COTR After BC2 OTR screen just after BC2 with BC2 screen inserted (smoothes  -bunching) with BC2 screen OUT (  -bunching present – COTR!) OTR22OTR22

Paul Emma, et al. LCLS FAC May 13,  -Bunching in BC2 May Blow up X-Emittance OTR screen in BC2 OTR21  x,y measured with wire-scanners 320-m downbeam of BC2  x  y

Paul Emma, et al. LCLS FAC May 13, FY2009 Commissioning Activities Pre-Beam Checkout (Nov-Dec ‘08) – check-list in prep. Re-establish injector & linac beam quality (Nov-Dec ‘08) – have experience First LTU Commissioning with beam (Jan-Mar ‘09) – lots of time ‘Undulator’/Dump Comm. without undulators (Jan-Mar ‘09) Calibrate & commission: RF BPMs, Loss Monitors, BFWs, ADS BBA algorithm testing (without segments) Install undulator segments (Mar ’09, two wks) – optimize linac again First Undulator Segments Commissioning (Mar-Apr ‘09) Care with first transport to minimize radiation on segments Full alignment process (BBA, BFW’s) Commission FEE Diagnostics (Apr-Jun ‘09) Direct Imager, Calorimeter, Slit, Solid Attenuator, Gas Attenuator, Gas Detector Beam-Based K Measurement Components Optimization & characterization of SASE (Jun-Jul ‘09) Optimize linac beam quality (adjust compression, emittance tuning, BBA) Measure gain length