Javier A. Sevilla MMF FAC Review October 27, 2005 1 Magnetic Measuring Facility (MMF) Outline Summary of Facility Requirements.

Slides:



Advertisements
Similar presentations
David Saenz Space Conversion to June 17, Space Conversion to Offices Scope Schedule Budget.
Advertisements

Rodd Pope, SLAC Undulator System October 12-13, 2006 FAC Meeting 1 Undulator System Assembly Plans Rodd Pope, SLAC.
David Saenz FAC CF April 20, 06 Meeting of the LCLS Facilities Advisory Committee LCLS Conventional Facilities D. Saenz.
Richard M. Boyce FAC Review – Accelerator Installation October 29-31, Installation – Accelerator Systems Installation Planning.
Jo Beth Folger MMF Site and October 14, Conventional Facilities – MMF Presentation Outline Facility Design.
David Saenz FAC CF April 07, 2005 Conventional Facilities Overview SLAC Site Plan Systems Description Construction Schedule.
Javier A. Sevilla Interface & Configuration FAC Review April 16, Interface and Configuration Management Outline CF.
Michael Scharfenstein FAC June 17, ES&H Status of Construction and Technical System Installations Michael Scharfenstein.
David Saenz Facility Advisory October 30, 2007 CONVENTIONAL FACILITES MANAGEMENT.
1 David Saenz 1 Hutch Construction in FEH June 08, 2009 Hutch Construction in Far Experimental Hall David Saenz – Project Manager.
Richard Hislop FAC April 20-21, 2006 CONSTRUCTION SAFETY Richard Hislop LCLS Construction Safety Coordinator.
David Saenz Far Experimental Hall - June 17, Far Experimental Hall - Hutches Scope Budget Schedule.
Michael Scharfenstein FAC October LCLS Environment, Safety & Health Michael Scharfenstein ES&H Coordinator.
Mark Reichanadter LCLS FAC April 20-21, 2006 Meeting of the LCLS Facilities Advisory Committee LCLS Project Management M.
David Saenz FAC CF Oct 12-13, 2004 Conventional Facilities Overview SLAC Site Plan Systems Description Construction Schedule.
Jess Albino Facility Advisory October 29, 2007 FACILITY ADVISORY COMMITTEE PLENARY CONVENTIONAL FACILITIES UPDATE October.
David Saenz CF Oct 30, CF MEP Commissioning.
Robert Ruland Installation Alignment -Magnetic Measurements – Fiducialization April 7-8, 2005 FAC Meeting 1 Installation Alignment,
Robert Ruland MMF Introduction, Schedule, Budget October 14, 2004 MMF Review 1 MMF Introduction, Schedule, Budget Robert Ruland.
Stephen Milton Undulator System 20 April, 2006 LCLS Undulator System Update S. Milton, ANL FAC, April 20 th, 2006.
Rodd Pope, SLAC Undulator System April 20-21, 2006 FAC Meeting 1 Undulator System Assembly Plans Rodd Pope, SLAC In collaboration.
Jess Albino Session 5 Conventional November 11, Facility Advisory Committee LINAC Coherent Light Source Project.
Jo Beth Folger FAC - CF Breakout – Sector April 8, Sector 20 Project Overview Sector 20 Site Plan Description Schedule.
Bob Law FAC Oct 24, Sector 20 Project Overview Sector 20 Site Plan Description Organizational Chart Schedule Cost.
David Saenz FAC November 11, 2008 SLAC National Accelerator Laboratory 1 Far Experimental Hutches David Saenz Project Manager.
Robert Ruland MMF Layout, Workflow October 14, 2004 MMF Review 1 MMF Layout, Workflow Robert Ruland Magnetic Measurements Facility.
Mike Scharfenstein FAC Review - November 11, 2008 SLAC National Accelerator Laboratory 1 Environment Safety & Health Status.
Michael Scharfenstein FAC April 16, 2007 LCLS CONSTRUCTION SAFETY Michael Scharfenstein.
Mike Scharfenstein CF Breakout - 12 November 2008 SLAC National Accelerator Laboratory 1 ES&H Status of Construction and Technical.
Jose Chan FAC Review- LTU-DUMP Installation Status & 11/11/08 1 LTU-Dump Installation Status & Schedule.
Javier A. Sevilla April 5, Magnetic Measuring Facility (MMF) Outline Organizational Chart Facility Design Criteria,
Richard Hislop FAC October Construction Safety Richard Hislop.
M. Scharfenstein - ES&H Coordinator 8 June 2009
Michael P. Andrews NuMI Shutdown & Facility Coordinator LBNE Project ESH Manager AD ESH Special Projects Coordinator.
1 BROOKHAVEN SCIENCE ASSOCIATES LOB - Ring Building Construction Coordination Michael P. Bromfield Construction Engineer NSLS-II Conventional Facilities.
1 BROOKHAVEN SCIENCE ASSOCIATES Construction Management Status Steve Sawch Assistant Director for Construction Management NSLS-II Conventional Facilities.
1 BROOKHAVEN SCIENCE ASSOCIATES Conventional Facilities & Beam Stability Marty Fallier Director for Conventional Facilities NSLS-II Beam Stability Workshop.
1 BROOKHAVEN SCIENCE ASSOCIATES Ring Building Construction Status Steve Sawch Assistant Director for Construction Management NSLS-II Conventional Facilities.
Javier A. Sevilla Interface & Configuration FAC Review October 12, Interface and Configuration Management Outline.
Wilsdorf Hall Materials Science Engineering & Nanotechnology Building University of Virginia Leaha Martynuska Construction Management Option Senior Thesis.
David Saenz FAC Review CF Design, Cost and Schedule Oct 27, 2005 CF Overview & Status Design Status CMGC Status Latest.
1 BROOKHAVEN SCIENCE ASSOCIATES NSLS – II CFAC Review Conventional Facilities Method of Accomplishment Marty Fallier Director for Conventional Facilities.
1 BROOKHAVEN SCIENCE ASSOCIATES Conventional Facilities Steve Dierker Director, NSLS-II Conventional Facilities Division NSLS-II User Workshop July 17,
David Saenz Readiness for Oct 12, 2006 # Meeting of the LCLS Facilities Advisory Committee LCLS Conventional Facilities.
David Saenz EIR Review Oct 9-11, Conventional Facilities (CF) WBS 1.9 ETC and Methodology David Saenz CF Systems Manager.
1 BROOKHAVEN SCIENCE ASSOCIATES CF Coordination with Technical Divisions Ove Dyling Conventional Facilities Advisory Committee Review October 5-6, 2010.
1 BROOKHAVEN SCIENCE ASSOCIATES NSLS – II CFAC Review Conventional Facilities Overview Scope & Schedule Marty Fallier Director for Conventional Facilities.
1 BROOKHAVEN SCIENCE ASSOCIATES Conventional Facilities Schedule Steve Sawch Asst. Director, Construction Management CF Advisory Committee Review of the.
CF Organization & Schedule
Meeting of the LCLS Facilities Advisory Committee
Sector 20 Project Overview
Far Experimental Hall Hutches Civil Construction
Far Experimental Hall Hutches Civil Construction
CONVENTIONAL FACILITIES STATUS
M. Scharfenstein - ES&H Coordinator 14 May 2009
Conventional Facilities (WBS 1
Details supporting the increase
Undulator Tuning Status Heinz-Dieter Nuhn, SLAC / LCLS for Zack Wolf, Yurii Levashov, Achim Weidemann, Seva Kaplounenko, Scott Jansson, Ralph Colon, Dave.
Conventional Facilities WBS 1.9
Integrated Safety and Environmental Management
CONVENTIONAL FACILITIES
Richard Hislop Construction Safety Coordinator
LCLS MMF Facility Status
Department Of Energy Review Linac Coherent Light Source Project
Phase 1 Statement of Work Preconstruction “Plan The Work”
Javier A. Sevilla Conventional Facilities
Physics Requirements for Conventional Facilities
CF Scope, Management & Organization
CMGC Overview SLAC Site Plan Systems Description Construction Schedule
PROJECT SAFETY Richard Hislop.
Presentation transcript:

Javier A. Sevilla MMF FAC Review October 27, Magnetic Measuring Facility (MMF) Outline Summary of Facility Requirements Team Facility Layout Pre-Construction Activities Construction activities and Status to Date Safety Program Budget and Schedule Technical Challenges (Risks) Management Challenges Path Forward

Javier A. Sevilla MMF FAC Review October 27, Site Location Building 081-MMF LCLS Undulator Hall BTH PEP Ring Road NORTH LINAC B48-ROB 280

Javier A. Sevilla MMF FAC Review October 27, Facility Design Requirements Technical Note LCLS-TN-041-Z Space Requirements Environmental Stability (3 areas) Space Temperature: ± 0.1 °C short term may go up to 0.3°C if < 1Hr Relative Humidity: 45%± 5% Other areas: ±1°C and ±2.5°C Vibration <0.5 microns-MM Lab Utility Requirements Electrical (new 800A, 12.47KV feeder MMF  Bldg Upgrade) Other (compressed air and small chiller for User’s equipment)

Javier A. Sevilla MMF FAC Review October 27, MMF Facility Uses Undulator magnet tuning – 2 magnet measuring machine test stands Aligned with same orientation to Earth’s magnetic field as LCLS Undulator Hall. Undulator fiducialization – large coordinate measuring machine Cradle assembly area Magnet storage/temperature acclimation Work desks in lab and office space for 2 employees

Javier A. Sevilla MMF FAC Review October 27, Resultant Facility Criteria ~4,800 sq. ft. floor space (inc. ~3,000 laboratory space, mech Rm) + mezzanine 1,400 sf (HVAC & Electrical) Locate within an existing building to aid in temperature control Adequate ceiling height for overhead cranes Accessible for magnet delivery using trucks and forklifts Electrical service – 800A, 480v, 3 Ø (New Feeder to building)

Javier A. Sevilla MMF FAC Review October 27, Teamwork Future Users Magnetic Measurement Facility (MMF) Robert Ruland – Alignment Mgr Zachary Wolf – User Conventional Facilities-WBS 1.09 David Saenz – CF Sys Manager Jim Welch – CF Systems Physicist Javier A. Sevilla-CF Project/CAM K.Chan, K. Yang-CEF UTR Richard Hislop & M. Scharfenstein– Safety & ESH Anita Malahowski –Cost/Schedule General Contractor and Subs Building Occupants (Stores, Transportation, Receiving, Property Jacobs (A&E Title III) GC & Contractors DOE SSO

Javier A. Sevilla MMF FAC Review October 27, Floor Space Allocation-Bldg. 081 SHIPPING & RECEIVING EQUIPMENT REPAIR VEHICLE SHOP Offices (N) MCC-B081 Front Rear (N) Fire Alarm Panel AP Receiving PC Transportation Stores MMF

Javier A. Sevilla MMF FAC Review October 27, Building 081 Site Plan Before Now Haz Mat

Javier A. Sevilla MMF FAC Review October 27, MMF Ground Floor Plan Coordinate Measuring Area ~ 1,000 ft. sq. Cradle Assembly Area ~325 ft. sq. Magnet Loading and Storage ~850 ft. sq. ± 2.5°C ± 1°C, 45% RH ±5 Magnet Measuring Lab ~1,800 ft. sq. ± 0.1°C, 45%RH ±5 Rear Mechanical Room ~256 ft. sq.

Javier A. Sevilla MMF FAC Review October 27, Mezzanine Floor Plan Mezzanine for Mechanical/Electrical Equipment in Conditioned space 4 Air handling Units 1 Motor Control Center, X-trmr, Panels, 1 small Compressor HVAC Control Panel Equipment: Rear MCC-MMF (on-site)

Javier A. Sevilla MMF FAC Review October 27, NORTH CMM Test stands Demising Wall

Javier A. Sevilla MMF FAC Review October 27, Pre-Construction Activities Selection of General Contractor based on specific criteria Review of subcontractors qualifications (electrical, controls and mechanical) Pre-Construction Meeting Review of Contractor Safety Plan Site mobilization Order LLP equipment

Javier A. Sevilla MMF FAC Review October 27, General Contractor and Subcontractors Team Project Manager: Steve Winslow Project Superintendent: Gary Meadows Project Engineer: Kevin Ng Safety Coordinator: Craig Pancoast President: Eric Raff Subs: AIM AMS ASI SJS North Star Blue water

Javier A. Sevilla MMF FAC Review October 27, Construction Progress New Demising WallDemolition Work

Javier A. Sevilla MMF FAC Review October 27, Work Completed and On-Going Demolition of (e) offices Asbestos Abatement New demising wall and others walls Excavation New concrete footings New fence Wet Sprinkler System Steel Fabrication MEP Layout

Javier A. Sevilla MMF FAC Review October 27, Work Progress Footings for Test Stands No. 1 & 2 Footings for Test Stand No. 1

Javier A. Sevilla MMF FAC Review October 27, Safety Program Alignment of Goals and Objectives LCLS Environmental, Safety ad Health Plan Contractor’s Site Specific Safety Plan PM, CEF and LCLS UTR’s ES&H SME Building Occupants ZERO ACCIDENTS DOE SO

Javier A. Sevilla MMF FAC Review October 27, Budget & Schedule Title III Construction $2.5M (excludes: fire alarm building upgrade B081, roof repair and some stores relocation costs) Electrical Feeder (12.47KV, Transformer and MCC): 460K$ Total TPC: 3.0 M$ Bidding and Award First bids due May 5, 2005 Re-bid combined with S20: July 7, Awarded: July 28, 2005 Kick Off meeting: August 22, 2005 Mobilization on site: August 29, 2005 Beneficial Occupancy, LCLS L4 February,

Javier A. Sevilla MMF FAC Review October 27, Critical Path Schedule L4: BO Feb

Javier A. Sevilla MMF FAC Review October 27, Risks Internal technical: Not achieving the Temperature and Stability requirements Plan: Design reviews, constructability and commissioning plan Internal non-technical: Delays in the BO date Plan: Use Good planning and effective Project Management approach, and select only “qualified” contractors including subs Internal non-technical: Safety accidents Plan: Strict implementation of Safety Plans and Procedures

Javier A. Sevilla MMF FAC Review October 27, Management Challenges Schedule and Resources Support form other SLAC’s Departments (ES&H, CEF) Prioritization of activities On-Going implementation of new Policies at SLAC (UTR responsibilities, Authority and Oversight)

Javier A. Sevilla MMF FAC Review October 27, Path Forward Continue partnership with ALL stakeholders Continue to enforce Safety Regulations to All Sub- Contractors Strict implementation and compliance of drawings and technical specifications to meet User’s requirements Continue Construction towards Testing and Commissioning Strict Schedule and Cost Controls Execute an integrated verification of: operational performance, testing, complete documentation and training of SLAC personnel, which will operate and maintain this Facility.

Javier A. Sevilla MMF FAC Review October 27, Magnetic Measuring Facility (MMF) SUMMARY Summary of Facility Requirements Team Facility Layout Pre-Construction activities to date Construction activities and Status to Date Safety Program Budget and Schedule Technical Challenges (Risks) Management Challenges Path Forward Thanks !

Javier A. Sevilla MMF FAC Review October 27, END